TxDOT contract A00180424 bid tabulation
Rehabilitate Existing Roadway, SH 255 (FM 1472 INTERSECTION to 0.48 MILES EAST OF FM 3338 INT). Let by Texas DOT on July 2, 2025, Webb, Laredo District. 3 bids received; low bid $26,042,350 by CK Newberry, LLC, -15% against the engineer's estimate of $30,716,267.
- Owner
- Texas DOT
- Letting
- 02 JUL 2025
- Pay items
- 118
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | CK Newberry, LLC | $26,042,350 | Low | -15% |
| 2 | Anderson Columbia Co., Inc. | $27,693,592 | +6.0% | -10% |
| 3 | Texas Materials Group, Inc. | $28,988,807 | +11% | -6.0% |
Engineer's estimate: $30,716,267.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. CK Newberry, LLC | 2. Anderson Columbia Co., Inc. | 3. Texas Materials Group, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 96 | $2,500.00 | $500.00 | $1,000.00 | $1,000.00 |
| 2 | Removing concrete (mowstrip) (104-7003) | SY | 20 | $27.50 | $50.00 | $70.00 | $42.00 |
| 3 | Removing concrete (curb & gutter) (104-7017) | LF | 5,880 | $14.00 | $7.00 | $4.00 | $8.30 |
| 4 | Remove (20") TRT/untrt base & asphalt pavement (105-7099) | CY | 2,481 | $55.00 | $20.00 | $16.00 | $28.00 |
| 5 | Excavation (roadway) (110-7001) | CY | 8,982.40 | $17.00 | $10.00 | $20.00 | $20.55 |
| 6 | Embankment (final)(OC)(type C) (132-7005) | CY | 10,026.50 | $23.33 | $17.00 | $14.00 | $27.00 |
| 7 | Backfill (type B) (134-7002) | STA | 96 | $115.00 | $500.00 | $220.00 | $150.00 |
| 8 | Drill seed (permanent_rural_clay) (164-7042) | ACRE | 82.30 | $567.50 | $550.00 | $1,400.00 | $1,200.00 |
| 9 | Drill seed (temporary_warm) (164-7045) | ACRE | 82.30 | $567.50 | $550.00 | $500.00 | $400.00 |
| 10 | FL BS (roadway del)(type E GR 1-2)(final pos) (247-7275) | CY | 3,889 | $120.00 | $70.00 | $64.00 | $72.00 |
| 11 | Cement (275-7001) | TON | 130 | $293.00 | $200.00 | $265.00 | $230.00 |
| 12 | Cement TRT (new base)(6") (275-7010) | SY | 24,414 | $6.50 | $1.50 | $3.50 | $2.45 |
| 13 | Cement (291-7001) | TON | 1,392 | $300.00 | $200.00 | $262.00 | $230.00 |
| 14 | Asphalt binder (PG 64-22) (291-7003) | TON | 3,479 | $600.00 | $550.00 | $620.00 | $689.00 |
| 15 | Foam asphalt TRT (existing material) (12") (291-7011) | SY | 241,153 | $6.50 | $3.00 | $5.00 | $5.85 |
| 16 | Prime coat (RC-250) (310-7006) | GAL | 50,440 | $6.00 | $4.25 | $6.00 | $4.55 |
| 17 | Aggregate (type-PB, GR-5)(sac-B) (316-7214) | CY | 1,802 | $110.00 | $115.00 | $180.00 | $189.00 |
| 18 | D-GR HMA type-B sac-B PG70-22 (341-7007) | TON | 71,079 | $120.00 | $105.00 | $104.00 | $110.00 |
| 19 | Stone-MTRX-asphalt SMA-C sac-A PG76-22 (346-7001) | TON | 35,344 | $150.00 | $135.00 | $168.00 | $169.00 |
| 20 | Planing asphalt concrete pavement(4") (354-7053) | SY | 233,897 | $4.50 | $1.25 | $2.40 | $2.15 |
| 21 | Plan asphalt concrete pavement (4"-7.5") (354-7090) | SY | 3,912 | $5.00 | $4.50 | $5.00 | $6.30 |
| 22 | Concrete pavement (CRCP) (12") (360-7006) | SY | 24,735 | $110.00 | $125.00 | $120.00 | $116.00 |
| 23 | Flowable backfill (401-7001) | CY | 209.20 | $265.00 | $350.00 | $150.00 | $145.00 |
| 24 | Temporary special shoring (403-7001) | SF | 4,644 | $25.00 | $20.00 | $14.00 | $13.00 |
| 25 | Drilled shaft (36 in) (416-7006) | LF | 52.80 | $482.00 | $425.00 | $440.00 | $400.00 |
| 26 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 10 | $358.00 | $300.00 | $270.00 | $300.00 |
| 27 | Riprap (concrete)(4 in) (432-7001) | CY | 412 | $707.00 | $500.00 | $520.00 | $485.00 |
| 28 | Riprap (concrete)(5 in) (432-7002) | CY | 141 | $650.00 | $550.00 | $620.00 | $515.00 |
| 29 | Riprap (mow strip)(4 in) (432-7013) | CY | 92 | $800.00 | $700.00 | $680.00 | $495.00 |
| 30 | RC pipe (CL III)(18 in) (464-7003) | LF | 100 | $117.50 | $100.00 | $110.00 | $100.00 |
| 31 | RC pipe (CL III)(24 in) (464-7005) | LF | 100 | $102.00 | $125.00 | $144.00 | $132.00 |
| 32 | Inlet (complete)(pod)(SFG)(3FTX3FT) (465-7051) | EACH | 6 | $5,500.00 | $7,000.00 | $4,000.00 | $3,750.00 |
| 33 | Set (type I)(S= 8 FT)(HW= 5 FT)(4:1)(C) (467-7184) | EACH | 16 | $12,000 | $12,000 | $15,000 | $14,750 |
| 34 | Set (type I)(S= 8 FT)(HW= 6 FT)(4:1)(C) (467-7188) | EACH | 26 | $16,000 | $8,000.00 | $18,000 | $16,750 |
| 35 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 1 | $1,155.00 | $4,000.00 | $1,500.00 | $1,381.00 |
| 36 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 1 | $2,560.00 | $5,000.00 | $1,600.00 | $1,392.00 |
| 37 | Adjusting inlets (479-7002) | EACH | 6 | $500.00 | $2,500.00 | $1,000.00 | $1,000.00 |
| 38 | Adjusting manholes (cap) (479-7005) | EACH | 2 | $3,000.00 | $3,000.00 | $2,500.00 | $2,500.00 |
| 39 | Clean existing culverts (480-7001) | EACH | 10 | $1,500.00 | $3,000.00 | $4,000.00 | $3,500.00 |
| 40 | Removing structure (inlet) (496-7002) | EACH | 12 | $1,095.00 | $1,500.00 | $2,000.00 | $1,850.00 |
| 41 | Removing structure (wingwall) (496-7005) | EACH | 13 | $3,500.00 | $2,000.00 | $2,500.00 | $2,250.00 |
| 42 | Removing structure (pipe) (496-7007) | LF | 20 | $30.00 | $50.00 | $46.00 | $43.00 |
| 43 | Mobilization (500-7001) | LS | 1 | $2,674,908 | $2,500,000 | $1,380,000 | $2,100,000 |
| 44 | Barricades, signs and traffic handling (502-7001) | MO | 24 | $4,000.00 | $10,000 | $2,500.00 | $8,200.00 |
| 45 | Portable changeable message sign (503-7002) | EACH | 2 | $11,000 | $25,000 | $34,000 | $20,000 |
| 46 | TMA (stationary) (505-7001) | DAY | 453 | $270.00 | $100.00 | $280.00 | $165.00 |
| 47 | TMA (mobile operation) (505-7002) | HR | 136 | $205.00 | $100.00 | $70.00 | $60.00 |
| 48 | Rock filter dams (install) (type 3) (506-7003) | LF | 873 | $50.00 | $120.00 | $160.00 | $150.00 |
| 49 | Rock filter dams (remove) (506-7011) | LF | 873 | $25.00 | $22.00 | $16.00 | $15.00 |
| 50 | Construction exits (install) (type 1) (506-7020) | SY | 156 | $20.00 | $20.00 | $50.00 | $45.00 |
| 51 | Construction exits (remove) (506-7024) | SY | 156 | $20.00 | $10.00 | $17.00 | $15.00 |
| 52 | Backhoe work (erosion & sediment control) (506-7030) | HR | 56 | $100.00 | $75.00 | $170.00 | $146.00 |
| 53 | Temporary sediment control fence (install) (506-7039) | LF | 2,242 | $3.00 | $7.00 | $5.00 | $4.00 |
| 54 | Temporary sediment control fence (remove) (506-7041) | LF | 2,242 | $3.00 | $2.00 | $2.00 | $1.50 |
| 55 | One-way traffic control (pilot car) (510-7002) | HR | 944 | $105.00 | $150.00 | $180.00 | $153.00 |
| 56 | One-way traffic control (port traffic signal) (510-7003) | MO | 7 | $6,504.00 | $3,500.00 | $7,000.00 | $5,100.00 |
| 57 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 9,120 | $60.00 | $35.00 | $28.00 | $37.00 |
| 58 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 5,160 | $15.00 | $18.00 | $26.00 | $24.50 |
| 59 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 9,120 | $12.50 | $28.00 | $17.00 | $24.00 |
| 60 | Concrete curb & gutter (type II) (529-7009) | LF | 3,787 | $40.00 | $35.00 | $46.00 | $42.50 |
| 61 | Driveways (ACP) (530-7010) | SY | 1,383 | $66.00 | $80.00 | $115.00 | $108.00 |
| 62 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 114,189 | $0.15 | $0.10 | $0.15 | $0.09 |
| 63 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 13,200 | $0.45 | $0.25 | $0.15 | $0.17 |
| 64 | Metal W-beam guard fence (timber post) (540-7001) | LF | 925 | $30.00 | $24.00 | $25.00 | $26.50 |
| 65 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 16 | $2,500.00 | $1,900.00 | $3,160.00 | $2,200.00 |
| 66 | Downstream anchor terminal section (540-7015) | EACH | 3 | $1,750.00 | $1,400.00 | $1,500.00 | $1,250.00 |
| 67 | Remove metal beam guard fence (542-7001) | LF | 850 | $3.50 | $3.00 | $3.30 | $3.00 |
| 68 | Remove terminal anchor section (542-7002) | EACH | 3 | $250.00 | $275.00 | $300.00 | $220.00 |
| 69 | Guardrail end treatment (install) (544-7001) | EACH | 19 | $2,650.00 | $3,300.00 | $3,610.00 | $3,050.00 |
| 70 | Guardrail end treatment (remove) (544-7003) | EACH | 19 | $325.00 | $300.00 | $320.00 | $335.00 |
| 71 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 60 | $1,400.00 | $700.00 | $1,020.00 | $1,100.00 |
| 72 | Crash cushion attenuator (remove) (545-7004) | EACH | 6 | $1,000.00 | $600.00 | $820.00 | $700.00 |
| 73 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 6 | $14,000 | $10,000 | $7,080.00 | $8,300.00 |
| 74 | Relocate RD IL asm (trans-base) (610-7004) | EACH | 1 | $3,085.00 | $4,500.00 | $4,940.00 | $4,500.00 |
| 75 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 357 | $22.00 | $21.00 | $20.00 | $21.00 |
| 76 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 245 | $25.00 | $50.00 | $6.50 | $50.00 |
| 77 | Electrical conductor (no.6) bare (620-7009) | LF | 122 | $2.63 | $2.00 | $2.20 | $1.85 |
| 78 | Electrical conductor (no.6) insulated (620-7010) | LF | 244 | $2.63 | $2.25 | $3.00 | $2.20 |
| 79 | Tray cable (3 conductor) (12 AWG) (621-7002) | LF | 1,040 | $5.75 | $2.75 | $3.30 | $2.65 |
| 80 | Ground box type A (122311)W/apron (624-7002) | EACH | 4 | $2,005.00 | $1,400.00 | $1,400.00 | $1,300.00 |
| 81 | Ground box type C (162911)W/apron (624-7006) | EACH | 3 | $2,166.00 | $1,600.00 | $1,460.00 | $1,500.00 |
| 82 | Remove ground box (624-7013) | EACH | 3 | $692.00 | $450.00 | $550.00 | $450.00 |
| 83 | Relocate electrical services (628-7001) | EACH | 1 | $3,800.00 | $3,000.00 | $2,760.00 | $2,800.00 |
| 84 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 110 | $600.00 | $700.00 | $845.00 | $675.00 |
| 85 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 15 | $950.00 | $775.00 | $1,030.00 | $775.00 |
| 86 | Remove SM RD SN sup&AM (644-7073) | EACH | 118 | $118.00 | $100.00 | $98.00 | $100.00 |
| 87 | Remove overhd sign sup (650-7193) | EACH | 2 | $9,148.00 | $7,500.00 | $8,170.00 | $13,000 |
| 88 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 43 | $22.00 | $32.00 | $49.00 | $32.00 |
| 89 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 24 | $45.00 | $75.00 | $98.00 | $75.00 |
| 90 | Remove delin & object marker assms (658-7078) | EACH | 43 | $15.50 | $15.00 | $27.00 | $15.00 |
| 91 | Work zone pavement marking removing (traffic BTN) type W (662-7058) | LF | 8,448 | $1.20 | $1.00 | $1.00 | $0.80 |
| 92 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 5,606 | $0.50 | $1.00 | $2.00 | $1.60 |
| 93 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 4,138 | $2.25 | $1.00 | $2.00 | $1.60 |
| 94 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 1,382 | $2.00 | $1.00 | $1.00 | $0.96 |
| 95 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 2,692 | $2.50 | $1.00 | $1.00 | $0.96 |
| 96 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 144 | $9.50 | $16.00 | $18.00 | $16.00 |
| 97 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 14 | $198.00 | $175.00 | $190.00 | $175.00 |
| 98 | Reflectorized pavement marking type I(W)(uturn arrow)(100MIL) (666-7051) | EACH | 6 | $215.00 | $325.00 | $350.00 | $325.00 |
| 99 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 20 | $291.00 | $250.00 | $270.00 | $250.00 |
| 100 | Pavement sler 6" (666-7347) | LF | 204,614 | $0.75 | $0.25 | $0.30 | $0.26 |
| 101 | Pavement sler 24" (666-7352) | LF | 144 | $1.65 | $1.10 | $1.20 | $1.10 |
| 102 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 9,241 | $0.65 | $0.90 | $1.00 | $0.88 |
| 103 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 84,727 | $0.50 | $0.65 | $0.70 | $0.63 |
| 104 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 83,580 | $0.50 | $0.65 | $0.70 | $0.63 |
| 105 | Reflectorized pavement marker type I-C (672-7002) | EACH | 762 | $5.50 | $7.50 | $8.00 | $7.50 |
| 106 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,630 | $4.70 | $5.50 | $6.00 | $5.50 |
| 107 | Eliminating existing PM & markers (4") (677-7001) | LF | 12,444 | $0.60 | $1.00 | $0.30 | $0.25 |
| 108 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 5 | $92.00 | $35.00 | $38.00 | $35.00 |
| 109 | Eliminating existing PM & markers (word) (677-7015) | EACH | 4 | $150.00 | $35.00 | $38.00 | $35.00 |
| 110 | Removing traffic signals (680-7004) | EACH | 1 | $5,200.00 | $6,000.00 | $7,030.00 | $7,200.00 |
| 111 | Ins HY traffic signal (DPT sup CNT & cab)(fla) (680-7006) | EACH | 1 | $8,920.00 | $12,500 | $3,600.00 | $12,600 |
| 112 | Traffic signal CBL (type A)(12 AWG)(4 conductor) (684-7009) | LF | 534 | $2.67 | $2.50 | $3.00 | $2.45 |
| 113 | Tree trimming / brush removal (752-7001) | MI | 1.14 | $14,000 | $25,000 | $22,000 | $20,176 |
| 114 | Bonding course (3007-7001) | GAL | 49,175 | $5.00 | $4.00 | $4.70 | $0.10 |
| 115 | Continuous grinding-concrete pavement (3017-7001) | SY | 18,967 | $12.00 | $5.50 | $6.50 | $8.83 |
| 116 | ITS radio(SNGL)(5 GHZ)-I-U (6014-7001) | EACH | 1 | $10,800 | $6,000.00 | $5,400.00 | $5,800.00 |
| 117 | Remove ITS radio (6014-7007) | EACH | 2 | $3,127.00 | $600.00 | $1,050.00 | $580.00 |
| 118 | TMSP radar speed control monitor (6025-7001) | EACH | 2 | $9,500.00 | $5,000.00 | $18,000 | $9,200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 2, 2025. Compiled by Mirage Metrics.