TxDOT contract A00183414 bid tabulation
Bridge Replacement, FM 923 (At Bush Knob Creek to .). Let by Texas DOT on July 2, 2025, Throckmorton, Wichita Falls District. 8 bids received; low bid $728,607 by C & W Southern LLC, +2.9% against the engineer's estimate of $707,817.
- Owner
- Texas DOT
- Letting
- 02 JUL 2025
- Pay items
- 36
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | C & W Southern LLC | $728,607 | Low | +3.0% |
| 2 | Talbert Companies LLC | $737,258 | +1.0% | +4.0% |
| 3 | Hodges and Son Construction Company, Inc. | $747,184 | +3.0% | +6.0% |
| 4 | Skyline Bridge LLC | $751,775 | +3.0% | +6.0% |
| 5 | Blacksmith Ventures LLC | $756,248 | +4.0% | +7.0% |
| 6 | THK Construction LLC | $873,923 | +20% | +23% |
| 7 | Coppell Construction Co., Inc. | $887,640 | +22% | +25% |
| 8 | Earth Builders, L.P. | $1,040,958 | +43% | +47% |
Engineer's estimate: $707,817.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. C & W Southern LLC | 2. Talbert Companies LLC | 3. Hodges and Son Construction Company, Inc. | 4. Skyline Bridge LLC | 5. Blacksmith Ventures LLC | 6. THK Construction LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7005) | LF | 640 | $10.00 | $8.00 | $10.90 | $9.00 | $15.00 | $5.00 | $20.00 |
| 2 | Excavation (roadway & channel) (110-7004) | CY | 291 | $50.00 | $20.00 | $32.70 | $20.00 | $20.00 | $125.00 | $25.00 |
| 3 | Embankment (final)(OC)(type B) (132-7003) | CY | 268 | $35.00 | $20.00 | $32.70 | $20.00 | $60.00 | $35.00 | $25.00 |
| 4 | Drill seed (permanent_rural_sand) (164-7009) | SY | 1,027 | $3.00 | $2.15 | $2.34 | $2.50 | $2.50 | $3.00 | $2.37 |
| 5 | Vegetative watering (168-7001) | TGL | 8.60 | $100.00 | $20.00 | $27.25 | $1.00 | $1.00 | $10.00 | $10.00 |
| 6 | Rework BS metal (type C)(8")(ord comp) (251-7051) | SY | 1,214 | $25.00 | $20.00 | $19.62 | $15.00 | $12.00 | $15.00 | $50.00 |
| 7 | Cement (275-7001) | TON | 24 | $500.00 | $450.00 | $272.50 | $350.00 | $375.00 | $450.00 | $400.00 |
| 8 | Cement TRT (existing material)(8") (275-7003) | SY | 1,652 | $10.00 | $25.00 | $7.63 | $10.00 | $13.50 | $25.00 | $20.00 |
| 9 | Prime coat (MC-30) (310-7004) | GAL | 413 | $10.00 | $15.00 | $30.52 | $20.00 | $50.00 | $6.00 | $50.00 |
| 10 | Cem stabil BKFL (400-7010) | CY | 83 | $275.00 | $350.00 | $272.50 | $300.00 | $350.00 | $75.00 | $350.00 |
| 11 | Drilled shaft (24 in) (416-7004) | LF | 198 | $250.00 | $264.00 | $261.60 | $180.00 | $275.00 | $300.00 | $319.56 |
| 12 | Class C concrete (abutment)(HPC) (420-7013) | CY | 21.60 | $1,500.00 | $1,100.00 | $1,417.00 | $2,000.00 | $1,400.00 | $1,800.00 | $1,100.00 |
| 13 | Reinforced concrete slab (slab beam)(HPC) (422-7008) | SF | 1,606 | $35.00 | $35.00 | $30.52 | $32.00 | $30.00 | $22.00 | $30.00 |
| 14 | Approach slab (422-7013) | CY | 48 | $1,000.00 | $1,020.00 | $872.00 | $900.00 | $900.00 | $1,600.00 | $1,000.00 |
| 15 | Prestressed concrete slab beam (4SB15) (425-7018) | LF | 396 | $275.00 | $315.00 | $212.55 | $260.00 | $285.00 | $215.00 | $272.69 |
| 16 | Riprap (mow strip)(4 in) (432-7013) | CY | 34 | $575.00 | $550.00 | $654.00 | $700.00 | $750.00 | $500.00 | $800.00 |
| 17 | Riprap (stone protection)(18 in) (432-7043) | CY | 303 | $125.00 | $180.00 | $245.25 | $200.00 | $225.00 | $195.00 | $200.00 |
| 18 | Rail (type T631) (450-7020) | LF | 124 | $120.00 | $90.50 | $110.09 | $95.00 | $100.00 | $125.00 | $110.20 |
| 19 | Armor joint (sealed) (454-7003) | LF | 64 | $165.00 | $250.00 | $207.10 | $200.00 | $150.00 | $175.00 | $150.00 |
| 20 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $20,000 | $10,000 | $10,900 | $25,000 | $15,000 | $15,000 | $65,000 |
| 21 | Mobilization (500-7001) | LS | 1 | $60,133 | $60,000 | $75,300 | $60,000 | $50,000 | $100,000 | $80,000 |
| 22 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $7,500.00 | $1,176.00 | $2,180.00 | $6,000.00 | $2,500.00 | $3,000.00 | $1,054.17 |
| 23 | Rock filter dams (install) (type 1) (506-7001) | LF | 120 | $50.00 | $10.00 | $30.52 | $1.00 | $50.00 | $50.00 | $30.80 |
| 24 | Rock filter dams (remove) (506-7011) | LF | 120 | $15.00 | $1.00 | $5.45 | $1.00 | $10.00 | $1.00 | $20.00 |
| 25 | Temporary sediment control fence (install) (506-7039) | LF | 200 | $6.00 | $5.20 | $9.59 | $1.00 | $4.00 | $5.00 | $9.68 |
| 26 | Temporary sediment control fence (remove) (506-7041) | LF | 200 | $2.00 | $2.10 | $3.27 | $1.00 | $1.50 | $1.00 | $3.30 |
| 27 | Metal W-beam guard fence (timber post) (540-7001) | LF | 276 | $28.00 | $24.50 | $32.70 | $26.00 | $29.00 | $35.00 | $26.95 |
| 28 | Remove metal beam guard fence (542-7001) | LF | 300 | $1.00 | $2.00 | $5.45 | $2.00 | $5.00 | $1.00 | $10.00 |
| 29 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $2,500.00 | $3,150.00 | $3,210.05 | $3,100.00 | $3,800.00 | $4,500.00 | $3,300.00 |
| 30 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $500.00 | $200.00 | $218.00 | $500.00 | $500.00 | $1.00 | $500.00 |
| 31 | Install small roadside sign support and assembly tytwt(1)WS(T) (644-7058) | EACH | 2 | $1,000.00 | $500.00 | $763.00 | $1,000.00 | $1,800.00 | $500.00 | $1,500.00 |
| 32 | Relocate SM RD SN sup&AM type TWT (644-7068) | EACH | 1 | $500.00 | $100.00 | $218.00 | $800.00 | $500.00 | $500.00 | $1,500.00 |
| 33 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $200.00 | $250.00 | $109.00 | $50.00 | $200.00 | $1.00 | $250.00 |
| 34 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 10 | $75.00 | $25.00 | $49.05 | $25.00 | $50.00 | $50.00 | $27.50 |
| 35 | D-GR HMA type B PG 64-22 (del) site 1 (8011-7002) | TON | 363 | $95.00 | $150.00 | $218.00 | $205.00 | $165.00 | $105.00 | $165.00 |
| 36 | D-GR HMA type D PG 70-22 (del) site 1 (8011-7146) | TON | 175 | $98.00 | $200.00 | $218.00 | $255.00 | $215.00 | $105.00 | $220.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 2, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.