TxDOT contract A00183477 bid tabulation
Bridge Replacement, ERIE ST (AT LNVA CANAL to STR#201240AA0336002). Let by Texas DOT on June 3, 2026, Jefferson, Beaumont District. 4 bids received; low bid $3,062,119 by R Construction Civil, LLC, -5.0% against the engineer's estimate of $3,223,814.
- Owner
- Texas DOT
- Letting
- 03 JUN 2026
- Pay items
- 79
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | R Construction Civil, LLC | $3,062,119 | Low | -5.0% |
| 2 | Elite Contractors and Equipment LTD | $3,296,888 | +8.0% | +2.0% |
| 3 | Isi Contracting, Inc. | $3,748,801 | +22% | +16% |
| 4 | Ragle Construction, Inc. | $5,118,303 | +67% | +59% |
Engineer's estimate: $3,223,814.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. R Construction Civil, LLC | 2. Elite Contractors and Equipment LTD | 3. Isi Contracting, Inc. | 4. Ragle Construction, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 10 | $12,500 | $3,450.00 | $1,200.00 | $1,808.00 | $43,000 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 51 | $62.00 | $20.00 | $24.00 | $30.00 | |
| 3 | Removing concrete (driveways) (104-7011) | SY | 40 | $15.50 | $78.00 | $20.00 | $29.00 | $49.00 |
| 4 | Removing concrete (sawcut) (104-7020) | LF | 85 | $25.00 | $20.00 | $9.00 | $12.00 | |
| 5 | Remove (0"-10") TRT/untrt base & asphalt pavement (105-7050) | SY | 2,183 | $16.00 | $8.00 | $8.00 | $51.00 | $15.00 |
| 6 | Excavation (roadway) (110-7001) | CY | 1,457 | $15.00 | $33.00 | $15.00 | $38.00 | $50.00 |
| 7 | Embankment (final)(OC)(type C) (132-7005) | CY | 3,773 | $23.20 | $25.00 | $25.00 | $36.00 | $42.00 |
| 8 | Backfill (type A or B) (134-7004) | STA | 10 | $165.00 | $1,200.00 | $500.00 | $2,018.00 | $664.00 |
| 9 | Broadcast seed (temporary_warm) (164-7005) | SY | 3,056.50 | $0.20 | $0.25 | $0.50 | $0.53 | $0.22 |
| 10 | Broadcast seed (temporary_cool) (164-7006) | SY | 2,342 | $0.15 | $0.25 | $0.50 | $0.26 | $0.22 |
| 11 | Hydro mulch seed (permanent_rural_sandy) (164-7017) | SY | 6,113 | $0.52 | $0.60 | $1.00 | $0.46 | $0.55 |
| 12 | Vegetative watering (168-7001) | TGL | 103 | $14.43 | $250.00 | $10.00 | $135.00 | $63.00 |
| 13 | Proof rolling (216-7001) | HR | 30 | $138.00 | $660.00 | $100.00 | $113.00 | $105.00 |
| 14 | FL BS (compacted in place)(type A GR 1-2) (247-7001) | TON | 791 | $83.00 | $83.00 | $26.00 | $78.00 | |
| 15 | FL BS (compacted in place)(type A GR 1-2) (12") (247-7113) | SY | 2,080 | $45.00 | $56.00 | $50.00 | $34.00 | $51.00 |
| 16 | Prime coat (AE-P) (310-7001) | GAL | 575 | $7.45 | $7.00 | $12.00 | $18.00 | $13.00 |
| 17 | D-GR HMA type-C PG76-22 (exempt) (341-7040) | TON | 316 | $125.00 | $290.00 | $275.00 | $297.00 | $350.00 |
| 18 | Tack coat (341-7082) | GAL | 173 | $4.10 | $7.00 | $10.00 | $6.00 | $12.00 |
| 19 | Cem stabil BKFL (400-7010) | CY | 259 | $125.00 | $108.00 | $155.00 | $135.00 | $127.00 |
| 20 | Temporary special shoring (cofferdam) (403-7002) | SF | 6,455 | $55.00 | $35.00 | $30.00 | $32.00 | $60.00 |
| 21 | Prestressed concrete pil (16 in SQ) (409-7001) | LF | 770 | $175.00 | $520.00 | $180.00 | $307.00 | $166.00 |
| 22 | Class C concrete (abutment) (420-7012) | CY | 20.60 | $1,250.00 | $767.00 | $1,750.00 | $2,169.00 | $1,200.00 |
| 23 | Class C concrete (cap) (420-7022) | CY | 15.20 | $1,260.00 | $1,260.00 | $2,300.00 | $2,574.00 | $2,200.00 |
| 24 | CL E concrete (seal slab)(non-reinforced) (420-7070) | CY | 32 | $490.00 | $425.00 | $711.00 | $600.00 | |
| 25 | Reinforced concrete slab (slab beam) (422-7007) | SF | 3,309 | $35.00 | $24.00 | $30.00 | $49.00 | $28.00 |
| 26 | Approach slab (422-7013) | CY | 44.90 | $695.00 | $840.00 | $820.00 | $1,267.00 | $760.00 |
| 27 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 651 | $255.50 | $240.00 | $275.00 | $289.00 | $272.00 |
| 28 | Riprap (concrete)(5 in) (432-7002) | CY | 183 | $625.00 | $700.00 | $500.00 | $490.00 | $696.00 |
| 29 | Riprap (mow strip)(4 in) (432-7013) | CY | 19.60 | $776.00 | $800.00 | $671.00 | $615.00 | |
| 30 | Rail (type T221) (450-7004) | LF | 244 | $183.86 | $300.00 | $150.00 | $262.00 | $120.00 |
| 31 | Armor joint (sealed) (454-7003) | LF | 59 | $155.48 | $125.00 | $180.00 | $107.00 | $153.00 |
| 32 | Concrete box culvert (9 FT X 9 FT) (462-7031) | LF | 168 | $1,300.00 | $1,700.00 | $1,012.00 | $1,611.00 | |
| 33 | RC pipe (CL III)(12 in) (464-7001) | LF | 52 | $64.00 | $95.00 | $94.00 | $85.00 | $118.00 |
| 34 | RC pipe (CL III)(18 in) (464-7003) | LF | 254 | $89.65 | $99.00 | $96.00 | $138.00 | $147.00 |
| 35 | RC pipe (CL III)(24 in) (464-7005) | LF | 124 | $114.31 | $152.00 | $105.00 | $119.00 | $178.00 |
| 36 | RC pipe (CL III)(36 in) (464-7009) | LF | 114 | $175.45 | $214.00 | $168.00 | $175.00 | $225.00 |
| 37 | Set (type I)(S= 9 FT)(HW= 10 FT)(3:1)(C) (467-7220) | EACH | 6 | $20,000 | $20,250 | $20,468 | $21,000 | |
| 38 | Set (type II) (12 in) (RCP) (6: 1) (P) (467-7292) | EACH | 2 | $1,250.00 | $2,300.00 | $1,100.00 | $2,806.00 | $1,927.00 |
| 39 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 5 | $1,288.57 | $2,700.00 | $1,100.00 | $2,900.00 | $2,100.00 |
| 40 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 2 | $2,052.06 | $2,900.00 | $1,500.00 | $3,168.00 | $2,150.00 |
| 41 | Set (type II) (36 in) (RCP) (4: 1) (C) (467-7366) | EACH | 2 | $4,250.00 | $5,125.00 | $3,500.00 | $3,833.00 | $4,000.00 |
| 42 | Set (type II)(18 in)(RCP)(3:1)(P) (467-7467) | EACH | 1 | $2,430.00 | $1,800.00 | $2,764.00 | $2,550.00 | |
| 43 | Removing structure (pipe) (496-7007) | LF | 290 | $27.00 | $32.00 | $20.00 | $45.00 | $24.00 |
| 44 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 2 | $24,000 | $54,000 | $30,000 | $71,986 | $100,000 |
| 45 | Mobilization (500-7001) | LS | 1 | $300,000 | $70,000 | $200,000 | $250,000 | $500,000 |
| 46 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $8,250.00 | $5,000.00 | $5,000.00 | $10,619 | $15,000 |
| 47 | Rock filter dams (install) (type 2) (506-7002) | LF | 226 | $42.71 | $50.00 | $50.00 | $36.81 | $48.00 |
| 48 | Rock filter dams (remove) (506-7011) | LF | 226 | $11.00 | $15.00 | $12.00 | $15.78 | $15.00 |
| 49 | Construction exits (install) (type 1) (506-7020) | SY | 360 | $31.00 | $45.00 | $30.00 | $26.29 | $45.00 |
| 50 | Construction exits (remove) (506-7024) | SY | 360 | $11.90 | $12.00 | $10.00 | $10.52 | $12.00 |
| 51 | Temporary sediment control fence (install) (506-7039) | LF | 2,493 | $4.22 | $5.00 | $4.00 | $2.37 | $5.00 |
| 52 | Temporary sediment control fence (remove) (506-7041) | LF | 2,493 | $1.21 | $1.00 | $1.50 | $0.63 | $1.00 |
| 53 | Constructing detours (type 3) (508-7005) | SY | 1,195 | $200.00 | $45.00 | $150.00 | $136.00 | $135.00 |
| 54 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 220 | $43.50 | $85.00 | $36.00 | $85.00 | $42.00 |
| 55 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 40 | $48.50 | $90.00 | $50.00 | $97.00 | $42.00 |
| 56 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 220 | $11.30 | $13.00 | $12.00 | $18.83 | $20.00 |
| 57 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 40 | $15.00 | $13.00 | $50.00 | $8.16 | $20.00 |
| 58 | Driveways (concrete) (530-7006) | SY | 40 | $115.00 | $140.00 | $180.00 | $324.00 | $135.00 |
| 59 | Driveways (ACP) (530-7010) | SY | 934 | $50.00 | $37.00 | $50.00 | $65.00 | $87.00 |
| 60 | Driveways (base) (530-7015) | SY | 1,124 | $32.50 | $43.00 | $30.00 | $60.00 | $66.00 |
| 61 | Metal W-beam guard fence (timber post) (540-7001) | LF | 725 | $26.45 | $26.00 | $35.00 | $48.00 | $29.95 |
| 62 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $1,950.00 | $1,950.00 | $2,000.00 | $1,696.00 | $2,050.00 |
| 63 | Driveway terminal anchor section (540-7014) | EACH | 2 | $1,300.00 | $1,600.00 | $2,130.00 | $1,340.00 | |
| 64 | Metal W-beam guard fence (special) (540-7017) | LF | 175 | $57.00 | $80.00 | $78.00 | $63.50 | |
| 65 | Guardrail end treatment (install) (544-7001) | EACH | 6 | $3,006.41 | $3,170.00 | $3,400.00 | $3,932.00 | $3,455.00 |
| 66 | Crash cushion attenuator (install)(L)(N)(TL2) (545-7005) | EACH | 4 | $27,000 | $25,000 | $32,500 | $34,889 | $32,150 |
| 67 | Relocate existing mailbox (560-7012) | EACH | 1 | $403.75 | $335.00 | $250.00 | $642.36 | $280.00 |
| 68 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 1 | $650.00 | $1,775.00 | $780.00 | $348.15 | $965.00 |
| 69 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 1 | $1,900.00 | $880.00 | $348.15 | $1,115.00 | |
| 70 | Remove SM RD SN sup&AM (644-7073) | EACH | 3 | $102.14 | $240.00 | $150.00 | $84.49 | $110.00 |
| 71 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 14 | $26.36 | $21.00 | $25.00 | $3.56 | $24.00 |
| 72 | Work zone pavement marking removing (W)4"(solid) (662-7064) | LF | 4,085 | $1.00 | $1.00 | $2.00 | $1.36 | $0.90 |
| 73 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 18 | $6.75 | $17.00 | $16.00 | $7.94 | $16.00 |
| 74 | Work zone pavement marking removing (Y)4"(solid) (662-7097) | LF | 3,200 | $0.80 | $1.00 | $1.50 | $1.60 | $0.90 |
| 75 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 12 | $31.00 | $30.00 | $21.56 | $30.00 | |
| 76 | Post and cable fence (removal) (772-7001) | LF | 380 | $4.30 | $3.00 | $10.00 | $5.52 | $3.00 |
| 77 | Post and cable fence (new installation) (772-7003) | LF | 367 | $12.00 | $15.00 | $40.00 | $26.03 | $18.00 |
| 78 | Temporary detour bridge (4012-7001) | EACH | 1 | $178,000 | $190,000 | $500,000 | $435,303 | $1,000,000 |
| 79 | Residential driveway temporary signal system (6089-7001) | MO | 4 | $17,500 | $12,250 | $20,000 | $17,304 | $11,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 3, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.