TxDOT contract A00184386 bid tabulation
Hazard Elimination & Safety, ODOMS LN (On Odoms Rd., From Baker Potts Rd. to 0.18 Miles East of Altas Palmas Rd.). Let by Texas DOT on August 8, 2025, Cameron, Pharr District. 6 bids received; low bid $978,047 by Earthworks Enterprise, -27% against the engineer's estimate of $1,337,871.
- Owner
- Texas DOT
- Letting
- 08 AUG 2025
- Pay items
- 52
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Earthworks Enterprise | $978,047 | Low | -27% |
| 2 | Rovan Texas, L.L.C. | $1,488,577 | +52% | +11% |
| 3 | Foremost Paving, Inc. | $1,691,067 | +73% | +26% |
| 4 | Artillery L.L.C. | $1,697,893 | +74% | +27% |
| 5 | Ioc Company LLC | $1,927,544 | +97% | +44% |
| 6 | Clore Equipment LLC | $2,056,430 | +110% | +54% |
Engineer's estimate: $1,337,871.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Earthworks Enterprise | 2. Rovan Texas, L.L.C. | 3. Foremost Paving, Inc. | 4. Artillery L.L.C. | 5. Ioc Company LLC | 6. Clore Equipment LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 53 | $1,200.00 | $134.00 | $1,904.80 | $2,500.00 | $1,500.00 | $1,000.00 | $763.62 |
| 2 | Excavation (roadway) (110-7001) | CY | 5,851 | $12.40 | $4.00 | $12.59 | $26.90 | $18.00 | $10.00 | $26.81 |
| 3 | Embankment (final)(DC)(type C) (132-7006) | CY | 802 | $8.87 | $18.00 | $17.44 | $3.00 | $20.00 | $15.00 | $49.61 |
| 4 | Furn & place topsoil (vehicle) (160-7007) | CY | 100 | $50.53 | $74.00 | $63.96 | $62.20 | $30.00 | $40.00 | $62.29 |
| 5 | Hydro mulch seed (permanent_rural_clay) (164-7018) | SY | 15,031 | $0.45 | $0.60 | $0.53 | $0.50 | $1.00 | $0.46 | $0.52 |
| 6 | Hydro mulch seed (temporary_warm) (164-7021) | SY | 15,031 | $0.45 | $0.40 | $0.35 | $0.30 | $1.00 | $0.30 | $0.35 |
| 7 | Vegetative watering (168-7001) | TGL | 96 | $27.25 | $29.00 | $68.55 | $55.50 | $40.00 | $40.00 | $150.75 |
| 8 | FL BS (roadway del)(type E GR 4)(final pos) (247-7277) | CY | 1,415 | $40.96 | $70.00 | $72.79 | $59.30 | $60.00 | $75.00 | $64.54 |
| 9 | Geogrid base reinforcement (type 2) (250-7002) | SY | 16,048 | $1.27 | $1.10 | $1.66 | $2.50 | $3.00 | $3.25 | $2.29 |
| 10 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 49 | $521.86 | $394.00 | $336.06 | $388.60 | $450.00 | $350.00 | $324.49 |
| 11 | Lime TRT (existing material)(6") (260-7006) | SY | 16,048 | $9.27 | $2.17 | $2.42 | $3.50 | $2.00 | $5.00 | $6.21 |
| 12 | Cement (275-7001) | TON | 78 | $205.49 | $226.00 | $201.90 | $254.10 | $200.00 | $200.00 | $230.77 |
| 13 | Cement TRT (existing material & new base)(6") (275-7006) | SY | 16,048 | $2.52 | $1.01 | $3.37 | $6.40 | $3.00 | $5.00 | $13.29 |
| 14 | Prime coat (AE-P) (310-7001) | GAL | 2,686 | $8.83 | $4.50 | $5.60 | $6.20 | $10.00 | $6.00 | $19.82 |
| 15 | D-GR HMA type D sac-B PG64-22 (341-7045) | TON | 1,530 | $110.00 | $118.00 | $124.56 | $152.70 | $200.00 | $210.00 | $135.94 |
| 16 | Struct excavation (special) (400-7005) | CY | 5 | $73.50 | $88.00 | $150.00 | $130.00 | $150.00 | $425.00 | $174.32 |
| 17 | Cut & restoring pavement (400-7006) | SY | 213 | $85.00 | $30.00 | $72.09 | $100.00 | $200.00 | $180.00 | $48.58 |
| 18 | Cem stabil BKFL (400-7010) | CY | 10 | $96.50 | $88.00 | $120.00 | $195.00 | $150.00 | $200.00 | $311.16 |
| 19 | Trench excavation protection (402-7001) | LF | 61 | $2.71 | $4.50 | $10.00 | $1.00 | $20.00 | $5.00 | $116.50 |
| 20 | RC pipe (CL III)(18 in) (464-7003) | LF | 1,219 | $118.23 | $96.00 | $71.37 | $128.00 | $140.00 | $145.13 | $111.66 |
| 21 | RC pipe (CL III)(24 in) (464-7005) | LF | 32 | $97.66 | $110.00 | $83.65 | $140.00 | $150.00 | $272.21 | $171.54 |
| 22 | RC pipe (CL V)(18 in) (464-7032) | LF | 180 | $130.62 | $109.00 | $85.62 | $170.00 | $150.00 | $290.42 | $144.58 |
| 23 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 4 | $5,500.00 | $6,488.05 | $7,000.00 | $7,000.00 | $7,369.63 | $8,801.02 | |
| 24 | Set (type II) (18 in) (RCP) (3: 1) (C) (467-7305) | EACH | 10 | $1,796.91 | $970.00 | $1,684.64 | $1,100.00 | $1,500.00 | $3,074.28 | $3,890.95 |
| 25 | Set (type II) (18 in) (RCP) (6: 1) (C) (467-7307) | EACH | 4 | $1,900.00 | $1,042.00 | $1,415.01 | $1,390.00 | $2,000.00 | $3,667.33 | $3,890.95 |
| 26 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 68 | $1,579.72 | $1,042.00 | $1,415.00 | $1,390.00 | $1,500.00 | $1,883.90 | $2,920.37 |
| 27 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 2 | $2,600.00 | $1,300.00 | $1,784.96 | $1,300.00 | $2,000.00 | $3,930.60 | $4,107.38 |
| 28 | Removing structure (set) (496-7004) | EACH | 2 | $561.88 | $288.00 | $882.78 | $600.00 | $1,000.00 | $750.00 | $949.96 |
| 29 | Removing structure (pipe) (496-7007) | LF | 780 | $13.88 | $20.50 | $23.60 | $20.00 | $10.00 | $40.00 | $31.73 |
| 30 | Mobilization (500-7001) | LS | 1 | $99,102 | $100,000 | $276,568 | $135,000 | $175,000 | $200,000 | $195,361 |
| 31 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $4,000.00 | $2,051.00 | $6,468.74 | $6,009.90 | $6,000.00 | $3,904.95 | $9,742.50 |
| 32 | TMA (stationary) (505-7001) | DAY | 10 | $45.00 | $97.00 | $552.81 | $629.60 | $500.00 | $268.53 | $820.81 |
| 33 | Rock filter dams (install) (type 2) (506-7002) | LF | 13 | $393.00 | $359.33 | $310.00 | $100.00 | $310.00 | $351.81 | |
| 34 | Rock filter dams (remove) (506-7011) | LF | 13 | $213.00 | $193.48 | $170.00 | $50.00 | $170.00 | $189.44 | |
| 35 | Construction exits (install) (type 2) (506-7021) | SY | 858 | $28.05 | $12.00 | $28.75 | $30.20 | $30.00 | $60.61 | $20.05 |
| 36 | Construction exits (remove) (506-7024) | SY | 858 | $8.92 | $6.00 | $12.19 | $18.00 | $10.00 | $30.54 | $4.14 |
| 37 | Temporary sediment control fence (install) (506-7039) | LF | 707 | $6.05 | $6.00 | $5.25 | $4.70 | $10.00 | $4.65 | $5.14 |
| 38 | Temporary sediment control fence (remove) (506-7041) | LF | 707 | $2.25 | $3.00 | $2.49 | $2.20 | $3.00 | $2.15 | $2.44 |
| 39 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 120 | $10.00 | $8.84 | $10.80 | $8.00 | $10.75 | $8.66 | |
| 40 | Biodegradable erosion control logs (remove) (506-7046) | LF | 120 | $5.00 | $4.42 | $5.90 | $3.00 | $5.90 | $4.33 | |
| 41 | Driveways (ACP) (530-7010) | SY | 1,347 | $69.75 | $27.00 | $52.49 | $94.00 | $80.00 | $140.44 | $97.50 |
| 42 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 17 | $267.11 | $393.00 | $374.19 | $325.00 | $250.00 | $525.00 | $568.31 |
| 43 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 7 | $926.71 | $1,026.00 | $978.65 | $850.00 | $1,200.00 | $985.00 | $1,173.39 |
| 44 | Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026) | EACH | 4 | $857.43 | $1,147.00 | $1,093.79 | $950.00 | $1,200.00 | $1,200.00 | $1,369.95 |
| 45 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 1 | $1,046.32 | $1,237.00 | $1,180.14 | $1,025.00 | $1,200.00 | $1,600.00 | $1,173.39 |
| 46 | Remove SM RD SN sup&AM (644-7073) | EACH | 6 | $124.15 | $302.00 | $287.84 | $250.00 | $850.00 | $150.00 | $827.93 |
| 47 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 6 | $90.20 | $67.00 | $63.33 | $55.00 | $1,000.00 | $150.00 | $59.56 |
| 48 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 71 | $8.86 | $18.00 | $19.90 | $14.80 | $8.00 | $16.08 | $19.49 |
| 49 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 10,176 | $0.84 | $1.25 | $0.93 | $1.00 | $1.50 | $1.03 | $0.91 |
| 50 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 770 | $0.66 | $1.50 | $2.76 | $1.20 | $1.50 | $1.30 | $2.71 |
| 51 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 4,314 | $0.85 | $1.25 | $1.38 | $1.00 | $1.50 | $1.03 | $1.35 |
| 52 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 84 | $6.68 | $8.00 | $27.64 | $5.80 | $15.00 | $6.30 | $27.06 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.