TxDOT contract A00185027 bid tabulation
Intersection Improvements With Right And/Or Left Turn Lanes, FM 920 (College St to Ric Williamson Memorial Highway). Let by Texas DOT on June 2, 2026, Parker, Fort Worth District. 9 bids received; low bid $8,486,108 by Foutsco Paving Company, LLC, -38% against the engineer's estimate of $13,679,045.
- Owner
- Texas DOT
- Letting
- 02 JUN 2026
- Pay items
- 132
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Foutsco Paving Company, LLC | $8,486,108 | Low | -38% |
| 2 | Jagoe-Public Company | $8,701,080 | +3.0% | -36% |
| 3 | Jay Mills Contracting, Incorporated | $8,936,757 | +5.0% | -35% |
| 4 | A. L. Helmcamp, Inc. | $9,172,554 | +8.0% | -33% |
| 5 | Overland Corporation | $9,632,104 | +14% | -30% |
| 6 | Ed Bell Construction Company | $9,849,892 | +16% | -28% |
| 7 | Texas Materials Group, Inc. | $9,977,577 | +18% | -27% |
| 8 | Eurovia Atlantic Coast LLC | $10,802,514 | +27% | -21% |
| 9 | Prater Dirt Work LLC | $11,991,783 | +41% | -12% |
Engineer's estimate: $13,679,045.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Foutsco Paving Company, LLC | 2. Jagoe-Public Company | 3. Jay Mills Contracting, Incorporated | 4. A. L. Helmcamp, Inc. | 5. Overland Corporation | 6. Ed Bell Construction Company |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 132 | $1,500.00 | $1,000.00 | $750.00 | $2,000.00 | $1,000.00 | $5,600.00 | $6,240.00 |
| 2 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 53 | $1,500.00 | $1,500.00 | $620.00 | $725.00 | $700.00 | $700.00 | $700.00 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 32 | $43.00 | $23.00 | $110.00 | $21.00 | $90.00 | $83.00 | $40.00 |
| 4 | Removing concrete (driveways) (104-7011) | SY | 117 | $58.00 | $18.00 | $50.00 | $21.00 | $40.00 | $30.52 | $60.00 |
| 5 | Remove stab base and asphalt pavement (6"-20") (105-7123) | SY | 10,479 | $7.00 | $12.00 | $20.00 | $11.00 | $7.00 | $14.00 | $13.00 |
| 6 | Excavation (roadway) (110-7001) | CY | 20,322 | $50.00 | $16.00 | $40.00 | $22.00 | $21.00 | $30.00 | $6.50 |
| 7 | Excavation (channel) (110-7002) | CY | 255 | $43.00 | $50.00 | $50.00 | $50.00 | $40.00 | $73.00 | $63.00 |
| 8 | Embankment (final)(DC)(type B) (132-7004) | CY | 5,233 | $30.00 | $10.00 | $15.00 | $22.00 | $17.00 | $7.40 | $55.00 |
| 9 | Backfill (type A) (134-7001) | STA | 132 | $290.00 | $150.00 | $400.00 | $270.00 | $310.00 | $491.36 | $600.00 |
| 10 | Furn & place topsoil (4") (160-7002) | SY | 57,888 | $2.00 | $4.00 | $2.11 | $3.40 | $1.50 | $1.35 | $2.50 |
| 11 | Block sodding (162-7002) | SY | 1,072 | $4.00 | $5.00 | $5.00 | $7.30 | $6.50 | $19.65 | $15.00 |
| 12 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 57,888 | $5.00 | $0.30 | $0.30 | $0.30 | $0.22 | $1.02 | $0.35 |
| 13 | Broadcast seed (temporary_warm) (164-7005) | SY | 4,354 | $9.00 | $0.25 | $0.20 | $0.47 | $0.22 | $0.70 | $0.25 |
| 14 | Broadcast seed (temporary_cool) (164-7006) | SY | 4,354 | $9.00 | $0.27 | $0.20 | $0.54 | $0.22 | $0.72 | $0.25 |
| 15 | Vegetative watering (168-7001) | TGL | 2,064 | $500.00 | $1.00 | $20.00 | $21.00 | $20.00 | $0.01 | $10.00 |
| 16 | Soil ret BLKT(SL_mod_clay_long) (169-7002) | SY | 4,354 | $4.00 | $1.50 | $1.50 | $1.05 | $2.20 | $1.50 | $2.00 |
| 17 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 6,512 | $100.00 | $84.00 | $90.00 | $80.15 | $82.00 | $90.00 | $100.00 |
| 18 | Lime (quicklime (slurry)) (260-7003) | TON | 488 | $305.58 | $320.00 | $350.00 | $350.00 | $265.00 | $315.00 | $350.00 |
| 19 | Lime TRT (subgrade) (8") (260-7020) | SY | 29,303 | $5.00 | $4.50 | $8.00 | $5.10 | $7.50 | $5.23 | $8.00 |
| 20 | Prime coat (multi option) (310-7015) | GAL | 17,581 | $15.00 | $4.00 | $3.50 | $6.25 | $7.00 | $5.73 | $1.00 |
| 21 | SP mixes SP-B PG64-22 (344-7001) | TON | 6,740 | $150.00 | $100.00 | $110.00 | $112.00 | $131.40 | $116.25 | $120.00 |
| 22 | SP mixes SP-C sac-A PG70-28 (344-7024) | TON | 7,953 | $170.00 | $130.00 | $145.00 | $172.00 | $175.00 | $155.16 | $175.00 |
| 23 | Plane & text asphalt concrete pavement(0" to 2") (354-7002) | SY | 43,002 | $2.00 | $1.00 | $3.00 | $2.20 | $3.00 | $6.00 | $2.50 |
| 24 | Cut & restore asphalt paving (400-7008) | SY | 133 | $264.00 | $300.00 | $195.00 | $400.00 | $75.00 | $302.00 | $305.00 |
| 25 | Trench excavation protection (402-7001) | LF | 47 | $30.00 | $1.20 | $250.00 | $7.00 | $26.00 | $15.00 | $100.00 |
| 26 | Temporary special shoring (403-7001) | SF | 420 | $51.00 | $70.00 | $90.00 | $88.00 | $70.00 | $70.00 | $80.00 |
| 27 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 184 | $355.00 | $250.00 | $470.00 | $275.00 | $265.00 | $250.00 | $266.25 |
| 28 | Riprap (concrete)(5 in) (432-7002) | CY | 21 | $855.00 | $576.00 | $800.00 | $660.00 | $800.00 | $769.29 | $800.00 |
| 29 | Riprap (stone protection)(18 in) (432-7043) | CY | 304 | $230.00 | $146.00 | $330.00 | $150.00 | $240.00 | $188.88 | $250.00 |
| 30 | Concrete box culvert (8 FT X 5 FT) (462-7022) | LF | 60 | $1,025.00 | $811.00 | $1,000.00 | $1,430.00 | $2,200.00 | $1,657.60 | $1,100.00 |
| 31 | Concrete box culvert (9 FT X 5 FT) (462-7027) | LF | 60 | $1,095.00 | $811.00 | $1,000.00 | $1,650.00 | $2,400.00 | $1,715.21 | $1,100.00 |
| 32 | RC pipe (CL III)(18 in) (464-7003) | LF | 131 | $91.00 | $90.00 | $60.00 | $75.00 | $100.00 | $109.68 | $75.00 |
| 33 | RC pipe (CL III)(24 in) (464-7005) | LF | 1,880 | $135.00 | $85.00 | $100.00 | $80.00 | $110.00 | $97.05 | $90.00 |
| 34 | RC pipe (CL III)(30 in) (464-7007) | LF | 5 | $300.00 | $311.00 | $360.00 | $320.00 | $120.00 | $330.25 | $750.00 |
| 35 | RC pipe (CL III)(42 in) (464-7010) | LF | 15 | $420.00 | $234.00 | $260.00 | $350.00 | $270.00 | $263.47 | $800.00 |
| 36 | RC pipe (CL III)(54 in) (464-7012) | LF | 4 | $440.00 | $433.00 | $1,100.00 | $700.00 | $370.00 | $472.86 | $1,500.00 |
| 37 | Inlet(complete)(pazd)(FG)(5FTX5FT-4FTX4FT) (465-7162) | EACH | 2 | $10,000 | $10,000 | $11,000 | $8,000.00 | $11,000 | $9,439.30 | $12,000 |
| 38 | Inlet (complete)(AD)(3FT X 3FT)(FTW) (465-7234) | EACH | 1 | $5,000.00 | $2,800.00 | $8,000.00 | $4,650.00 | $13,000 | $2,869.30 | $10,000 |
| 39 | Headwall (CH - PW - 0) (diameter= 24 in) (466-7101) | EACH | 1 | $10,000 | $3,100.00 | $9,000.00 | $8,800.00 | $11,000 | $3,122.50 | $11,000 |
| 40 | Headwall (CH - PW - 0) (diameter= 54 in) (466-7108) | EACH | 1 | $17,000 | $15,000 | $23,000 | $16,500 | $38,000 | $14,755 | $19,000 |
| 41 | Wingwall (PW - 1) (HW=7 FT) (466-7177) | EACH | 2 | $57,000 | $28,000 | $39,000 | $85,800 | $72,000 | $27,523 | $37,500 |
| 42 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 8 | $1,700.00 | $675.00 | $1,900.00 | $1,900.00 | $1,600.00 | $671.80 | $1,100.00 |
| 43 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 71 | $2,700.00 | $1,110.00 | $1,900.00 | $2,500.00 | $2,200.00 | $1,110.70 | $1,800.00 |
| 44 | Set (type II) (30 in) (RCP) (3: 1) (C) (467-7345) | EACH | 1 | $4,200.00 | $1,800.00 | $4,400.00 | $3,150.00 | $2,600.00 | $1,817.40 | $2,500.00 |
| 45 | Set (type II) (42 in) (RCP) (4: 1) (C) (467-7378) | EACH | 1 | $6,200.00 | $3,100.00 | $8,000.00 | $6,500.00 | $5,800.00 | $3,074.00 | $10,000 |
| 46 | Set (type II) (54 in) (RCP) (4: 1) (C) (467-7398) | EACH | 1 | $9,950.00 | $6,300.00 | $12,000 | $11,000 | $13,000 | $6,307.70 | $15,000 |
| 47 | Removing structure (inlet) (496-7002) | EACH | 1 | $1,095.00 | $1,600.00 | $2,900.00 | $960.00 | $800.00 | $1,635.00 | $2,000.00 |
| 48 | Removing structure (wingwall) (496-7005) | EACH | 2 | $2,226.00 | $1,250.00 | $3,300.00 | $1,100.00 | $1,100.00 | $1,248.00 | $5,000.00 |
| 49 | Removing structure (pipe) (496-7007) | LF | 1,495 | $55.00 | $25.00 | $44.00 | $24.00 | $16.00 | $25.50 | $24.00 |
| 50 | Removing structure (box culvert) (496-7008) | LF | 47 | $240.00 | $202.00 | $1,500.00 | $110.00 | $220.00 | $202.60 | $210.00 |
| 51 | Mobilization (500-7001) | LS | 1 | $1,243,550 | $608,000 | $965,000 | $890,000 | $880,000 | $961,055 | $981,000 |
| 52 | Barricades, signs and traffic handling (502-7001) | MO | 22 | $12,000 | $74,000 | $10,000 | $8,000.00 | $20,000 | $11,500 | $21,000 |
| 53 | Portable changeable message sign (503-7001) | DAY | 896 | $125.00 | $1.00 | $5.00 | $100.00 | $90.00 | $150.00 | $125.00 |
| 54 | TMA (stationary) (505-7001) | DAY | 882 | $222.00 | $1.00 | $5.00 | $150.00 | $200.00 | $215.09 | $75.00 |
| 55 | TMA (mobile operation) (505-7003) | DAY | 96 | $204.00 | $1.00 | $100.00 | $150.00 | $100.00 | $1.00 | $600.00 |
| 56 | Rock filter dams (install) (type 1) (506-7001) | LF | 124 | $36.00 | $35.00 | $39.00 | $38.00 | $41.00 | $38.50 | $53.78 |
| 57 | Rock filter dams (remove) (506-7011) | LF | 124 | $46.00 | $10.00 | $10.00 | $9.90 | $16.00 | $10.00 | $21.30 |
| 58 | Construction exits (install) (type 1) (506-7020) | SY | 888 | $32.00 | $35.00 | $10.00 | $33.25 | $38.00 | $35.00 | $37.28 |
| 59 | Construction exits (remove) (506-7024) | SY | 888 | $20.00 | $10.00 | $5.00 | $9.90 | $13.00 | $13.00 | $13.85 |
| 60 | Temporary sediment control fence (install) (506-7039) | LF | 23,740 | $1.00 | $1.00 | $3.75 | $4.50 | $4.00 | $3.60 | $3.83 |
| 61 | Temporary sediment control fence (remove) (506-7041) | LF | 23,740 | $1.00 | $0.50 | $1.00 | $1.00 | $0.90 | $1.10 | $1.17 |
| 62 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 210 | $8.00 | $4.00 | $12.00 | $6.50 | $6.00 | $4.25 | $4.53 |
| 63 | Biodegradable erosion control logs (remove) (506-7046) | LF | 210 | $6.00 | $1.00 | $1.25 | $1.05 | $2.00 | $1.20 | $1.28 |
| 64 | Constructing detours (508-7001) | SY | 1,974 | $150.00 | $150.00 | $90.00 | $72.00 | $95.00 | $125.00 | $120.00 |
| 65 | One-way traffic control (port traffic signal) (510-7003) | MO | 2 | $15,000 | $5,000.00 | $20,000 | $3,500.00 | $8,000.00 | $5,250.00 | $5,000.00 |
| 66 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 8,480 | $50.00 | $42.00 | $40.00 | $61.00 | $36.00 | $42.00 | $30.00 |
| 67 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 920 | $50.00 | $42.00 | $40.00 | $71.00 | $36.00 | $42.00 | $95.00 |
| 68 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 6,740 | $23.00 | $12.00 | $10.00 | $9.20 | $13.00 | $12.00 | $12.00 |
| 69 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 920 | $27.00 | $12.00 | $10.00 | $9.20 | $13.00 | $12.00 | $24.00 |
| 70 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 8,480 | $70.00 | $18.00 | $15.00 | $11.50 | $24.00 | $18.00 | $15.00 |
| 71 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 920 | $75.00 | $18.00 | $15.00 | $11.50 | $24.00 | $18.00 | $30.00 |
| 72 | Driveways (concrete) (530-7006) | SY | 121 | $110.00 | $105.00 | $180.00 | $160.00 | $190.00 | $184.70 | $200.00 |
| 73 | Driveways (ACP) (530-7010) | SY | 3,453 | $80.00 | $48.00 | $50.00 | $110.00 | $100.00 | $106.30 | $115.00 |
| 74 | Turnouts (ACP) (530-7018) | SY | 81 | $120.00 | $120.00 | $36.00 | $175.00 | $100.00 | $116.32 | $200.00 |
| 75 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 70,834 | $2.00 | $0.20 | $0.20 | $0.22 | $0.25 | $0.28 | $0.17 |
| 76 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 18,970 | $2.00 | $0.21 | $0.20 | $0.22 | $0.25 | $0.28 | $0.17 |
| 77 | Remove metal beam guard fence (542-7001) | LF | 150 | $89.00 | $5.00 | $5.00 | $5.50 | $15.00 | $5.00 | $10.65 |
| 78 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $1,000.00 | $250.00 | $260.00 | $275.00 | $700.00 | $250.00 | $372.75 |
| 79 | Remove and install existing gate (550-7017) | EACH | 1 | $800.00 | $500.00 | $2,800.00 | $3,300.00 | $2,900.00 | $2,750.00 | $2,928.75 |
| 80 | Wire fence (type B) (552-7002) | LF | 75 | $36.00 | $40.00 | $42.00 | $50.00 | $43.00 | $41.50 | $44.20 |
| 81 | Wire fence (type D) (552-7004) | LF | 36 | $50.00 | $50.00 | $90.00 | $105.00 | $96.00 | $92.25 | $98.25 |
| 82 | Wire fence (special) (552-7005) | LF | 31 | $130.00 | $50.00 | $70.00 | $80.00 | $72.00 | $68.75 | $73.22 |
| 83 | Wire fence (remove) (552-7011) | LF | 31 | $23.00 | $15.00 | $17.00 | $18.15 | $38.00 | $511.00 | $17.57 |
| 84 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 19 | $640.00 | $280.00 | $290.00 | $308.00 | $275.00 | $280.00 | $618.33 |
| 85 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 4 | $580.00 | $185.00 | $290.00 | $313.50 | $300.00 | $285.00 | $890.38 |
| 86 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 4 | $753.00 | $800.00 | $800.00 | $880.00 | $740.00 | $800.00 | $1,482.02 |
| 87 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 23 | $7,275.00 | $4,400.00 | $5,000.00 | $4,840.00 | $4,600.00 | $4,400.00 | $4,686.00 |
| 88 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 365 | $50.00 | $17.00 | $14.00 | $18.70 | $18.00 | $17.00 | $18.11 |
| 89 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 1,375 | $60.00 | $30.00 | $31.00 | $33.00 | $32.00 | $30.00 | $31.95 |
| 90 | Electrical conductor (no.12) bare (620-7003) | LF | 1,740 | $3.00 | $1.55 | $1.50 | $1.71 | $1.70 | $1.55 | $1.65 |
| 91 | Electrical conductor (no.12) insulated (620-7004) | LF | 3,480 | $2.00 | $1.65 | $1.50 | $1.82 | $1.80 | $1.65 | $1.76 |
| 92 | Ground box type A (122311)W/apron (624-7002) | EACH | 3 | $2,500.00 | $1,085.00 | $1,500.00 | $1,200.00 | $1,200.00 | $1,085.00 | $1,155.53 |
| 93 | Elc SRV type A 240/480 060(NS)SS(E)SP(O) (628-7048) | EACH | 7 | $12,385 | $6,900.00 | $12,500 | $7,600.00 | $7,300.00 | $6,900.00 | $7,348.50 |
| 94 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 11 | $1,000.00 | $650.00 | $700.00 | $715.00 | $950.00 | $650.00 | $670.95 |
| 95 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 3 | $1,800.00 | $895.00 | $900.00 | $985.00 | $950.00 | $895.00 | $942.53 |
| 96 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 7 | $600.00 | $550.00 | $600.00 | $605.00 | $950.00 | $550.00 | $644.33 |
| 97 | Remove SM RD SN sup&AM (644-7073) | EACH | 1 | $500.00 | $150.00 | $150.00 | $165.00 | $110.00 | $150.00 | $105.44 |
| 98 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 10 | $200.00 | $65.00 | $70.00 | $71.50 | $80.00 | $65.00 | $58.58 |
| 99 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 24,810 | $3.00 | $0.25 | $0.40 | $0.32 | $0.30 | $0.36 | $0.27 |
| 100 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 64 | $40.00 | $5.00 | $7.00 | $6.60 | $6.30 | $6.70 | $3.20 |
| 101 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 26,658 | $5.00 | $0.25 | $0.40 | $0.32 | $0.30 | $0.36 | $0.27 |
| 102 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 26,290 | $1.00 | $0.89 | $0.80 | $0.78 | $0.75 | $0.78 | $1.03 |
| 103 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 116 | $10.00 | $4.76 | $7.00 | $13.20 | $12.60 | $6.65 | $6.12 |
| 104 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 28,112 | $1.00 | $0.89 | $0.80 | $0.78 | $0.75 | $0.78 | $1.03 |
| 105 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 10,140 | $2.00 | $0.86 | $0.90 | $0.86 | $0.82 | $0.89 | $1.01 |
| 106 | Reflectorized pavement marking type I (W)18"(solid)(100MIL) (666-7033) | LF | 127 | $8.00 | $6.00 | $5.00 | $13.20 | $12.50 | $5.05 | $5.33 |
| 107 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 647 | $12.00 | $6.75 | $7.00 | $13.20 | $12.50 | $6.70 | $7.30 |
| 108 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 42 | $134.00 | $150.00 | $130.00 | $170.50 | $165.00 | $131.00 | $186.38 |
| 109 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 42 | $40.00 | $150.00 | $160.00 | $269.50 | $260.00 | $158.00 | $207.68 |
| 110 | Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117) | LF | 1,817 | $4.00 | $3.00 | $3.75 | $4.95 | $4.80 | $3.75 | $4.53 |
| 111 | Pavement sler 6" (666-7347) | LF | 160,482 | $1.00 | $0.13 | $0.18 | $0.25 | $0.23 | $0.18 | $0.18 |
| 112 | Pavement sler 12" (666-7350) | LF | 1,692 | $2.00 | $0.20 | $0.80 | $1.93 | $1.80 | $0.78 | $0.24 |
| 113 | Pavement sler 24" (666-7352) | LF | 251 | $2.00 | $1.00 | $1.50 | $3.58 | $3.40 | $1.40 | $0.64 |
| 114 | Pavement sler (arrow) (666-7353) | EACH | 13 | $35.00 | $16.00 | $27.00 | $77.00 | $74.00 | $26.00 | $42.60 |
| 115 | Pavement sler (word) (666-7354) | EACH | 9 | $45.00 | $16.00 | $33.00 | $82.50 | $79.00 | $32.00 | $53.25 |
| 116 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 78,395 | $1.00 | $0.52 | $0.60 | $0.56 | $0.54 | $0.58 | $0.61 |
| 117 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 13,095 | $2.00 | $0.53 | $0.70 | $0.59 | $0.57 | $0.66 | $0.67 |
| 118 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 83,341 | $3.00 | $0.52 | $0.60 | $0.56 | $0.54 | $0.58 | $0.61 |
| 119 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 2,681 | $6.00 | $3.90 | $4.25 | $5.50 | $5.25 | $4.15 | $4.26 |
| 120 | Eliminating existing PM & markers (4") (677-7001) | LF | 157,342 | $1.00 | $0.47 | $0.50 | $0.21 | $0.20 | $0.44 | $0.53 |
| 121 | Eliminating existing PM & markers (6") (677-7002) | LF | 3,140 | $2.00 | $0.60 | $0.40 | $0.22 | $0.21 | $0.35 | $0.53 |
| 122 | Eliminating existing PM & markers (12") (677-7006) | LF | 1,692 | $2.00 | $1.89 | $1.75 | $2.20 | $2.10 | $1.65 | $1.33 |
| 123 | Eliminating existing PM & markers (24") (677-7008) | LF | 251 | $7.00 | $2.50 | $2.75 | $4.13 | $3.90 | $2.75 | $3.20 |
| 124 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 13 | $142.00 | $55.00 | $40.00 | $77.00 | $70.00 | $39.00 | $37.28 |
| 125 | Eliminating existing PM & markers (word) (677-7015) | EACH | 9 | $142.00 | $55.00 | $47.00 | $77.00 | $70.00 | $46.00 | $47.93 |
| 126 | Pavement surface preparation for marking (6") (678-7002) | LF | 160,482 | $1.00 | $0.17 | $0.02 | $0.01 | $0.01 | $0.02 | $0.14 |
| 127 | Pavement surface preparation for marking (12") (678-7006) | LF | 1,692 | $6.00 | $0.45 | $0.40 | $0.06 | $0.05 | $0.41 | $0.53 |
| 128 | Pavement surface preparation for marking (24") (678-7008) | LF | 251 | $16.00 | $0.55 | $0.50 | $0.06 | $0.05 | $0.49 | $1.07 |
| 129 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 13 | $245.00 | $10.00 | $12.00 | $1.10 | $1.00 | $11.75 | $31.95 |
| 130 | Pavement surface preparation for marking (word) (678-7016) | EACH | 9 | $486.00 | $10.00 | $14.00 | $1.10 | $1.00 | $13.75 | $42.60 |
| 131 | Underseal course (3006-7001) | GAL | 13,831 | $5.00 | $4.00 | $3.25 | $0.01 | $4.00 | $4.38 | $0.01 |
| 132 | Remove and replace wood fence (5035-7001) | LF | 239 | $110.00 | $50.00 | $39.00 | $120.00 | $26.00 | $60.00 | $80.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 2, 2026. Compiled by Mirage Metrics.