TxDOT contract A00187815 bid tabulation
Bridge Maintenance, Various (Districtwide to .). Let by Texas DOT on January 7, 2026, Ector, Odessa District. 12 bids received; low bid $1,656,587 by BK Field Operations LLC, -32% against the engineer's estimate of $2,435,466.
- Owner
- Texas DOT
- Letting
- 07 JAN 2026
- Pay items
- 28
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | BK Field Operations LLC | $1,656,587 | Low | -32% |
| 2 | Premier Contractors LLC | $1,899,157 | +15% | -22% |
| 3 | MPB, Inc. | $1,973,836 | +19% | -19% |
| 4 | Ragle Construction, Inc. | $1,989,084 | +20% | -18% |
| 5 | Pathfield Investments LLC | $2,082,561 | +26% | -14% |
| 6 | Relmco, Inc. | $2,252,384 | +36% | -8.0% |
| 7 | SCR Civil Construction, LLC | $2,307,782 | +39% | -5.0% |
| 8 | Built Right Construction of Oklahoma, LLC | $2,685,515 | +62% | +10% |
| 9 | Grey Sky Construction LLC | $2,767,400 | +67% | +14% |
| 10 | Ti-Zack Concrete, LLC | $2,790,042 | +68% | +15% |
| 11 | Blacksmith Ventures LLC | $2,873,110 | +73% | +18% |
| 12 | Southern Road & Bridge, LLC | $3,855,482 | +133% | +58% |
Engineer's estimate: $2,435,466.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. BK Field Operations LLC | 2. Premier Contractors LLC | 3. MPB, Inc. | 4. Ragle Construction, Inc. | 5. Pathfield Investments LLC | 6. Relmco, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Flowable backfill (401-7001) | CY | 159 | $275.00 | $300.00 | $200.00 | $320.00 | $290.00 | $90.00 | $250.00 |
| 2 | Class C concrete (miscellaneous) (420-7067) | CY | 45 | $997.93 | $450.00 | $500.00 | $600.00 | $250.00 | $1,000.00 | $1,200.00 |
| 3 | Blast finish (427-7007) | SF | 1,000 | $4.00 | $25.00 | $5.00 | $5.00 | $5.00 | $20.00 | $10.00 |
| 4 | Concrete structure repair(deck rep(part depth)) (429-7003) | SF | 150 | $250.00 | $350.00 | $200.00 | $235.00 | $60.00 | $190.00 | $200.00 |
| 5 | Concrete structure repair(deck rep (full depth)) (429-7005) | SF | 60 | $180.00 | $600.00 | $250.00 | $145.00 | $145.00 | $240.00 | $300.00 |
| 6 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 4,568 | $150.00 | $75.00 | $200.00 | $96.00 | $125.00 | $175.00 | $150.00 |
| 7 | Concrete structure repair (standard) (429-7009) | SF | 35 | $150.00 | $310.00 | $200.00 | $135.00 | $200.00 | $210.00 | $200.00 |
| 8 | Riprap (concrete)(4 in) (432-7001) | CY | 185 | $613.61 | $650.00 | $600.00 | $550.00 | $560.00 | $900.00 | $825.00 |
| 9 | Elastomeric bearing (EE2) (434-7004) | EACH | 20 | $3,000.00 | $5,500.00 | $3,000.00 | $3,300.00 | $3,500.00 | $8,000.00 | $2,500.00 |
| 10 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 3,293 | $44.95 | $50.00 | $40.00 | $63.00 | $23.00 | $50.00 | $43.00 |
| 11 | Rail (type PR11) (450-7044) | LF | 450 | $137.27 | $145.00 | $120.00 | $165.00 | $110.00 | $260.00 | $150.00 |
| 12 | Header type expansion joint (454-7009) | CF | 8 | $541.94 | $1,500.00 | $1,000.00 | $1,985.00 | $350.00 | $1,100.00 | $1,200.00 |
| 13 | Joint sealant (454-7010) | LF | 45 | $28.00 | $100.00 | $50.00 | $15.30 | $55.00 | $60.00 | $38.00 |
| 14 | Clean existing culverts (480-7001) | EACH | 4 | $3,000.00 | $4,500.00 | $3,000.00 | $10,000 | $2,600.00 | $4,000.00 | $4,500.00 |
| 15 | Raising existing struct (495-7001) | LS | 2 | $83,000 | $32,000 | $15,000 | $38,500 | $157,500 | $27,000 | $35,000 |
| 16 | Mobilization (500-7001) | LS | 1 | $156,349 | $70,000 | $150,000 | $130,000 | $190,000 | $180,000 | $150,000 |
| 17 | Barricades, signs and traffic handling (502-7001) | MO | 16 | $15,000 | $1.00 | $1.00 | $3,500.00 | $4,000.00 | $10.00 | $3,500.00 |
| 18 | Portable changeable message sign (503-7001) | DAY | 701 | $130.00 | $1.00 | $1.00 | $60.00 | $10.00 | $1.00 | $150.00 |
| 19 | TMA (stationary) (505-7001) | DAY | 820 | $200.00 | $1.00 | $1.00 | $100.00 | $25.00 | $1.00 | $150.00 |
| 20 | Concrete rail repair (in-kind) (778-7001) | LF | 143 | $375.00 | $350.00 | $350.00 | $355.00 | $100.00 | $190.00 | $350.00 |
| 21 | Concrete rail repair (miscellaneous) (778-7002) | LF | 190 | $250.00 | $350.00 | $250.00 | $350.00 | $100.00 | $190.00 | $150.00 |
| 22 | CNC crack repair (discrete)(inject) (780-7002) | LF | 1,190 | $50.00 | $80.00 | $50.00 | $60.00 | $40.00 | $40.00 | $80.00 |
| 23 | Rep steel bridge member (beam) (784-7002) | EACH | 2 | $20,000 | $32,000 | $12,500 | $5,500.00 | $30,000 | $5,000.00 | $7,500.00 |
| 24 | Rep steel bridge MBR (straighten memb) (784-7020) | EACH | 2 | $25,000 | $20,000 | $18,000 | $60,750 | $10,000 | $30,000 | $62,500 |
| 25 | Concrete beam repair (788-7001) | EACH | 6 | $5,380.41 | $7,000.00 | $6,000.00 | $2,700.00 | $7,500.00 | $4,000.00 | $6,500.00 |
| 26 | Steel bridge zone painting ref STR #1 (4010-7001) | EACH | 1 | $50,000 | $100,000 | $30,000 | $125,000 | $200,000 | $60,000 | $92,500 |
| 27 | Asphalt plug expansion joint (4028-7001) | LF | 210 | $236.55 | $150.00 | $120.00 | $205.00 | $55.00 | $40.00 | $50.00 |
| 28 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 3 | $1,039.07 | $750.00 | $1,500.00 | $1,750.00 | $850.00 | $3,000.00 | $2,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 7, 2026. Compiled by Mirage Metrics.