TxDOT contract A00188847 bid tabulation

Surfacing/Roadway Restoration, SH 225 (SL 8 to Miller Cut Off Rd). Let by Texas DOT on January 6, 2026, Harris, Houston District. 6 bids received; low bid $22,200,382 by Texas Materials Group, Inc., +6.8% against the engineer's estimate of $20,784,641.

Owner
Texas DOT
Letting
06 JAN 2026
Pay items
91
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Texas Materials Group, Inc.$22,200,382Low+7.0%
2Isi Contracting, Inc.$23,639,645+6.0%+14%
3Ragle Construction, Inc.$27,244,511+23%+31%
4Posillico Civil, Inc.$28,210,072+27%+36%
5Icon GC, LLC$28,994,626+31%+40%
6Durwood Greene Construction Co.$29,881,180+35%+44%
TxDOT contract A00188847: bids by rank

Engineer's estimate: $20,784,641.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Texas Materials Group, Inc.2. Isi Contracting, Inc.3. Ragle Construction, Inc.4. Posillico Civil, Inc.5. Icon GC, LLC6. Durwood Greene Construction Co.
1Removing concrete (mowstrip) (104-7005)LF3,175$20.00$18.00$5.00$8.00$12.50$18.00$35.00
2Removing concrete (curb) (104-7016)LF1,179$52.30$5.00$6.00$9.25$20.00$20.00
3Stone-MTRX-asphalt SMA-D sac-A PG76-22 (346-7009)TON66,910.80$155.00$170.00$195.00$217.00$243.00$257.00$235.00
4Plane concrete pavement(0" to 1.5") (354-7065)SY24,386.10$12.00$6.50$18.00$7.00$10.00$6.00$35.00
5Full-depth repair CRCP (var depth) (361-7044)CY7,237.60$820.00$965.00$750.00$850.00$1,145.00$1,091.00$1,100.00
6Riprap (mow strip)(4 in) (432-7013)CY137.20$745.00$1,000.00$366.00$900.00$620.00$374.00$1,400.00
7Rail (CLF-RO) (450-7049)LF360$160.00$175.00$108.00$110.00$195.00$211.00$150.00
8Adjusting inlets (479-7002)EACH7$900.00$618.00$1,300.00$750.00$2,094.00$3,200.00
9Mobilization (500-7001)LS1$1,889,513$1,000,000$1,250,000$2,700,000$225,000$200,451$2,000,000
10Barricades, signs and traffic handling (502-7001)MO13$3,462.00$1,365.00$6,750.00$100,000$35,000$52,847$50,000
11Portable changeable message sign (503-7001)DAY390$131.00$130.00$180.00$106.00$120.00$112.00$300.00
12TMA (stationary) (505-7001)DAY390$220.00$750.00$3,100.00$346.00$285.00$294.00$350.00
13TMA (mobile operation) (505-7003)DAY390$120.00$1.00$400.00$675.00$1,250.00$757.00$350.00
14Concrete curb (mono) (type II) (529-7007)LF1,179$74.00$80.00$13.00$18.00$5.00$75.00
15Concrete curb (dowel) (529-7014)LF471.60$144.00$195.00$41.50$20.00$12.00$75.00
16Mill rumble strips (asphalt) (shoulder) (533-7001)LF91,489$0.13$0.15$0.43$0.17$0.15$0.17$0.28
17Metal W-beam guard fence (timber post) (540-7001)LF3,175$25.00$32.00$15.36$27.15$23.50$30.00$28.00
18Metal beam guard fence trans (thrie-beam) (540-7005)EACH46$1,815.00$1,500.00$1,512.00$1,960.00$1,912.50$2,319.00$2,850.00
19Downstream anchor terminal section (540-7015)EACH46$1,575.00$1,300.00$2,000.00$1,115.00$1,414.00$1,791.00$1,600.00
20Remove metal beam guard fence (542-7001)LF3,175$2.20$8.00$0.40$2.00$3.40$5.00$4.00
21Remove downstream anchor terminal (542-7003)EACH46$164.00$311.00$25.58$230.00$131.25$294.00$150.00
22RM metal beam guard fence trans (thrie-beam) (542-7004)EACH46$164.00$465.00$50.87$260.00$157.50$294.00$170.00
23Guardrail end treatment (install) (544-7001)EACH46$2,900.00$2,450.00$2,500.00$3,200.00$3,196.20$3,434.00$3,805.00
24Guardrail end treatment (remove) (544-7003)EACH46$164.00$311.00$51.00$330.00$236.25$352.00$250.00
25Chain link fence (install) (8') (550-7005)LF360$35.00$0.10$114.00$41.80$36.75$173.00$50.00
26Conduit (PVC) (schedule 80) (2") (618-7054)LF50$21.00$13.69$13.16$14.00$25.00$26.00
27Conduit (PVC) (schedule 80) (2") (bore) (618-7055)LF1,050$22.00$12.75$12.25$13.00$26.00$27.00
28Electrical conductor (no.8) bare (620-7007)LF1,640$1.85$1.66$1.60$1.70$2.00$2.30
29Ground box type D (162922)W/apron (624-7008)EACH14$1,375.00$1,296.00$1,245.35$1,308.00$1,641.00$1,700.00
30Replace existing aluminum signs(type A) (636-7004)SF100$39.00$25.00$26.01$34.70$68.25$23.00$80.00
31Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH3$625.00$650.00$695.00$695.10$814.00$800.00
32Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH10$815.00$825.00$858.00$945.00$848.40$894.00$1,000.00
33Remove SM RD SN sup&AM (644-7073)EACH8$152.00$110.00$114.00$95.00$78.75$100.00$90.00
34In SRSS & AM (rail)(130 MPH)(P mount) (644-7083)EACH1$7,125.00$7,413.00$4,125.00$4,783.80$5,284.00$5,600.00
35In SRSS & AM (rail)(130 MPH)(U-BM MNT) (644-7087)EACH1$6,150.00$6,399.00$4,285.00$4,783.80$14,089$5,600.00
36Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012)EACH317$8.00$21.00$21.85$24.00$18.90$29.00$22.50
37Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH64$25.00$30.00$31.21$30.00$24.15$53.00$28.75
38Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031)EACH62$25.00$26.01$24.00$18.90$29.00$22.50
39Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032)EACH349$7.00$30.00$31.21$30.00$24.15$34.00$28.75
40Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036)EACH9$30.00$31.21$30.00$24.15$53.00$28.75
41Work zone pavement marking removing (reflectorized) type I-A (662-7047)EACH769$6.00$4.00$4.16$2.00$4.20$2.00$4.40
42Work zone pavement marking removing (reflectorized) type I-C (662-7049)EACH932$6.00$4.00$4.16$2.00$4.20$2.00$4.40
43Work zone pavement marking removing (reflectorized) type II-C-R (662-7053)EACH4,637$6.00$3.00$3.12$2.00$3.15$2.00$3.30
44Work zone pavement marking removing (W)6"(broken) (662-7065)LF83,048$0.33$0.35$0.37$0.42$0.38$0.49$0.40
45Work zone pavement marking removing (W)6"(solid) (662-7068)LF97,576$0.33$0.35$0.37$0.42$0.38$0.49$0.40
46Work zone pavement marking removing (W)(entr gore) (662-7084)EACH21$273.15$200.00$208.00$835.06$210.00$980.00$220.00
47Work zone pavement marking removing (W)(exit gore) (662-7085)EACH21$273.15$350.00$364.00$553.12$367.50$649.00$385.00
48Work zone pavement marking removing (Y)6"(solid) (662-7100)LF52,400$0.33$0.36$0.37$0.42$0.38$0.49$0.40
49Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009)LF1,058$2.00$2.30$2.39$2.25$2.42$3.00$2.40
50Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF24,377$2.05$1.00$1.04$1.75$1.20$2.00$1.10
51Reflectorized pavement marking type I (W)12"(lane drop)(100MIL) (666-7027)LF4,152$5.10$3.00$3.12$3.75$3.15$4.00$3.30
52Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030)LF7,496$5.90$3.00$3.12$3.75$3.15$4.00$3.30
53Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF558$6.00$6.24$7.75$6.30$9.00$6.60
54Reflectorized pavement marking type I (Y)8"(solid)(100MIL) (666-7114)LF2,084$1.00$1.04$1.75$1.05$2.00$1.10
55Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117)LF1,185$6.00$6.24$3.75$6.30$4.00$6.60
56Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266)LF1,614$0.90$2.00$2.08$0.98$2.10$1.00$2.20
57Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270)LF1,653$1.35$2.00$2.08$0.98$2.10$1.00$2.20
58All-wther PM type I (W)6"(solid)(100MIL) (666-7309)LF74,998$0.75$0.80$0.82$0.88$0.84$1.00$0.88
59All-wther PM type I (W)6"(broken)(100MIL) (666-7310)LF49,170$2.10$0.80$0.80$0.88$0.84$1.00$0.88
60All-wther PM type I (Y)6"(solid)(100MIL) (666-7315)LF62,893$0.94$0.80$0.82$0.88$0.84$1.00$0.88
61Pavement sler (arrow) (666-7353)EACH52$8.00$20.00$21.00$1.00$21.00$1.00$22.00
62Pavement sler (word) (666-7354)EACH52$11.00$20.00$21.00$1.00$21.00$1.00$22.00
63Pavement sler (double arrow) (666-7356)EACH31$25.00$26.00$1.00$26.25$1.00$27.50
64Pavement sler (uturn arrow) (666-7358)EACH4$30.00$31.00$1.00$31.50$1.00$33.00
65Pavement sler (U-L arrow) (666-7360)EACH10$30.00$31.00$1.00$31.50$1.00$33.00
66Pavement sler (symbol) (666-7363)EACH4$19.00$40.00$42.00$1.00$42.00$1.00$44.00
67Pavement sler (RR crossing) (666-7364)EACH2$100.00$104.00$1.00$105.00$1.00$110.00
68Prefabricated PM type C (W)(arrow) (668-7091)EACH52$205.00$230.00$239.00$272.46$241.50$320.00$253.00
69Prefabricated PM type C (W)(double arrow) (668-7093)EACH31$325.00$338.00$412.34$341.25$484.00$357.50
70Prefabricated PM type C (W)(uturn arrow) (668-7096)EACH4$340.00$354.00$423.98$357.00$498.00$374.00
71Prefabricated PM type C (W)(U-LT arrow) (668-7098)EACH10$515.00$536.00$541.40$540.75$636.00$566.50
72Prefabricated PM type C (W)(word) (668-7103)EACH52$265.00$290.00$302.00$322.42$304.50$379.00$319.00
73Prefabricated PM type C (W)(RR crossing) (668-7108)EACH2$700.00$728.00$521.84$735.00$613.00$770.00
74Prefabricated PM type C (multi)(shield) (668-7135)EACH4$3,100.00$2,500.00$2,601.00$3,133.00$2,625.00$3,679.00$2,750.00
75Reflectorized pavement marker type I-A (672-7001)EACH93$6.00$6.24$9.75$6.40$11.00$6.50
76Reflectorized pavement marker type I-C (672-7002)EACH16$6.00$6.24$9.75$6.40$11.00$6.50
77Reflectorized pavement marker type II-C-R (672-7006)EACH4,754$6.15$5.50$5.72$9.75$5.80$11.00$6.00
78Pavement surface preparation for marking (arrow) (678-7009)EACH52$10.60$10.00$10.40$5.00$10.50$6.00$11.00
79Pavement surface preparation for marking (double arrow) (678-7010)EACH31$10.00$10.40$5.00$10.50$6.00$11.00
80Pavement surface preparation for marking (uturn arr) (678-7012)EACH4$10.00$10.40$5.00$10.50$6.00$11.00
81Pavement surface preparation for marking (U/LT arrow) (678-7013)EACH10$10.00$10.40$5.00$10.50$6.00$11.00
82Pavement surface preparation for marking (word) (678-7016)EACH52$14.20$10.00$10.40$5.00$10.50$6.00$11.00
83Pavement surface preparation for marking (RR crossing) (678-7020)EACH2$10.00$10.40$5.00$10.50$6.00$11.00
84Pavement surface preparation for marking (shield) (678-7025)EACH4$60.00$10.00$10.00$5.00$10.50$6.00$11.00
85JT cleaning and sealing(trans CNTR JTS) (713-7001)LF2,470$23.50$6.00$2.00$3.00$3.20$4.00$18.00
86JT cleaning and sealing(LNGT CNSTR JTS) (713-7002)LF5,949$20.00$5.00$2.00$3.00$3.20$4.00$18.00
87Underseal course (3006-7001)GAL121,656$3.25$6.00$4.50$4.20$5.80$6.00$3.00
88VIVDS prosr sys (6006-7001)EACH3$13,000$4,918.00$4,727.07$4,965.00$15,510$14,300
89VIVDS cam assy var LNS (6006-7003)EACH17$3,600.00$6,784.00$6,520.07$6,850.00$4,289.00$4,000.00
90VIVDS CNTRL software (6006-7005)EACH1$850.00$1,159.00$1,113.90$1,170.00$1,014.00$935.00
91VIVDS cabling (6006-7007)LF4,010$1.80$2.70$2.58$2.75$2.00$2.00
TxDOT contract A00188847: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of January 6, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy