TxDOT contract A00193243 bid tabulation
Hazard Elimination & Safety, IH 10 (Sutton County line to 9.885 miles E of Sutton County line). Let by Texas DOT on May 1, 2025, Kimble, San Angelo District. 5 bids received; low bid $5,866,107 by Relmco, Inc., -20% against the engineer's estimate of $7,328,607.
- Owner
- Texas DOT
- Letting
- 01 MAY 2025
- Pay items
- 44
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Relmco, Inc. | $5,866,107 | Low | -20% |
| 2 | 3LW Civil LLC | $6,760,548 | +15% | -8.0% |
| 3 | MPB, Inc. | $7,284,508 | +24% | -1.0% |
| 4 | Ragle Construction, Inc. | $7,886,868 | +34% | +8.0% |
| 5 | Icos Management, LLC | $8,061,816 | +37% | +10% |
Engineer's estimate: $7,328,607.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Relmco, Inc. | 2. 3LW Civil LLC | 3. MPB, Inc. | 4. Ragle Construction, Inc. | 5. Icos Management, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Excavation (roadway) (110-7001) | CY | 36 | $35.00 | $100.00 | $19.63 | $25.00 | $750.00 | $165.00 |
| 2 | Embankment (vehicle)(OC)(type A) (132-7013) | CY | 154 | $91.00 | $200.00 | $57.20 | $55.00 | $170.00 | $110.00 |
| 3 | Riprap (concrete)(5 in) (432-7002) | CY | 43 | $495.00 | $785.30 | $530.00 | $670.00 | $770.00 | |
| 4 | Riprap (mow strip)(4 in) (432-7013) | CY | 1,303 | $700.00 | $515.00 | $650.10 | $715.00 | $700.00 | $660.00 |
| 5 | Rail (type SSTR) (450-7024) | LF | 162 | $192.00 | $204.97 | $230.00 | $160.00 | $550.00 | |
| 6 | Retrofit rail (type SSTR) (451-7024) | LF | 8,772 | $243.00 | $175.00 | $211.24 | $230.00 | $250.00 | $374.00 |
| 7 | Retrofit rail (type T131RC) (451-7049) | LF | 1,470 | $183.00 | $210.70 | $242.68 | $225.00 | $250.00 | $440.00 |
| 8 | Wingwall (FW - S) (HW=7 FT) (466-7163) | EACH | 1 | $21,960 | $26,839 | $28,275 | $22,650 | $27,500 | |
| 9 | Wingwall (FW - S) (HW=8 FT) (466-7164) | EACH | 3 | $23,580 | $22,937 | $29,000 | $24,800 | $33,000 | |
| 10 | Removing structure (wingwall) (496-7005) | EACH | 4 | $1,200.00 | $3,645.31 | $950.00 | $6,500.00 | $5,500.00 | |
| 11 | Mobilization (500-7001) | LS | 1 | $700,227 | $565,000 | $540,925 | $350,000 | $780,000 | $115,000 |
| 12 | Barricades, signs and traffic handling (502-7001) | MO | 31 | $6,284.00 | $4,500.00 | $6,117.80 | $6,000.00 | $22,000 | $1.00 |
| 13 | Portable changeable message sign (503-7001) | DAY | 558 | $59.00 | $150.00 | $45.33 | $50.00 | $50.00 | $1.00 |
| 14 | TMA (stationary) (505-7001) | DAY | 558 | $172.00 | $150.00 | $307.38 | $100.00 | $100.00 | $1.00 |
| 15 | Biodegradable erosion control logs (install) (6") (506-7042) | LF | 20,314 | $5.75 | $2.00 | $6.61 | $7.25 | $1.00 | $0.50 |
| 16 | Biodegradable erosion control logs (remove) (506-7046) | LF | 20,314 | $3.00 | $1.00 | $1.30 | $1.50 | $0.25 | $0.50 |
| 17 | One-way traffic control (port traffic signal) (510-7003) | MO | 10 | $4,970.00 | $3,500.00 | $5,817.45 | $3,500.00 | $3,500.00 | $5,500.00 |
| 18 | PTB (fur&inst)(SSCB or CSB)(type 1)or(steel) (512-7085) | LF | 3,060 | $34.00 | $30.00 | $46.19 | $60.00 | $255.00 | $66.00 |
| 19 | PTB (move)(SSCB or CSB)(type 1)or(steel) (512-7086) | LF | 6,960 | $13.00 | $15.00 | $10.92 | $20.00 | $12.00 | $22.00 |
| 20 | PTB (remove)(SSCB or CSB)(type 1)or(steel) (512-7088) | LF | 3,060 | $19.00 | $20.00 | $6.50 | $25.00 | $12.00 | $22.00 |
| 21 | Metal W-beam guard fence (steel post) (540-7002) | LF | 22,489 | $39.00 | $31.71 | $32.36 | $40.00 | $25.23 | $27.00 |
| 22 | Downstream anchor terminal section (540-7015) | EACH | 15 | $1,672.00 | $1,558.75 | $1,337.00 | $1,450.00 | $1,086.00 | $1,760.00 |
| 23 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 2,311 | $60.00 | $91.38 | $90.53 | $85.00 | $68.90 | $99.00 |
| 24 | Metal thrie-beam guard fence (steel post) (540-7020) | EACH | 48 | $3,377.00 | $2,633.75 | $3,249.04 | $2,450.00 | $2,112.00 | $2,420.00 |
| 25 | Remove metal beam guard fence (542-7001) | LF | 7,975 | $4.75 | $2.69 | $4.01 | $2.50 | $6.00 | $3.00 |
| 26 | Guardrail end treatment (install) (544-7001) | EACH | 143 | $3,384.00 | $3,332.50 | $3,604.07 | $3,100.00 | $2,676.00 | $3,520.00 |
| 27 | Guardrail end treatment (remove) (544-7003) | EACH | 48 | $348.00 | $268.75 | $376.59 | $250.00 | $600.00 | $550.00 |
| 28 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 46 | $2,522.00 | $800.00 | $1,215.75 | $1,175.00 | $1,850.00 | $2,200.00 |
| 29 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $800.00 | $1,032.92 | $785.00 | $1,450.00 | $2,200.00 | |
| 30 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 2 | $9,620.00 | $12,500 | $9,698.90 | $9,650.00 | $20,000 | $13,200 |
| 31 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 118 | $28.00 | $20.43 | $52.87 | $19.00 | $88.50 | $44.00 |
| 32 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 186 | $43.00 | $24.73 | $58.73 | $23.00 | $18.50 | $44.00 |
| 33 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 370 | $43.00 | $25.80 | $63.15 | $24.00 | $18.50 | $44.00 |
| 34 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 712 | $6.00 | $6.45 | $7.80 | $6.00 | $4.95 | $22.00 |
| 35 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 45,405 | $1.75 | $1.08 | $1.12 | $1.00 | $0.31 | $2.00 |
| 36 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 288 | $16.00 | $12.90 | $17.55 | $12.00 | $4.36 | $22.00 |
| 37 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 32,400 | $1.75 | $1.08 | $1.07 | $1.00 | $0.31 | $2.00 |
| 38 | Type I high perf PM (W)6"(broken)(090MIL) (666-7289) | LF | 38,258 | $1.00 | $0.91 | $1.04 | $0.85 | $0.77 | $3.30 |
| 39 | Type I high perf PM (Y)6"(broken)(090MIL) (666-7301) | LF | 29,528 | $0.75 | $0.91 | $1.11 | $0.85 | $0.83 | $3.30 |
| 40 | Type I high perf PM (Y)6"(solid)(090MIL) (666-7304) | LF | 34,353 | $1.00 | $0.91 | $1.27 | $0.85 | $0.77 | $3.30 |
| 41 | Pavement sler 6" (666-7347) | LF | 102,139 | $0.50 | $0.43 | $0.47 | $1.37 | $0.65 | $0.50 |
| 42 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 344 | $6.45 | $10.66 | $6.00 | $4.89 | $16.50 | |
| 43 | Reflectorized pavement marker type II-C-C (672-7005) | EACH | 372 | $9.00 | $6.45 | $10.66 | $6.00 | $4.89 | $22.00 |
| 44 | Eliminating existing PM & markers (4") (677-7001) | LF | 77,805 | $1.25 | $0.54 | $0.89 | $6.00 | $0.58 | $1.20 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 1, 2025. Compiled by Mirage Metrics.