TxDOT contract A00193383 bid tabulation

Hazard Elimination & Safety, FM 3084 (FM 1090 to 0.722 Mi N OF SH 35). Let by Texas DOT on July 1, 2025, Calhoun, Yoakum District. 7 bids received; low bid $4,398,168 by Clark Construction of Texas, Inc., -12% against the engineer's estimate of $5,019,826.

Owner
Texas DOT
Letting
01 JUL 2025
Pay items
89
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Clark Construction of Texas, Inc.$4,398,168Low-12%
2Hunter Industries, LTD.$4,520,307+3.0%-10%
3CK Newberry, LLC$4,594,619+4.0%-8.0%
4LCR Total Transport LLC$4,697,559+7.0%-6.0%
5J. Carroll Weaver, Inc.$5,092,932+16%+1.0%
6Cornerstone Paving and Construction, L.L.C.$5,470,799+24%+9.0%
7Matagorda Construction & Materials$7,334,598+67%+46%
TxDOT contract A00193383: bids by rank

Engineer's estimate: $5,019,826.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Clark Construction of Texas, Inc.2. Hunter Industries, LTD.3. CK Newberry, LLC4. LCR Total Transport LLC5. J. Carroll Weaver, Inc.6. Cornerstone Paving and Construction, L.L.C.
1Excavation (roadway) (110-7001)CY9,716$17.00$15.40$18.90$17.00$27.25$18.61$26.00
2Embankment (final)(OC)(type C) (132-7005)CY4,135$18.00$14.48$18.90$25.00$16.25$12.30$31.85
3Blading (150-7002)HR25$150.00$100.00$108.00$150.00$152.00$37.96$200.00
4Broadcast seed (temporary_warm) (164-7005)SY165$1.10$3.00$3.23$8.00$3.20$3.33$0.98
5Broadcast seed (temporary_cool) (164-7006)SY165$1.10$3.00$3.23$8.00$3.20$3.33$0.98
6Drill seed (permanent_rural_clay) (164-7010)SY44,067$0.50$0.25$0.27$0.35$0.25$0.28$0.42
7Drill seed (temporary_warm) (164-7013)SY11,017$0.50$0.16$0.17$0.30$0.20$0.18$0.42
8Drill seed (temporary_cool) (164-7014)SY11,017$0.50$0.20$0.22$0.30$0.20$0.22$0.42
9Vegetative watering (168-7001)TGL372.32$50.00$30.00$21.00$20.00$64.85$31.45$20.00
10FL BS (compacted in place)(tye GR1-2)(final pos) (247-7193)CY12,045$115.00$113.15$101.01$100.00$124.80$134.99$166.00
11FL BS (roadway del)(type E GR 1-2)(final pos) (247-7275)CY5,096$110.00$107.04$101.01$100.00$110.80$124.43$136.60
12Cement (275-7001)TON712$250.00$205.00$209.00$200.00$196.00$213.40$200.00
13Cement TRT (existing material & new base)(8") (275-7007)SY58,609$4.00$2.07$4.44$1.50$1.70$2.29$3.50
14Asphalt (RC-250) (316-7016)GAL9,959$6.00$7.83$5.36$5.00$4.25$5.38$5.90
15Aggregate (type-E, GR-5)(sac-B) (316-7194)CY356$135.00$210.00$111.75$175.00$149.00$158.61$143.30
16Aggregate (type-PE, GR-3)(sac-B) (316-7229)CY617$135.00$141.90$132.89$165.00$170.00$193.80$133.70
17Aggregate (type-PE, GR-4)(sac-B) (316-7232)CY611$135.00$141.21$110.80$135.00$170.00$158.33$139.00
18Asphalt (AC 20-5TR or AC-20XP or CRS-2P) (316-7264)GAL48,005$6.50$4.59$4.13$3.75$4.00$3.92$4.05
19D-GR HMA type D sac-B PG70-22 (exempt) (341-7067)TON250$250.00$244.56$125.60$175.00$172.50$199.79$173.00
20Flexible pavement structure repair(8") (351-7007)SY1,000$100.00$70.15$62.48$72.00$80.00$112.88$75.20
21Flexible pavement structure repair(12") (351-7011)SY1,500$100.00$99.80$90.09$105.00$113.00$143.53$98.30
22Cut and restore pavement (flex base) (400-7009)SY99$75.00$99.55$86.40$75.00$35.50$88.80$80.00
23Cem stabil BKFL (400-7010)CY34$250.00$250.00$270.00$325.00$181.50$349.40$250.00
24Riprap (concrete)(5 in) (432-7002)CY14$700.00$750.00$809.99$900.00$807.00$832.50$750.00
25Riprap (mow strip)(5 in) (432-7014)CY17.20$475.00$750.00$809.99$800.00$783.00$832.50$750.00
26Riprap (stone protection)(12 in) (432-7041)CY11$350.00$180.00$260.02$800.00$325.00$199.80$180.00
27CMP (gal steel 18 in) (460-7003)LF84$110.00$60.00$64.80$125.00$64.00$66.60$60.00
28Concrete box culvert (5 FT X 2 FT) (462-7006)LF101$750.00$700.00$755.99$1,150.00$744.00$777.00$700.00
29RC pipe (CL III)(15 in) (464-7002)LF412$110.00$55.00$59.40$130.00$87.50$61.05$55.00
30RC pipe (CL III)(18 in) (464-7003)LF132$120.00$60.00$64.80$240.00$107.00$66.60$60.00
31RC pipe (CL III)(24 in) (464-7005)LF80$160.00$140.00$151.20$125.00$122.00$155.40$140.00
32Set (type I)(S= 5 FT)(HW= 3 FT)(4:1)(C) (467-7096)EACH16$7,200.00$12,500$13,500$6,000.00$10,500$13,875$12,500
33Set (type II) (15 in) (RCP) (6: 1) (P) (467-7300)EACH30$1,400.00$900.00$971.99$2,500.00$1,100.00$999.00$900.00
34Set (type II) (18 in) (CMP) (6: 1) (P) (467-7304)EACH19$1,750.00$1,000.00$1,079.98$2,400.00$1,200.00$1,110.00$1,000.00
35Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306)EACH4$1,900.00$950.00$1,025.98$2,500.00$1,120.00$1,054.50$950.00
36Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH16$2,000.00$1,000.00$1,079.98$3,000.00$1,425.00$1,110.00$1,000.00
37Set (type II) (18 in) (TP) (6: 1) (P) (467-7312)EACH2$2,100.00$1,000.00$1,079.98$3,250.00$1,418.00$1,110.00$1,000.00
38Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH8$2,500.00$2,500.00$2,699.96$3,000.00$1,660.00$2,775.00$2,500.00
39Thermoplastic pipe (HDPE) (18") (468-7007)LF8$105.00$60.00$64.80$300.00$59.25$67.00$60.00
40Removing structure (small) (496-7036)EACH13$1,500.00$1,200.00$1,200.00$1,500.00$784.00$1,332.00$1,200.00
41Mobilization (500-7001)LS1$500,000$269,000$449,563$425,000$363,000$439,093$300,000
42Barricades, signs and traffic handling (502-7001)MO10$8,500.00$3,200.00$6,750.00$20,000$2,326.00$6,105.00$6,000.00
43Portable changeable message sign (503-7002)EACH2$12,000$12,500$8,174.94$7,500.00$11,500$7,300.39$18,000
44TMA (stationary) (505-7001)DAY20$300.00$200.00$510.93$300.00$283.00$555.00$125.00
45TMA (mobile operation) (505-7003)DAY20$400.00$300.00$766.40$300.00$422.50$555.00$125.00
46Rock filter dams (install) (type 1) (506-7001)LF530$40.00$55.00$59.17$50.00$58.00$61.05$61.00
47Rock filter dams (remove) (506-7011)LF530$10.00$12.00$12.91$20.00$12.60$13.32$24.00
48Sandbags for erosion control (506-7035)EACH100$22.00$14.00$15.06$20.00$14.75$15.54$26.00
49Temporary sediment control fence (install) (506-7039)LF310$4.50$4.75$5.11$7.00$5.00$5.55$8.00
50Temporary sediment control fence (remove) (506-7041)LF310$1.50$1.00$1.08$3.00$1.10$3.33$1.10
51Driveways (concrete) (530-7006)SY54$115.00$250.00$274.71$200.00$120.00$277.50$250.00
52Driveways (surface treat) (530-7016)SY1,699$45.00$39.38$43.60$35.00$36.00$16.65$57.50
53Turnouts (surface treat) (530-7019)SY180$47.00$91.22$43.60$35.00$40.00$14.43$126.10
54Metal W-beam guard fence (timber post) (540-7001)LF100$50.00$35.64$28.60$36.00$28.00$29.42$26.50
55Metal beam guard fence (long span system) (540-7027)EACH1$1,500.00$1,641.00$1,473.36$1,800.00$1,437.00$1,515.15$1,365.00
56Remove metal beam guard fence (542-7001)LF125$5.00$5.00$3.24$5.00$3.25$3.33$3.00
57Guardrail end treatment (install) (544-7001)EACH2$3,500.00$3,703.00$3,292.13$3,800.00$2,160.00$3,385.50$3,050.00
58Guardrail end treatment (remove) (544-7003)EACH2$500.00$300.00$361.60$300.00$353.00$371.85$335.00
59Mailbox install-S (WC-post) type 3 (560-7004)EACH14$225.00$150.00$150.00$150.00$158.00$199.80$150.00
60Mailbox install-D (WC-post) type 3 (560-7005)EACH5$300.00$175.00$175.00$175.00$185.00$255.30$175.00
61Conduit (PVC) (schedule 40) (2") (618-7030)LF1,205$15.00$16.08$17.44$21.00$21.75$23.31$16.10
62Electrical conductor (no.8) bare (620-7007)LF1,205$1.50$2.25$2.44$3.00$3.00$3.07$2.25
63Ground box type A (122311)W/apron (624-7002)EACH1$1,400.00$1,198.02$1,299.51$2,000.00$1,895.00$1,998.00$1,198.00
64Elc SRV type T 120/240 000(NS)GS(N)SP(O) (628-7326)EACH1$6,000.00$5,599.51$6,073.89$2,000.00$2,050.00$2,164.50$5,600.00
65Aluminum signs (type A) (636-7001)SF32$50.00$40.26$25.00$25.00$105.25$37.96$40.30
66Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025)EACH1$1,250.00$825.00$825.00$825.00$1,100.00$1,093.35$1,025.00
67Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH3$1,250.00$875.00$875.00$875.00$1,160.00$1,182.15$1,100.00
68Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH1$1,250.00$975.00$975.00$975.00$1,265.00$1,620.60$1,200.00
69Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057)EACH16$650.00$525.00$525.00$525.00$500.00$577.20$475.00
70Install small roadside sign support and assembly tytwt(1)WS(T) (644-7058)EACH6$650.00$550.00$550.00$550.00$579.00$749.25$550.00
71Remove SM RD SN sup&AM (644-7073)EACH27$100.00$100.00$100.00$100.00$89.50$105.45$85.00
72Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH12$55.00$35.00$35.00$35.00$47.50$33.30$45.00
73Install object marker assembly (OM-2Y)(WC)GND(BI) (658-7057)EACH16$90.00$75.00$75.00$75.00$100.00$81.59$95.00
74Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF119,050$0.50$0.30$0.45$0.50$0.45$0.28$0.45
75Work zone pavement marking non-removing (Y)6"(broken) (662-7036)LF11,704$0.35$0.30$0.68$0.70$0.75$0.61$0.68
76Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF2,585$0.80$0.30$0.78$0.80$0.80$0.61$0.78
77Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH3,643$2.00$2.00$1.63$0.60$2.00$1.12$1.00
78Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266)LF39,730$1.25$1.35$0.78$0.80$0.80$1.33$0.78
79Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270)LF1,310$1.25$1.35$1.10$1.10$1.20$2.16$1.10
80Reflectorized profile pavement marking type I(Y)6"(broken)(100MIL) (666-7274)LF4,879$1.25$1.35$1.10$1.10$1.20$2.16$1.10
81PRFB rumble strip (BLK)(4')(transverse) (668-7001)LF80$50.00$25.00$35.00$35.00$37.00$42.18$35.00
82Prefabricated PM type C (W)(24")(solid) (668-7089)LF24$20.00$20.00$50.00$50.00$53.00$33.30$50.00
83Reflectorized pavement marker type II-A-A (672-7004)EACH260$7.50$5.00$15.00$15.00$16.00$7.77$15.00
84Vehicle signal section (12")LED(yel) (682-7003)EACH2$375.00$179.31$194.50$350.00$350.00$370.74$180.00
85Vehicle signal section (12")LED(red) (682-7005)EACH2$375.00$179.31$194.50$350.00$350.00$370.74$180.00
86Traffic signal CBL (type A)(10 AWG)(3 conductor) (684-7002)LF1,205$3.00$5.31$5.76$3.25$3.40$3.55$5.40
87Install RDSD flash beacon assembly (685-7001)EACH2$5,500.00$5,343.50$5,796.19$8,000.00$8,421.00$8,880.00$5,500.00
88Removing RDSD FLSH BCN AM (solar PWRD) (685-7006)EACH2$625.00$263.93$286.29$850.00$895.00$943.50$265.00
89TMSP radar speed control monitor (6025-7001)EACH2$12,000$10,000$10,219$5,000.00$7,370.00$13,320$10,000
TxDOT contract A00193383: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of July 1, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy