TxDOT contract A00193944 bid tabulation
Rehabilitate Existing Roadway, FM 2377 (SH 342 to FM 983). Let by Texas DOT on August 8, 2025, Ellis, Dallas District. 7 bids received; low bid $6,535,505 by Knife River Corporation - South, -7.3% against the engineer's estimate of $7,053,217.
- Owner
- Texas DOT
- Letting
- 08 AUG 2025
- Pay items
- 104
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Knife River Corporation - South | $6,535,505 | Low | -7.0% |
| 2 | A. L. Helmcamp, Inc. | $6,582,349 | +1.0% | -7.0% |
| 3 | Ed Bell Construction Company | $7,164,925 | +10% | +2.0% |
| 4 | Texas Materials Group, Inc. | $7,327,363 | +12% | +4.0% |
| 5 | Big Creek Construction, LTD. | $7,750,287 | +19% | +10% |
| 6 | Grey Sky Construction LLC | $7,873,764 | +20% | +12% |
| 7 | Road Maker Contractors, LLC | $8,354,326 | +28% | +18% |
Engineer's estimate: $7,053,217.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Knife River Corporation - South | 2. A. L. Helmcamp, Inc. | 3. Ed Bell Construction Company | 4. Texas Materials Group, Inc. | 5. Big Creek Construction, LTD. | 6. Grey Sky Construction LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 171.84 | $1,200.00 | $785.00 | $800.00 | $2,633.00 | $410.00 | $1,500.00 | $4,000.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 18 | $50.00 | $33.00 | $16.00 | $75.00 | $50.00 | $150.00 | $20.00 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 2,411 | $23.00 | $26.00 | $16.00 | $17.50 | $52.57 | $22.00 | $20.00 |
| 4 | Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002) | SY | 2,456 | $9.00 | $8.00 | $12.00 | $13.00 | $26.76 | $24.00 | $20.00 |
| 5 | Excavation (roadway) (110-7001) | CY | 9,989 | $25.00 | $15.00 | $11.00 | $5.00 | $10.00 | $26.00 | $20.00 |
| 6 | Subgr widen (OC) (112-7001) | STA | 171.84 | $400.00 | $375.00 | $110.00 | $750.00 | $400.00 | $1,300.00 | $250.00 |
| 7 | Embankment (final)(OC)(type C) (132-7005) | CY | 16,708 | $26.00 | $21.00 | $20.00 | $10.50 | $35.00 | $24.00 | $30.00 |
| 8 | Backfill (type A or B) (134-7004) | STA | 171.84 | $225.00 | $235.00 | $120.00 | $375.00 | $312.00 | $150.00 | $250.00 |
| 9 | Blading (150-7001) | STA | 171.84 | $250.00 | $100.00 | $250.00 | $200.00 | $163.00 | $130.00 | $250.00 |
| 10 | Block sodding (162-7002) | SY | 238 | $9.00 | $14.00 | $10.00 | $15.00 | $12.99 | $10.00 | $6.00 |
| 11 | Drill seed (permanent_rural_clay) (164-7010) | SY | 98,791 | $0.27 | $0.15 | $0.25 | $0.16 | $0.14 | $0.40 | $0.50 |
| 12 | Drill seed (temporary_warm_cool) (164-7015) | SY | 98,791 | $0.27 | $0.13 | $0.21 | $0.13 | $0.12 | $0.30 | $0.50 |
| 13 | Vegetative watering (168-7001) | TGL | 29,429 | $7.00 | $0.01 | $1.00 | $1.00 | $0.01 | $1.00 | $1.00 |
| 14 | FL BS (compacted in place)(type D GR 1-2) (12") (247-7125) | SY | 56,094 | $26.00 | $29.25 | $31.75 | $30.00 | $40.00 | $38.00 | $25.00 |
| 15 | Rework BS metal (type B)(10")(ord comp) (251-7029) | SY | 1,317 | $2.50 | $12.00 | $3.25 | $10.00 | $37.00 | $30.00 | $6.00 |
| 16 | Rework BS metal (type C)(10")(ord comp) (251-7053) | SY | 40,956 | $2.50 | $2.00 | $2.50 | $3.25 | $3.10 | $3.50 | $6.00 |
| 17 | Cement (275-7001) | TON | 337 | $250.00 | $235.00 | $225.00 | $215.00 | $210.00 | $325.00 | $300.00 |
| 18 | Cement TRT (existing material)(6") (275-7002) | SY | 58,959 | $3.00 | $2.00 | $2.00 | $1.25 | $2.15 | $5.00 | $6.00 |
| 19 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 16,254 | $4.75 | $4.00 | $5.00 | $6.00 | $4.80 | $5.00 | $5.00 |
| 20 | Asphalt (CRS-2P) (316-7012) | GAL | 13,558 | $4.30 | $4.00 | $4.75 | $5.00 | $3.75 | $4.00 | $5.00 |
| 21 | Asphalt (AC-15P, AC-20-5TR or AC-20XP) (316-7071) | GAL | 11,378 | $5.00 | $4.00 | $4.75 | $6.00 | $3.80 | $5.00 | $5.00 |
| 22 | Aggregate (type-B, GR-3)(sac-B) (316-7171) | CY | 518 | $200.00 | $190.00 | $225.00 | $275.00 | $250.00 | $170.00 | $250.00 |
| 23 | SP mixes SP-C sac-B PG64-22 (344-7011) | TON | 5,896 | $135.00 | $130.00 | $140.00 | $163.00 | $150.00 | $120.00 | $150.00 |
| 24 | Planing asphalt concrete pavement(4") (354-7053) | SY | 42,178 | $4.00 | $3.00 | $3.50 | $4.50 | $4.50 | $2.75 | $6.00 |
| 25 | Cut & restore asphalt paving (400-7008) | SY | 90 | $400.00 | $675.00 | $131.00 | $400.00 | $130.00 | $275.00 | $200.00 |
| 26 | Flowable backfill (401-7001) | CY | 8 | $300.00 | $1,450.00 | $420.00 | $1,155.00 | $1,000.00 | $1,200.00 | $350.00 |
| 27 | Trench excavation protection (402-7001) | LF | 33 | $25.00 | $15.00 | $16.00 | $75.00 | $1.00 | $50.00 | $10.00 |
| 28 | Riprap (mow strip)(4 in) (432-7013) | CY | 32 | $800.00 | $700.00 | $761.00 | $1,000.00 | $725.00 | $1,200.00 | $550.00 |
| 29 | Riprap (stone common)(dry)(18 in) (432-7033) | CY | 10 | $330.00 | $460.00 | $444.00 | $402.35 | $400.00 | $325.00 | $185.00 |
| 30 | Riprap (stone common)(dry)(24 in) (432-7034) | CY | 92 | $350.00 | $320.00 | $420.00 | $235.04 | $250.00 | $300.00 | $250.00 |
| 31 | Retrofit rail (type T131RC) (451-7049) | LF | 196 | $350.00 | $310.00 | $210.00 | $235.00 | $199.12 | $400.00 | $250.00 |
| 32 | Concrete box culvert (5 FT X 4 FT) (462-7008) | LF | 192 | $550.00 | $500.00 | $735.00 | $400.00 | $480.00 | $525.00 | $650.00 |
| 33 | Concrete box culvert (4 FT X 3 FT)(extend) (462-7059) | LF | 11 | $1,100.00 | $1,200.00 | $1,155.00 | $900.00 | $1,045.00 | $2,000.00 | $1,000.00 |
| 34 | Concrete box culvert (5 FT X 3 FT)(extend) (462-7062) | LF | 8 | $1,150.00 | $1,500.00 | $1,260.00 | $1,000.00 | $1,150.00 | $2,550.00 | $1,000.00 |
| 35 | Concrete box culvert (6 FT X 3 FT)(extend) (462-7066) | LF | 16 | $1,200.00 | $1,200.00 | $1,470.00 | $1,100.00 | $1,200.00 | $1,500.00 | $1,000.00 |
| 36 | RC pipe (CL III)(18 in) (464-7003) | LF | 1,250 | $101.00 | $77.00 | $63.00 | $68.00 | $59.00 | $105.00 | $85.00 |
| 37 | RC pipe (CL III)(24 in) (464-7005) | LF | 404 | $155.00 | $108.00 | $95.00 | $91.00 | $73.00 | $125.00 | $105.00 |
| 38 | RC pipe (CL III)(30 in) (464-7007) | LF | 102 | $155.00 | $137.00 | $131.00 | $109.00 | $100.00 | $135.00 | $150.00 |
| 39 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 1 | $19,000 | $14,000 | $23,100 | $16,000 | $19,000 | $26,000 | $25,000 |
| 40 | Wingwall (PW - 1) (HW=6 FT) (466-7176) | EACH | 2 | $21,000 | $16,000 | $26,250 | $34,000 | $33,250 | $28,000 | $30,000 |
| 41 | Set (type I)(S= 4 FT)(HW= 5 FT)(3:1)(C) (467-7075) | EACH | 2 | $18,000 | $14,000 | $10,500 | $12,000 | $8,400.00 | $14,000 | $25,000 |
| 42 | Set (type I)(S= 5 FT)(HW= 5 FT)(3:1)(C) (467-7103) | EACH | 2 | $19,000 | $14,000 | $12,600 | $12,000 | $9,600.00 | $15,000 | $30,000 |
| 43 | Set (type I)(S= 6 FT)(HW= 5 FT)(4:1)(C) (467-7133) | EACH | 1 | $20,000 | $16,000 | $15,750 | $15,000 | $12,000 | $24,000 | $40,000 |
| 44 | Set (type II) (18 in) (RCP) (3: 1) (C) (467-7305) | EACH | 2 | $1,400.00 | $1,425.00 | $840.00 | $700.00 | $1,050.00 | $1,425.00 | $1,850.00 |
| 45 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 78 | $1,500.00 | $1,575.00 | $1,050.00 | $900.00 | $1,140.00 | $1,525.00 | $1,250.00 |
| 46 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 1 | $1,750.00 | $1,650.00 | $1,260.00 | $1,100.00 | $1,290.00 | $1,625.00 | $2,000.00 |
| 47 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 30 | $2,250.00 | $1,890.00 | $1,732.50 | $1,500.00 | $1,400.00 | $1,875.00 | $2,200.00 |
| 48 | Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348) | EACH | 8 | $3,550.00 | $4,300.00 | $5,775.00 | $3,500.00 | $3,200.00 | $3,200.00 | $3,000.00 |
| 49 | Removing structure (set) (496-7004) | EACH | 28 | $500.00 | $1,050.00 | $210.00 | $250.00 | $225.00 | $550.00 | $500.00 |
| 50 | Removing structure (wingwall) (496-7005) | EACH | 8 | $1,300.00 | $1,800.00 | $1,050.00 | $4,000.00 | $1,500.00 | $1,400.00 | $2,500.00 |
| 51 | Removing structure (pipe) (496-7007) | LF | 1,335 | $20.00 | $13.00 | $10.50 | $30.00 | $12.00 | $8.00 | $50.00 |
| 52 | Removing structure (box culvert) (496-7008) | LF | 152 | $125.00 | $105.00 | $105.00 | $90.00 | $80.00 | $50.00 | $100.00 |
| 53 | Mobilization (500-7001) | LS | 1 | $667,621 | $650,000 | $600,000 | $731,000 | $700,000 | $725,000 | $700,000 |
| 54 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $10,000 | $17,500 | $8,100.00 | $33,000 | $4,500.00 | $1,500.00 | $8,500.00 |
| 55 | Portable changeable message sign (503-7002) | EACH | 2 | $15,000 | $18,000 | $15,000 | $15,000 | $6,000.00 | $10,000 | $20,000 |
| 56 | TMA (stationary) (505-7001) | DAY | 200 | $275.00 | $50.00 | $275.00 | $100.00 | $200.00 | $200.00 | $250.00 |
| 57 | TMA (mobile operation) (505-7002) | HR | 192 | $75.00 | $40.00 | $70.00 | $50.00 | $10.00 | $200.00 | $55.00 |
| 58 | Rock filter dams (install) (type 3) (506-7003) | LF | 33 | $85.00 | $150.00 | $105.00 | $137.50 | $140.12 | $125.00 | $50.00 |
| 59 | Rock filter dams (remove) (506-7011) | LF | 33 | $20.00 | $24.00 | $26.00 | $33.00 | $23.80 | $20.00 | $20.00 |
| 60 | Construction exits (install) (type 1) (506-7020) | SY | 247 | $35.00 | $43.00 | $41.00 | $38.50 | $42.89 | $48.00 | $50.00 |
| 61 | Construction exits (remove) (506-7024) | SY | 247 | $12.00 | $14.00 | $12.50 | $11.00 | $13.86 | $14.50 | $2.00 |
| 62 | Temporary sediment control fence (install) (506-7039) | LF | 10,280 | $4.75 | $5.75 | $4.20 | $4.00 | $4.20 | $4.50 | $4.00 |
| 63 | Temporary sediment control fence (remove) (506-7041) | LF | 10,280 | $1.25 | $0.95 | $1.05 | $1.00 | $0.93 | $1.25 | $2.00 |
| 64 | Driveways (concrete) (530-7006) | SY | 2,112 | $150.00 | $160.00 | $115.00 | $110.00 | $135.00 | $120.00 | $85.00 |
| 65 | Driveways (ACP) (530-7010) | SY | 2,346 | $65.00 | $63.00 | $125.00 | $63.00 | $65.00 | $70.00 | $55.00 |
| 66 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 34,368 | $0.18 | $0.27 | $0.37 | $0.15 | $0.27 | $0.20 | $0.30 |
| 67 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 17,184 | $0.22 | $0.27 | $0.48 | $0.25 | $0.46 | $0.20 | $0.30 |
| 68 | Metal W-beam guard fence (timber post) (540-7001) | LF | 450 | $30.00 | $31.00 | $23.00 | $23.96 | $21.50 | $32.00 | $30.00 |
| 69 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,500.00 | $2,700.00 | $1,735.00 | $3,023.67 | $2,150.00 | $2,100.00 | $1,820.00 |
| 70 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,300.00 | $3,250.00 | $3,072.00 | $3,141.75 | $2,925.00 | $3,400.00 | $3,850.00 |
| 71 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 30 | $295.00 | $245.00 | $236.00 | $298.20 | $225.00 | $300.00 | $1,100.00 |
| 72 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 2 | $400.00 | $275.00 | $263.00 | $303.53 | $250.00 | $300.00 | $1,100.00 |
| 73 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 2 | $700.00 | $650.00 | $630.00 | $846.68 | $600.00 | $1,100.00 | $1,100.00 |
| 74 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 8 | $30.00 | $110.00 | $105.00 | $50.00 | $50.00 | $100.00 | $30.00 |
| 75 | Electrical conductor (no.12) insulated (620-7004) | LF | 656 | $2.00 | $4.35 | $11.00 | $5.00 | $20.00 | $20.00 | $3.00 |
| 76 | Aluminum signs (type A) (636-7001) | SF | 11 | $50.00 | $38.00 | $37.00 | $50.00 | $35.00 | $40.00 | $50.00 |
| 77 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 34 | $700.00 | $765.00 | $735.00 | $772.13 | $700.00 | $850.00 | $1,100.00 |
| 78 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 7 | $800.00 | $820.00 | $788.00 | $756.15 | $750.00 | $1,000.00 | $1,100.00 |
| 79 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 5 | $950.00 | $930.00 | $893.00 | $921.23 | $850.00 | $1,150.00 | $1,100.00 |
| 80 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 1 | $1,200.00 | $1,040.00 | $998.00 | $1,091.63 | $950.00 | $1,200.00 | $1,100.00 |
| 81 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 10 | $45.00 | $49.00 | $44.00 | $26.63 | $38.00 | $45.00 | $100.00 |
| 82 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 8 | $75.00 | $71.00 | $68.00 | $47.93 | $65.00 | $75.00 | $100.00 |
| 83 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 1,910 | $0.45 | $0.55 | $0.53 | $0.53 | $0.33 | $0.75 | $1.00 |
| 84 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 21,921 | $0.50 | $0.25 | $0.24 | $0.24 | $0.20 | $0.30 | $1.00 |
| 85 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 1,671 | $1.25 | $1.65 | $1.14 | $3.15 | $1.00 | $3.00 | $6.00 |
| 86 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 90 | $2.00 | $2.19 | $2.10 | $2.13 | $1.00 | $2.50 | $1.00 |
| 87 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 385 | $1.50 | $1.09 | $1.05 | $1.07 | $1.25 | $1.25 | $4.00 |
| 88 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 308 | $4.50 | $2.19 | $2.10 | $2.13 | $3.15 | $2.50 | $6.00 |
| 89 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 295 | $8.00 | $7.10 | $6.90 | $6.92 | $6.50 | $8.00 | $20.00 |
| 90 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 2 | $180.00 | $180.00 | $175.00 | $175.73 | $250.00 | $200.00 | $250.00 |
| 91 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 2 | $250.00 | $215.00 | $205.00 | $207.68 | $300.00 | $240.00 | $250.00 |
| 92 | Pavement sler 12" (666-7350) | LF | 240 | $1.50 | $1.09 | $1.05 | $1.07 | $1.20 | $1.25 | $4.00 |
| 93 | Pavement sler 24" (666-7352) | LF | 162 | $2.50 | $2.19 | $2.10 | $2.13 | $2.00 | $2.50 | $12.00 |
| 94 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 42,881 | $0.75 | $0.55 | $0.53 | $0.53 | $0.55 | $0.80 | $0.65 |
| 95 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 1,910 | $0.90 | $0.71 | $0.68 | $0.69 | $0.55 | $0.80 | $0.65 |
| 96 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 32,199 | $0.70 | $0.55 | $0.53 | $0.53 | $0.55 | $0.80 | $0.65 |
| 97 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 371 | $6.00 | $5.15 | $4.99 | $5.06 | $3.98 | $6.00 | $6.00 |
| 98 | Eliminating existing PM & markers (12") (677-7006) | LF | 240 | $2.10 | $3.28 | $3.15 | $3.20 | $2.00 | $4.00 | $6.00 |
| 99 | Eliminating existing PM & markers (24") (677-7008) | LF | 162 | $4.00 | $6.56 | $6.30 | $6.39 | $3.50 | $7.50 | $20.00 |
| 100 | Pavement surface preparation for marking (6") (678-7002) | LF | 360 | $0.20 | $1.09 | $1.05 | $1.07 | $0.35 | $1.20 | $1.00 |
| 101 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 2 | $350.00 | $550.00 | $525.00 | $500.00 | $500.00 | $1,000.00 | $350.00 |
| 102 | Install RDSD flash beacon assembly (685-7001) | EACH | 1 | $6,000.00 | $11,000 | $8,925.00 | $20,000 | $5,000.00 | $10,000 | $12,500 |
| 103 | Remove RDSD flash beacon assembly (685-7003) | EACH | 1 | $1,000.00 | $1,650.00 | $1,050.00 | $5,000.00 | $2,500.00 | $2,500.00 | $6,500.00 |
| 104 | Full - width mowing (730-7019) | CYC | 3 | $2,500.00 | $2,600.00 | $6,000.00 | $5,500.00 | $8,200.00 | $2,300.00 | $2,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 8, 2025. Compiled by Mirage Metrics.