TxDOT contract A00193944 bid tabulation

Rehabilitate Existing Roadway, FM 2377 (SH 342 to FM 983). Let by Texas DOT on August 8, 2025, Ellis, Dallas District. 7 bids received; low bid $6,535,505 by Knife River Corporation - South, -7.3% against the engineer's estimate of $7,053,217.

Owner
Texas DOT
Letting
08 AUG 2025
Pay items
104
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Knife River Corporation - South$6,535,505Low-7.0%
2A. L. Helmcamp, Inc.$6,582,349+1.0%-7.0%
3Ed Bell Construction Company$7,164,925+10%+2.0%
4Texas Materials Group, Inc.$7,327,363+12%+4.0%
5Big Creek Construction, LTD.$7,750,287+19%+10%
6Grey Sky Construction LLC$7,873,764+20%+12%
7Road Maker Contractors, LLC$8,354,326+28%+18%
TxDOT contract A00193944: bids by rank

Engineer's estimate: $7,053,217.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Knife River Corporation - South2. A. L. Helmcamp, Inc.3. Ed Bell Construction Company4. Texas Materials Group, Inc.5. Big Creek Construction, LTD.6. Grey Sky Construction LLC
1Preparing row (100-7002)STA171.84$1,200.00$785.00$800.00$2,633.00$410.00$1,500.00$4,000.00
2Removing concrete (riprap) (104-7006)SY18$50.00$33.00$16.00$75.00$50.00$150.00$20.00
3Removing concrete (driveways) (104-7011)SY2,411$23.00$26.00$16.00$17.50$52.57$22.00$20.00
4Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002)SY2,456$9.00$8.00$12.00$13.00$26.76$24.00$20.00
5Excavation (roadway) (110-7001)CY9,989$25.00$15.00$11.00$5.00$10.00$26.00$20.00
6Subgr widen (OC) (112-7001)STA171.84$400.00$375.00$110.00$750.00$400.00$1,300.00$250.00
7Embankment (final)(OC)(type C) (132-7005)CY16,708$26.00$21.00$20.00$10.50$35.00$24.00$30.00
8Backfill (type A or B) (134-7004)STA171.84$225.00$235.00$120.00$375.00$312.00$150.00$250.00
9Blading (150-7001)STA171.84$250.00$100.00$250.00$200.00$163.00$130.00$250.00
10Block sodding (162-7002)SY238$9.00$14.00$10.00$15.00$12.99$10.00$6.00
11Drill seed (permanent_rural_clay) (164-7010)SY98,791$0.27$0.15$0.25$0.16$0.14$0.40$0.50
12Drill seed (temporary_warm_cool) (164-7015)SY98,791$0.27$0.13$0.21$0.13$0.12$0.30$0.50
13Vegetative watering (168-7001)TGL29,429$7.00$0.01$1.00$1.00$0.01$1.00$1.00
14FL BS (compacted in place)(type D GR 1-2) (12") (247-7125)SY56,094$26.00$29.25$31.75$30.00$40.00$38.00$25.00
15Rework BS metal (type B)(10")(ord comp) (251-7029)SY1,317$2.50$12.00$3.25$10.00$37.00$30.00$6.00
16Rework BS metal (type C)(10")(ord comp) (251-7053)SY40,956$2.50$2.00$2.50$3.25$3.10$3.50$6.00
17Cement (275-7001)TON337$250.00$235.00$225.00$215.00$210.00$325.00$300.00
18Cement TRT (existing material)(6") (275-7002)SY58,959$3.00$2.00$2.00$1.25$2.15$5.00$6.00
19Prime coat(MC-30 or AE-P) (310-7013)GAL16,254$4.75$4.00$5.00$6.00$4.80$5.00$5.00
20Asphalt (CRS-2P) (316-7012)GAL13,558$4.30$4.00$4.75$5.00$3.75$4.00$5.00
21Asphalt (AC-15P, AC-20-5TR or AC-20XP) (316-7071)GAL11,378$5.00$4.00$4.75$6.00$3.80$5.00$5.00
22Aggregate (type-B, GR-3)(sac-B) (316-7171)CY518$200.00$190.00$225.00$275.00$250.00$170.00$250.00
23SP mixes SP-C sac-B PG64-22 (344-7011)TON5,896$135.00$130.00$140.00$163.00$150.00$120.00$150.00
24Planing asphalt concrete pavement(4") (354-7053)SY42,178$4.00$3.00$3.50$4.50$4.50$2.75$6.00
25Cut & restore asphalt paving (400-7008)SY90$400.00$675.00$131.00$400.00$130.00$275.00$200.00
26Flowable backfill (401-7001)CY8$300.00$1,450.00$420.00$1,155.00$1,000.00$1,200.00$350.00
27Trench excavation protection (402-7001)LF33$25.00$15.00$16.00$75.00$1.00$50.00$10.00
28Riprap (mow strip)(4 in) (432-7013)CY32$800.00$700.00$761.00$1,000.00$725.00$1,200.00$550.00
29Riprap (stone common)(dry)(18 in) (432-7033)CY10$330.00$460.00$444.00$402.35$400.00$325.00$185.00
30Riprap (stone common)(dry)(24 in) (432-7034)CY92$350.00$320.00$420.00$235.04$250.00$300.00$250.00
31Retrofit rail (type T131RC) (451-7049)LF196$350.00$310.00$210.00$235.00$199.12$400.00$250.00
32Concrete box culvert (5 FT X 4 FT) (462-7008)LF192$550.00$500.00$735.00$400.00$480.00$525.00$650.00
33Concrete box culvert (4 FT X 3 FT)(extend) (462-7059)LF11$1,100.00$1,200.00$1,155.00$900.00$1,045.00$2,000.00$1,000.00
34Concrete box culvert (5 FT X 3 FT)(extend) (462-7062)LF8$1,150.00$1,500.00$1,260.00$1,000.00$1,150.00$2,550.00$1,000.00
35Concrete box culvert (6 FT X 3 FT)(extend) (462-7066)LF16$1,200.00$1,200.00$1,470.00$1,100.00$1,200.00$1,500.00$1,000.00
36RC pipe (CL III)(18 in) (464-7003)LF1,250$101.00$77.00$63.00$68.00$59.00$105.00$85.00
37RC pipe (CL III)(24 in) (464-7005)LF404$155.00$108.00$95.00$91.00$73.00$125.00$105.00
38RC pipe (CL III)(30 in) (464-7007)LF102$155.00$137.00$131.00$109.00$100.00$135.00$150.00
39Wingwall (PW - 1) (HW=5 FT) (466-7175)EACH1$19,000$14,000$23,100$16,000$19,000$26,000$25,000
40Wingwall (PW - 1) (HW=6 FT) (466-7176)EACH2$21,000$16,000$26,250$34,000$33,250$28,000$30,000
41Set (type I)(S= 4 FT)(HW= 5 FT)(3:1)(C) (467-7075)EACH2$18,000$14,000$10,500$12,000$8,400.00$14,000$25,000
42Set (type I)(S= 5 FT)(HW= 5 FT)(3:1)(C) (467-7103)EACH2$19,000$14,000$12,600$12,000$9,600.00$15,000$30,000
43Set (type I)(S= 6 FT)(HW= 5 FT)(4:1)(C) (467-7133)EACH1$20,000$16,000$15,750$15,000$12,000$24,000$40,000
44Set (type II) (18 in) (RCP) (3: 1) (C) (467-7305)EACH2$1,400.00$1,425.00$840.00$700.00$1,050.00$1,425.00$1,850.00
45Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH78$1,500.00$1,575.00$1,050.00$900.00$1,140.00$1,525.00$1,250.00
46Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325)EACH1$1,750.00$1,650.00$1,260.00$1,100.00$1,290.00$1,625.00$2,000.00
47Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH30$2,250.00$1,890.00$1,732.50$1,500.00$1,400.00$1,875.00$2,200.00
48Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348)EACH8$3,550.00$4,300.00$5,775.00$3,500.00$3,200.00$3,200.00$3,000.00
49Removing structure (set) (496-7004)EACH28$500.00$1,050.00$210.00$250.00$225.00$550.00$500.00
50Removing structure (wingwall) (496-7005)EACH8$1,300.00$1,800.00$1,050.00$4,000.00$1,500.00$1,400.00$2,500.00
51Removing structure (pipe) (496-7007)LF1,335$20.00$13.00$10.50$30.00$12.00$8.00$50.00
52Removing structure (box culvert) (496-7008)LF152$125.00$105.00$105.00$90.00$80.00$50.00$100.00
53Mobilization (500-7001)LS1$667,621$650,000$600,000$731,000$700,000$725,000$700,000
54Barricades, signs and traffic handling (502-7001)MO12$10,000$17,500$8,100.00$33,000$4,500.00$1,500.00$8,500.00
55Portable changeable message sign (503-7002)EACH2$15,000$18,000$15,000$15,000$6,000.00$10,000$20,000
56TMA (stationary) (505-7001)DAY200$275.00$50.00$275.00$100.00$200.00$200.00$250.00
57TMA (mobile operation) (505-7002)HR192$75.00$40.00$70.00$50.00$10.00$200.00$55.00
58Rock filter dams (install) (type 3) (506-7003)LF33$85.00$150.00$105.00$137.50$140.12$125.00$50.00
59Rock filter dams (remove) (506-7011)LF33$20.00$24.00$26.00$33.00$23.80$20.00$20.00
60Construction exits (install) (type 1) (506-7020)SY247$35.00$43.00$41.00$38.50$42.89$48.00$50.00
61Construction exits (remove) (506-7024)SY247$12.00$14.00$12.50$11.00$13.86$14.50$2.00
62Temporary sediment control fence (install) (506-7039)LF10,280$4.75$5.75$4.20$4.00$4.20$4.50$4.00
63Temporary sediment control fence (remove) (506-7041)LF10,280$1.25$0.95$1.05$1.00$0.93$1.25$2.00
64Driveways (concrete) (530-7006)SY2,112$150.00$160.00$115.00$110.00$135.00$120.00$85.00
65Driveways (ACP) (530-7010)SY2,346$65.00$63.00$125.00$63.00$65.00$70.00$55.00
66Mill rumble strips (asphalt) (shoulder) (533-7001)LF34,368$0.18$0.27$0.37$0.15$0.27$0.20$0.30
67Mill rumble strips (asphalt) (centerline) (533-7002)LF17,184$0.22$0.27$0.48$0.25$0.46$0.20$0.30
68Metal W-beam guard fence (timber post) (540-7001)LF450$30.00$31.00$23.00$23.96$21.50$32.00$30.00
69Metal beam guard fence trans (thrie-beam) (540-7005)EACH4$2,500.00$2,700.00$1,735.00$3,023.67$2,150.00$2,100.00$1,820.00
70Guardrail end treatment (install) (544-7001)EACH4$3,300.00$3,250.00$3,072.00$3,141.75$2,925.00$3,400.00$3,850.00
71Mailbox install-S (TWW-post) type 4 (560-7008)EACH30$295.00$245.00$236.00$298.20$225.00$300.00$1,100.00
72Mailbox install-D (TWW-post) type 4 (560-7009)EACH2$400.00$275.00$263.00$303.53$250.00$300.00$1,100.00
73Mailbox install-M (TWW-post) type 4 (560-7010)EACH2$700.00$650.00$630.00$846.68$600.00$1,100.00$1,100.00
74Conduit (PVC) (schedule 40) (2") (618-7030)LF8$30.00$110.00$105.00$50.00$50.00$100.00$30.00
75Electrical conductor (no.12) insulated (620-7004)LF656$2.00$4.35$11.00$5.00$20.00$20.00$3.00
76Aluminum signs (type A) (636-7001)SF11$50.00$38.00$37.00$50.00$35.00$40.00$50.00
77Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH34$700.00$765.00$735.00$772.13$700.00$850.00$1,100.00
78Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002)EACH7$800.00$820.00$788.00$756.15$750.00$1,000.00$1,100.00
79Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH5$950.00$930.00$893.00$921.23$850.00$1,150.00$1,100.00
80Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH1$1,200.00$1,040.00$998.00$1,091.63$950.00$1,200.00$1,100.00
81Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH10$45.00$49.00$44.00$26.63$38.00$45.00$100.00
82Install object marker assembly (OM-2Z)(WFLX)GND (658-7058)EACH8$75.00$71.00$68.00$47.93$65.00$75.00$100.00
83Work zone pavement marking non-removing (Y)6"(broken) (662-7036)LF1,910$0.45$0.55$0.53$0.53$0.33$0.75$1.00
84Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF21,921$0.50$0.25$0.24$0.24$0.20$0.30$1.00
85Work zone pavement marking SHT terminal (tab)type Y (662-7113)EACH1,671$1.25$1.65$1.14$3.15$1.00$3.00$6.00
86Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009)LF90$2.00$2.19$2.10$2.13$1.00$2.50$1.00
87Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF385$1.50$1.09$1.05$1.07$1.25$1.25$4.00
88Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030)LF308$4.50$2.19$2.10$2.13$3.15$2.50$6.00
89Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF295$8.00$7.10$6.90$6.92$6.50$8.00$20.00
90Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH2$180.00$180.00$175.00$175.73$250.00$200.00$250.00
91Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066)EACH2$250.00$215.00$205.00$207.68$300.00$240.00$250.00
92Pavement sler 12" (666-7350)LF240$1.50$1.09$1.05$1.07$1.20$1.25$4.00
93Pavement sler 24" (666-7352)LF162$2.50$2.19$2.10$2.13$2.00$2.50$12.00
94Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF42,881$0.75$0.55$0.53$0.53$0.55$0.80$0.65
95Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF1,910$0.90$0.71$0.68$0.69$0.55$0.80$0.65
96Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF32,199$0.70$0.55$0.53$0.53$0.55$0.80$0.65
97Reflectorized pavement marker type II-A-A (672-7004)EACH371$6.00$5.15$4.99$5.06$3.98$6.00$6.00
98Eliminating existing PM & markers (12") (677-7006)LF240$2.10$3.28$3.15$3.20$2.00$4.00$6.00
99Eliminating existing PM & markers (24") (677-7008)LF162$4.00$6.56$6.30$6.39$3.50$7.50$20.00
100Pavement surface preparation for marking (6") (678-7002)LF360$0.20$1.09$1.05$1.07$0.35$1.20$1.00
101Vehicle signal section (12")LED(yel) (682-7003)EACH2$350.00$550.00$525.00$500.00$500.00$1,000.00$350.00
102Install RDSD flash beacon assembly (685-7001)EACH1$6,000.00$11,000$8,925.00$20,000$5,000.00$10,000$12,500
103Remove RDSD flash beacon assembly (685-7003)EACH1$1,000.00$1,650.00$1,050.00$5,000.00$2,500.00$2,500.00$6,500.00
104Full - width mowing (730-7019)CYC3$2,500.00$2,600.00$6,000.00$5,500.00$8,200.00$2,300.00$2,500.00
TxDOT contract A00193944: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of August 8, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy