TxDOT contract A00194194 bid tabulation
Bridge Replacement, COLOGNE RD (At Draw to STR# AA01-02-001 (Cologne Rd)). Let by Texas DOT on May 1, 2025, Victoria, Yoakum District. 7 bids received; low bid $1,925,463 by STX Civil, -14% against the engineer's estimate of $2,250,730.
- Owner
- Texas DOT
- Letting
- 01 MAY 2025
- Pay items
- 50
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | STX Civil | $1,925,463 | Low | -14% |
| 2 | Acme Bridge Company, Inc. | $2,042,063 | +6.0% | -9.0% |
| 3 | E-Z Bel Construction, LLC | $2,194,867 | +14% | -2.0% |
| 4 | Texas Steel Industrial Placing, LLC | $2,198,047 | +14% | -2.0% |
| 5 | Presidio Contracting, LLC | $2,226,203 | +16% | -1.0% |
| 6 | Dean Word Company, LTD. | $2,399,058 | +25% | +7.0% |
| 7 | CK Newberry, LLC | $2,965,231 | +54% | +32% |
Engineer's estimate: $2,250,730.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. STX Civil | 2. Acme Bridge Company, Inc. | 3. E-Z Bel Construction, LLC | 4. Texas Steel Industrial Placing, LLC | 5. Presidio Contracting, LLC | 6. Dean Word Company, LTD. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 11.60 | $3,500.00 | $2,200.00 | $2,910.00 | $2,100.00 | $3,000.00 | $5,000.00 | $7,900.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 697 | $32.50 | $12.00 | $24.00 | $18.00 | $25.00 | $58.05 | $63.00 |
| 3 | Excavation (channel) (110-7002) | CY | 1,334 | $26.00 | $15.00 | $23.10 | $29.00 | $25.00 | $46.90 | $40.00 |
| 4 | Embankment (final)(OC)(type C) (132-7005) | CY | 341 | $60.00 | $32.00 | $28.80 | $35.00 | $30.00 | $30.80 | $74.50 |
| 5 | Blading (150-7002) | HR | 48 | $120.00 | $110.00 | $70.60 | $175.00 | $100.00 | $50.00 | $31.00 |
| 6 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 4,368 | $1.00 | $1.00 | $1.50 | $2.00 | $1.43 | $1.00 | $2.00 |
| 7 | Broadcast seed (temporary_warm) (164-7005) | SY | 1,092 | $2.00 | $1.00 | $3.55 | $2.00 | $3.33 | $1.95 | $4.50 |
| 8 | Broadcast seed (temporary_cool) (164-7006) | SY | 1,092 | $2.00 | $1.00 | $3.55 | $2.00 | $3.33 | $1.95 | $4.50 |
| 9 | Vegetative watering (168-7001) | TGL | 56.20 | $90.00 | $50.00 | $38.30 | $25.00 | $50.00 | $85.00 | $142.00 |
| 10 | FL BS (compacted in place)(type E GR 5)(final pos) (247-7196) | CY | 698 | $140.00 | $120.00 | $168.00 | $116.00 | $145.00 | $171.40 | $169.50 |
| 11 | Asphalt (RC-250) (316-7016) | GAL | 599 | $15.00 | $11.00 | $14.80 | $18.00 | $12.00 | $18.90 | $15.00 |
| 12 | Aggregate (type-E, GR-5)(sac-B) (316-7194) | CY | 24.20 | $1,250.00 | $800.00 | $1,420.00 | $1,127.00 | $1,100.00 | $1,185.00 | $1,025.00 |
| 13 | Aggregate (type-PE, GR-4)(sac-B) (316-7232) | CY | 25.30 | $1,250.00 | $800.00 | $1,350.00 | $1,090.00 | $1,100.00 | $1,145.00 | $1,025.00 |
| 14 | Asphalt (AC 20-5TR or AC-20XP or CRS-2P) (316-7264) | GAL | 1,015 | $15.00 | $12.00 | $11.60 | $16.00 | $12.00 | $16.45 | $9.00 |
| 15 | Cem stabil BKFL (400-7010) | CY | 75 | $240.00 | $180.00 | $302.00 | $425.00 | $250.00 | $380.00 | $311.00 |
| 16 | Drilled shaft (24 in) (416-7004) | LF | 1,083 | $265.00 | $280.00 | $229.00 | $250.00 | $315.00 | $255.35 | $245.50 |
| 17 | Class C concrete (abutment) (420-7012) | CY | 57.40 | $1,500.00 | $1,800.00 | $1,330.00 | $2,200.00 | $1,625.00 | $1,528.00 | $1,789.50 |
| 18 | Class C concrete (cap) (420-7022) | CY | 21.10 | $1,600.00 | $2,120.00 | $1,890.00 | $2,300.00 | $1,750.00 | $1,885.00 | $2,574.50 |
| 19 | Class C concrete (column) (420-7038) | CY | 8.90 | $1,800.00 | $2,000.00 | $1,760.00 | $3,300.00 | $1,750.00 | $2,125.00 | $4,121.50 |
| 20 | Reinforced concrete slab (slab beam) (422-7007) | SF | 6,437 | $30.00 | $28.00 | $24.90 | $29.00 | $33.00 | $29.10 | $38.50 |
| 21 | Prestressed concrete slab beam (5SB12) (425-7017) | LF | 818.92 | $252.00 | $245.00 | $279.00 | $280.00 | $260.00 | $249.60 | $294.50 |
| 22 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 420 | $245.00 | $277.00 | $280.00 | $275.00 | $249.60 | $293.00 | |
| 23 | Riprap (stone protection)(18 in) (432-7043) | CY | 583 | $220.00 | $160.00 | $212.00 | $241.00 | $220.00 | $197.10 | $160.00 |
| 24 | Riprap (stone protection)(21 in) (432-7044) | CY | 640 | $175.00 | $217.00 | $261.00 | $190.00 | $197.10 | $140.50 | |
| 25 | Rail (type T223) (450-7008) | LF | 546 | $168.00 | $160.00 | $126.00 | $200.00 | $150.00 | $167.55 | $230.00 |
| 26 | Armor joint (sealed) (454-7003) | LF | 162 | $155.00 | $150.00 | $169.00 | $126.00 | $100.00 | $115.50 | $169.00 |
| 27 | RC pipe (CL III)(18 in) (464-7003) | LF | 157 | $90.00 | $94.30 | $81.00 | $100.00 | $54.10 | $100.50 | |
| 28 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 1 | $2,000.00 | $2,380.00 | $2,800.00 | $3,000.00 | $3,455.00 | $4,232.00 | |
| 29 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 3 | $37,500 | $25,000 | $17,000 | $23,133 | $30,000 | $35,100 | $25,500 |
| 30 | Removing structure (small) (496-7036) | EACH | 1 | $100.00 | $3,190.00 | $501.00 | $2,500.00 | $1,250.00 | $355.00 | |
| 31 | Mobilization (500-7001) | LS | 1 | $200,000 | $152,500 | $163,000 | $170,000 | $220,000 | $200,000 | $200,000 |
| 32 | Barricades, signs and traffic handling (502-7001) | MO | 15 | $3,500.00 | $1,500.00 | $4,180.00 | $1,500.00 | $1,315.00 | $3,260.00 | $1,223.00 |
| 33 | Rock filter dams (install) (type 1) (506-7006) | CY | 18 | $320.00 | $220.00 | $417.00 | $180.00 | $150.00 | $413.00 | $524.50 |
| 34 | Rock filter dams (remove) (506-7012) | CY | 18 | $70.00 | $30.00 | $53.00 | $24.00 | $30.00 | $50.00 | $66.50 |
| 35 | Sandbags for erosion control (506-7035) | EACH | 90 | $25.00 | $1.00 | $4.25 | $20.00 | $10.00 | $4.20 | $5.50 |
| 36 | Temporary sediment control fence (install) (506-7039) | LF | 2,766 | $4.50 | $6.00 | $5.00 | $4.00 | $4.00 | $5.00 | $6.50 |
| 37 | Temporary sediment control fence (remove) (506-7041) | LF | 2,766 | $1.50 | $1.00 | $1.05 | $2.00 | $1.00 | $1.00 | $1.50 |
| 38 | Metal W-beam guard fence (timber post) (540-7001) | LF | 225 | $38.50 | $30.00 | $29.70 | $27.00 | $30.00 | $27.85 | $40.00 |
| 39 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 10 | $1,875.00 | $1,500.00 | $1,270.00 | $1,570.00 | $1,650.00 | $1,660.00 | $1,468.00 |
| 40 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,500.00 | $1,490.00 | $1,682.00 | $1,500.00 | $1,280.00 | $2,185.00 | |
| 41 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,500.00 | $3,200.00 | $3,290.00 | $3,420.00 | $3,250.00 | $3,125.00 | $4,670.50 |
| 42 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 2 | $30,500 | $31,300 | $29,500 | $30,000 | $32,000 | $40,031 | |
| 43 | Wire fence (type A) (552-7001) | LF | 540 | $20.00 | $21.20 | $34.00 | $30.00 | $25.75 | $45.50 | |
| 44 | Wire fence (type C) (552-7003) | LF | 106 | $20.00 | $21.20 | $35.00 | $35.00 | $35.20 | $46.50 | |
| 45 | Wire fence (water gap) (552-7010) | LF | 80 | $30.00 | $53.00 | $60.00 | $50.00 | $48.85 | $80.00 | |
| 46 | Wire fence (remove) (552-7011) | LF | 106 | $0.10 | $5.30 | $13.00 | $10.00 | $9.50 | $16.50 | |
| 47 | Install small roadside sign support and assembly tytwt(1)UA(T) (644-7054) | EACH | 4 | $600.00 | $1,050.00 | $740.00 | $800.00 | $783.00 | $1,201.00 | |
| 48 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 1 | $600.00 | $700.00 | $450.00 | $500.00 | $489.00 | $800.50 | |
| 49 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 18 | $75.00 | $20.00 | $29.20 | $25.00 | $50.00 | $25.75 | $33.50 |
| 50 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 18 | $75.00 | $20.00 | $29.20 | $26.00 | $50.00 | $31.50 | $33.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 1, 2025. Compiled by Mirage Metrics.