Bridge Replacement, CR 1170 (At Sikes Creek to .). Let by Texas DOT on August 6, 2026, Houston, Lufkin District. 6 bids received; low bid $2,809,388 by THK Construction LLC, +14% against the engineer's estimate of $2,474,314.

Owner
Texas DOT
Letting
06 AUG 2026
Pay items
49
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1THK Construction LLC$2,809,388Low+14%
2Garret Shields Infrastructure$2,983,618+6.0%+21%
3Skyline Bridge LLC$3,029,411+8.0%+22%
4Longview Bridge and Road, LTD.$3,105,504+11%+26%
5A. L. Helmcamp, Inc.$3,320,376+18%+34%
6Hodges and Son Construction Company, Inc.$3,422,483+22%+38%
TxDOT contract A00194392: bids by rank

Engineer's estimate: $2,474,314.

Bid tabulation

LinePay itemUnitQuantityEstimate1. THK Construction LLC2. Garret Shields Infrastructure3. Skyline Bridge LLC4. Longview Bridge and Road, LTD.5. A. L. Helmcamp, Inc.6. Hodges and Son Construction Company, Inc.
1Preparing row (100-7002)STA19.22$1,200.00$1,500.00$1,000.00$2,500.00$1,000.00$3,500.00$2,800.00
2Excavation (roadway) (110-7001)CY3,030$10.00$18.00$30.00$18.00$8.00$37.00$6.00
3Embankment (final)(OC)(type B) (132-7003)CY1,331$15.00$18.00$40.00$35.00$10.00$27.00$20.00
4Block sodding (162-7002)SY500$6.00$7.35$8.00$10.00$8.75$8.00$8.00
5Bond fiber MTRX seed (permanent)(rural)(sand) (164-7076)SY4,715$0.60$0.63$0.15$2.50$2.30$0.75$1.00
6Bond fiber MTRX seed (temporary)(warm) (164-7077)SY2,358$0.15$0.53$0.50$2.50$2.30$0.60$1.00
7Bond fiber MTRX seed (temporary)(cool) (164-7078)SY2,358$0.15$0.53$0.50$2.50$2.30$0.60$1.00
8Vegetative watering (168-7001)TGL198.80$5.00$1.00$25.00$1.00$16.50$70.00$1.00
9FL BS (compacted in place)(type D GR 1-2) (6") (247-7056)SY3,503$25.00$45.00$30.00$45.00$21.00$40.00$45.00
10Cem stabil BKFL (400-7010)CY322$210.00$275.00$200.00$300.00$253.00$220.00$275.00
11Drilled shaft (24 in) (416-7004)LF555$178.65$200.00$235.00$330.00$150.00$245.00
12Drilled shaft (30 in) (416-7005)LF930$250.00$268.09$300.00$245.00$370.00$170.00$275.00
13Class C concrete (abutment) (420-7012)CY130.20$950.00$975.00$100.00$1,350.00$1,185.00$1,700.00$1,800.00
14Reinforced concrete slab (box beam) (422-7005)SF5,626$20.00$24.00$25.00$25.00$25.00$38.00$28.00
15Reinforced concrete slab (slab beam) (422-7007)SF2,600$28.00$20.00$28.00$30.00$48.00$28.00
16Shear key (422-7020)CY40.70$600.00$800.00$300.00$900.00$450.00$650.00$600.00
17Prestressed concrete slab beam (5SB15) (425-7019)LF500$259.05$300.00$375.00$368.00$330.00$360.00
18Prestressed concrete box beam (4B20) (425-7026)LF496$310.80$340.00$410.00$368.00$330.00$350.00
19Prestressed concrete box beam (5B20) (425-7027)LF248$326.26$340.00$325.00$720.00$370.00$350.00
20Prestressed concrete box beam (4B34) (425-7030)LF358$240.00$307.83$400.00$440.00$330.00$350.00$415.00
21Prestressed concrete box beam (5B34) (425-7031)LF179$240.00$332.50$400.00$370.00$655.00$410.00$415.00
22Riprap (stone protection)(24 in) (432-7045)CY2,246$150.00$160.00$230.00$150.00$220.00$160.00$200.00
23Rail (type T223) (450-7008)LF786$150.00$175.00$100.00$125.00$164.00$250.00$200.00
24Type A joint (454-7001)LF267$50.00$200.00$30.00$75.00$43.00$55.00$10.00
25Removing structure (bridge 0 - 99 FT length) (496-7009)EACH5$10,000$40,000$25,000$12,000$12,000$23,000$10,000
26Mobilization (500-7001)LS1$250,000$210,000$250,000$250,000$100,000$330,000$305,000
27Barricades, signs and traffic handling (502-7001)MO22$1,500.00$1,614.53$10,000$2,000.00$1,600.00$4,000.00$2,000.00
28Portable changeable message sign (503-7002)EACH10$7,500.00$2,000.00$1,000.00$5,000.00$6,600.00$9,700.00$35,000
29Rock filter dams (install) (type 2) (506-7002)LF195$40.00$30.00$25.00$50.00$37.40$42.00$1.00
30Rock filter dams (remove) (506-7011)LF195$10.00$1.00$5.00$10.00$17.60$9.00$1.00
31Construction exits (install) (type 1) (506-7020)SY560$35.00$1.00$20.00$10.00$44.00$39.00$1.00
32Construction exits (remove) (506-7024)SY560$10.00$1.00$5.00$1.00$17.60$10.00$1.00
33Construction perimeter fence (506-7034)LF198$6.00$10.00$6.00$12.50$5.50$5.00$1.00
34Temporary sediment control fence (install) (506-7039)LF4,100$4.00$3.50$5.00$4.00$4.00$4.00$1.00
35Temporary sediment control fence (remove) (506-7041)LF4,100$1.00$1.00$1.00$2.00$0.80$0.85$1.00
36Driveways (base) (530-7015)SY35$50.00$40.00$120.00$60.00$21.00$135.00$120.00
37Metal W-beam guard fence (timber post) (540-7001)LF425$22.00$30.44$35.00$28.00$32.00$26.50$26.00
38Metal beam guard fence trans (thrie-beam) (540-7005)EACH10$1,200.00$1,785.00$1,500.00$1,900.00$2,035.00$1,750.00$1,800.00
39Downstream anchor terminal section (540-7015)EACH10$1,100.00$1,417.50$1,200.00$1,500.00$1,485.00$1,350.00$1,500.00
40Metal beam guard fence trans (non - sym) (540-7016)EACH10$625.00$997.50$1,000.00$1,200.00$1,050.00$795.00$1,000.00
41Guardrail end treatment (install) (544-7001)EACH10$2,500.00$3,360.00$3,500.00$3,600.00$3,520.00$3,400.00$3,200.00
42Gate (remove) (550-7016)EACH1$815.00$250.00$500.00$500.00$265.00$775.00$500.00
43Wire fence (type A) (552-7001)LF406$32.00$25.00$15.00$30.00$26.50$30.00$20.00
44Wire fence (type C) (552-7003)LF1,908$20.00$15.00$25.00$27.75$28.00$20.00
45Gate (type 1) (552-7006)EACH1$1,400.00$500.00$1,000.00$5,000.00$2,500.00$2,300.00$2,000.00
46Wire fence (water gap) (552-7010)LF493$60.00$20.00$60.00$100.00$79.00$3.50$22.00
47Remove SM RD SN sup&AM (644-7073)EACH10$100.00$250.00$100.00$100.00$132.00$270.00$50.00
48Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH28$50.00$18.90$20.00$30.00$20.00$26.50$20.00
49Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH42$25.00$26.25$20.00$30.00$27.50$32.50$25.00
TxDOT contract A00194392: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of August 6, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy