TxDOT contract A00196394 bid tabulation
Bridge Replacement, FM 71 (At Lacy Creek to .). Let by Texas DOT on October 9, 2025, Titus, Atlanta District. 7 bids received; low bid $1,331,903 by THK Construction LLC, -4.2% against the engineer's estimate of $1,390,646.
- Owner
- Texas DOT
- Letting
- 09 OCT 2025
- Pay items
- 56
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | THK Construction LLC | $1,331,903 | Low | -4.0% |
| 2 | Highway 19 Construction LLC | $1,411,903 | +6.0% | +2.0% |
| 3 | Longview Bridge and Road, LTD. | $1,456,227 | +9.0% | +5.0% |
| 4 | East Texas Bridge, Inc. | $1,456,288 | +9.0% | +5.0% |
| 5 | True Roads Construction, LLC | $1,503,897 | +13% | +8.0% |
| 6 | Hodges and Son Construction Company, Inc. | $1,515,332 | +14% | +9.0% |
| 7 | Skyline Bridge LLC | $1,571,258 | +18% | +13% |
Engineer's estimate: $1,390,646.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. THK Construction LLC | 2. Highway 19 Construction LLC | 3. Longview Bridge and Road, LTD. | 4. East Texas Bridge, Inc. | 5. True Roads Construction, LLC | 6. Hodges and Son Construction Company, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7001) | ACRE | 0.52 | $10,000 | $19,231 | $5,000.00 | $20,000 | $38,000 | $14,000 | $38,000 |
| 2 | Remove (8"-12") TRT/untrt base & asphalt pavement (105-7008) | SY | 212 | $90.00 | $25.00 | $15.00 | $35.00 | $20.00 | $50.00 | $20.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 561 | $25.00 | $45.00 | $25.00 | $23.00 | $15.00 | $13.50 | $30.00 |
| 4 | Embankment (final)(DC)(type C) (132-7006) | CY | 1,985 | $22.00 | $45.00 | $30.00 | $28.00 | $22.00 | $15.00 | $20.00 |
| 5 | Furn & place topsoil (4") (160-7002) | SY | 4,016 | $5.50 | $3.00 | $3.00 | $3.00 | $4.00 | $4.25 | $3.00 |
| 6 | Bond fiber MTRX seed (permanent)(rural)(sand) (164-7073) | SY | 4,016 | $1.20 | $0.59 | $0.75 | $0.70 | $0.60 | $0.65 | $1.00 |
| 7 | Bond fiber MTRX seed (temporary)(warm) (164-7077) | SY | 2,008 | $0.75 | $0.59 | $0.75 | $0.63 | $0.60 | $0.65 | $0.20 |
| 8 | Bond fiber MTRX seed (temporary)(cool) (164-7078) | SY | 2,008 | $0.75 | $0.59 | $0.75 | $0.70 | $0.60 | $0.65 | $1.00 |
| 9 | Vegetative watering (168-7001) | TGL | 131 | $160.00 | $10.00 | $10.00 | $15.00 | $20.00 | $50.00 | $1.00 |
| 10 | Soil ret BLKT(SL_steep_sand_short) (169-7007) | SY | 190 | $2.50 | $1.08 | $5.00 | $1.00 | $1.25 | $1.20 | $3.00 |
| 11 | FL BS (roadway del)(type D GR 4)(final pos) (247-7273) | CY | 339 | $100.00 | $88.14 | $123.00 | $120.00 | $120.00 | $120.00 | $95.00 |
| 12 | Rework BS metal(type C)(14")(density control) (251-7086) | SY | 1,540 | $25.00 | $10.00 | $9.00 | $4.00 | $15.00 | $9.00 | $8.00 |
| 13 | Cement (275-7001) | TON | 42 | $325.00 | $400.00 | $350.00 | $300.00 | $275.00 | $295.00 | $300.00 |
| 14 | Cement TRT (existing material & new base)(10") (275-7008) | SY | 2,506 | $9.00 | $8.00 | $5.00 | $4.00 | $4.50 | $5.50 | $6.50 |
| 15 | Prime coat & blotter (MC-30) (310-7010) | GAL | 627 | $15.00 | $12.90 | $15.00 | $6.50 | $8.00 | $8.00 | $8.00 |
| 16 | Asphalt (AC-20-5TR) (316-7007) | GAL | 902 | $13.00 | $13.98 | $12.00 | $5.50 | $8.00 | $9.00 | $15.00 |
| 17 | Aggregate (type PB GR 3 sac-A) (316-7260) | TON | 28 | $140.00 | $645.00 | $750.00 | $300.00 | $225.00 | $600.00 | $780.00 |
| 18 | SP mixes SP-C PG70-22 (344-7019) | TON | 269 | $180.00 | $200.00 | $242.00 | $220.00 | $180.00 | $170.00 | $200.00 |
| 19 | SP mixes SP-D sac-A PG76-22 (344-7064) | TON | 266 | $180.00 | $210.00 | $243.00 | $220.00 | $185.00 | $180.00 | $200.00 |
| 20 | Tack coat (344-7077) | GAL | 377 | $10.00 | $9.14 | $1.00 | $6.50 | $5.00 | $8.50 | $8.00 |
| 21 | Cem stabil BKFL (400-7010) | CY | 120 | $300.00 | $250.00 | $350.00 | $245.00 | $245.00 | $340.00 | $250.00 |
| 22 | Temporary special shoring (403-7001) | SF | 4,011 | $20.00 | $1.00 | $55.00 | $45.00 | $52.00 | $56.00 | $12.00 |
| 23 | Class A concrete (seal) (420-7001) | CY | 45 | $700.00 | $1,000.00 | $350.00 | $520.00 | $600.00 | $495.00 | $600.00 |
| 24 | Riprap (mow strip)(4 in) (432-7013) | CY | 35 | $800.00 | $750.00 | $550.00 | $615.00 | $725.00 | $725.00 | $600.00 |
| 25 | Riprap (stone protection)(12 in) (432-7041) | CY | 419 | $200.00 | $180.00 | $180.00 | $205.00 | $190.00 | $185.00 | $200.00 |
| 26 | Bedding material (6 in) (432-7050) | CY | 112 | $210.00 | $180.00 | $180.00 | $225.00 | $190.00 | $185.00 | $180.00 |
| 27 | Concrete box culvert (10 FT X 10 FT) (462-7038) | LF | 176 | $2,000.00 | $1,544.32 | $1,653.00 | $1,700.00 | $1,800.00 | $2,000.00 | $2,200.00 |
| 28 | Wingwall (PW - 1) (HW=13 FT) (466-7183) | EACH | 2 | $40,000 | $100,000 | $75,950 | $65,000 | $100,000 | $80,000 | $145,000 |
| 29 | Removing structure (wingwall) (496-7005) | EACH | 2 | $5,000.00 | $2,500.00 | $1,000.00 | $8,500.00 | $4,500.00 | $1,500.00 | $6,000.00 |
| 30 | Removing structure (box culvert) (496-7008) | LF | 80 | $450.00 | $250.00 | $100.00 | $140.00 | $200.00 | $125.00 | $350.00 |
| 31 | Mobilization (500-7001) | LS | 1 | $110,000 | $100,000 | $100,000 | $140,000 | $100,000 | $125,000 | $140,000 |
| 32 | Barricades, signs and traffic handling (502-7001) | MO | 7 | $6,000.00 | $1,194.02 | $1,500.00 | $4,500.00 | $2,500.00 | $2,000.00 | $2,000.00 |
| 33 | Portable changeable message sign (503-7002) | EACH | 3 | $6,000.00 | $20,000 | $5,000.00 | $18,000 | $7,000.00 | $16,500 | $10,000 |
| 34 | TMA (stationary) (505-7001) | DAY | 5 | $350.00 | $400.00 | $1,000.00 | $275.00 | $300.00 | $125.00 | $150.00 |
| 35 | TMA (mobile operation) (505-7003) | DAY | 8 | $700.00 | $400.00 | $1,000.00 | $395.00 | $300.00 | $125.00 | $150.00 |
| 36 | Rock filter dams (install) (type 2) (506-7002) | LF | 56 | $60.00 | $43.00 | $55.00 | $43.00 | $45.00 | $46.00 | $1.00 |
| 37 | Rock filter dams (install) (type 3) (506-7003) | LF | 55 | $85.00 | $59.13 | $85.00 | $45.00 | $60.00 | $64.00 | $1.00 |
| 38 | Rock filter dams (remove) (506-7011) | LF | 111 | $20.00 | $13.98 | $10.00 | $20.00 | $13.00 | $15.00 | $1.00 |
| 39 | Construction exits (install) (type 1) (506-7020) | SY | 160 | $40.00 | $40.85 | $10.00 | $65.00 | $38.00 | $44.00 | $1.00 |
| 40 | Construction exits (remove) (506-7024) | SY | 160 | $12.00 | $12.90 | $5.00 | $20.00 | $12.00 | $14.00 | $1.00 |
| 41 | Temporary sediment control fence (install) (506-7039) | LF | 1,239 | $5.00 | $4.30 | $4.00 | $4.50 | $4.50 | $4.40 | $1.00 |
| 42 | Temporary sediment control fence (remove) (506-7041) | LF | 1,239 | $1.50 | $1.40 | $1.00 | $1.50 | $1.30 | $1.50 | $1.00 |
| 43 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 56 | $11.00 | $10.75 | $10.00 | $17.00 | $11.00 | $11.00 | $1.00 |
| 44 | Biodegradable erosion control logs (remove) (506-7046) | LF | 56 | $2.50 | $5.40 | $1.00 | $2.50 | $5.50 | $5.75 | $1.00 |
| 45 | Metal W-beam guard fence (timber post) (540-7001) | LF | 500 | $30.00 | $21.23 | $33.00 | $28.00 | $22.00 | $27.00 | $25.00 |
| 46 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 100 | $105.00 | $81.70 | $85.00 | $110.00 | $85.00 | $110.00 | $95.00 |
| 47 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,500.00 | $2,902.50 | $3,250.00 | $3,500.00 | $3,000.00 | $3,400.00 | $2,900.00 |
| 48 | Wire fence (type C) (552-7003) | LF | 203 | $30.00 | $30.00 | $15.00 | $15.00 | $24.00 | $29.00 | $15.00 |
| 49 | Wire fence (remove) (552-7011) | LF | 203 | $9.00 | $10.00 | $1.00 | $7.00 | $4.00 | $5.75 | $5.00 |
| 50 | Remove SM RD SN sup&AM (644-7073) | EACH | 5 | $320.00 | $250.00 | $100.00 | $235.00 | $100.00 | $120.00 | $50.00 |
| 51 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (BI) (658-7016) | EACH | 17 | $30.00 | $33.33 | $50.00 | $18.00 | $34.00 | $18.00 | $15.00 |
| 52 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 70 | $3.50 | $5.00 | $1.00 | $2.50 | $5.00 | $2.35 | $5.00 |
| 53 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 70 | $3.50 | $5.00 | $1.00 | $2.50 | $5.00 | $2.35 | $5.00 |
| 54 | All-wther PM type I (W)6"(solid)(100MIL) (666-7309) | LF | 1,260 | $3.00 | $5.38 | $5.00 | $6.00 | $5.50 | $5.50 | $6.50 |
| 55 | All-wther PM type I (Y)6"(solid)(100MIL) (666-7315) | LF | 1,260 | $3.00 | $5.38 | $5.00 | $6.00 | $5.50 | $5.50 | $6.50 |
| 56 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 16 | $15.00 | $10.75 | $10.00 | $12.00 | $11.00 | $11.00 | $12.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.