TxDOT contract A00196445 bid tabulation
Preventive Maintenance, US 67 (SL 306 (W SAN ANGELO) to CHADBOURNE STREET). Let by Texas DOT on September 4, 2025, Tom Green, San Angelo District. 3 bids received; low bid $20,466,166 by Reece Albert, Inc., -35% against the engineer's estimate of $31,358,149.
- Owner
- Texas DOT
- Letting
- 04 SEP 2025
- Pay items
- 91
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Reece Albert, Inc. | $20,466,166 | Low | -35% |
| 2 | RK Hall, LLC | $21,641,672 | +6.0% | -31% |
| 3 | Ragle Construction, Inc. | $23,983,016 | +17% | -24% |
Engineer's estimate: $31,358,149.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Reece Albert, Inc. | 2. RK Hall, LLC | 3. Ragle Construction, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 918 | $36.91 | $18.85 | $9.00 | |
| 2 | Remove (15"-19") TRT/untrt base & asphalt pavement (105-7015) | SY | 9,922 | $27.90 | $10.47 | $16.00 | |
| 3 | Excavation (channel) (110-7002) | CY | 20,822.47 | $3.88 | $17.14 | $1.00 | |
| 4 | Embankment (final)(OC)(type B) (132-7003) | CY | 1,834.19 | $65.02 | $16.85 | $24.00 | |
| 5 | Backfill (type A or B) (134-7004) | STA | 1,008 | $384.64 | $271.36 | $233.22 | $250.00 |
| 6 | Drill seed (permanent_rural_clay) (164-7010) | SY | 19,972.22 | $0.39 | $0.39 | $0.35 | |
| 7 | Drill seed (temporary_warm) (164-7013) | SY | 19,972.22 | $0.39 | $0.39 | $0.10 | |
| 8 | Drill seed (temporary_cool) (164-7014) | SY | 19,972.22 | $0.39 | $0.39 | $0.10 | |
| 9 | Proof rolling (216-7001) | HR | 12.94 | $229.93 | $132.56 | $170.00 | |
| 10 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 8,413.11 | $58.57 | $73.28 | $55.00 | |
| 11 | Prime coat (MC-30) (310-7004) | GAL | 59,109.61 | $5.55 | $4.85 | $6.60 | $4.75 |
| 12 | Asphalt (AC-20-5TR or AC-20XP) (316-7067) | GAL | 103,441.81 | $4.95 | $4.56 | $4.93 | $4.75 |
| 13 | Aggregate (type-PB, GR-4)(sac-B) (316-7211) | CY | 2,552.92 | $174.86 | $222.20 | $251.12 | $160.00 |
| 14 | SP mixes SP-C sac-A PG70-22 (344-7020) | TON | 35,538.44 | $180.00 | $139.19 | $134.00 | $168.25 |
| 15 | Tack coat (344-7077) | GAL | 170,048.11 | $7.15 | $2.41 | $3.56 | $4.25 |
| 16 | Tom-C PG76-22 sac-A (347-7001) | TON | 33,849.75 | $189.00 | $178.21 | $175.55 | $195.00 |
| 17 | Flexible pavement structure repair(8") (351-7007) | SY | 16,590.61 | $119.70 | $79.00 | $64.46 | $75.00 |
| 18 | Planing asphalt concrete pavement(0" to 3") (354-7033) | SY | 37,220.99 | $16.20 | $3.72 | $2.39 | $2.60 |
| 19 | Planing asphalt concrete pavement(2") (354-7051) | SY | 44,839.33 | $3.49 | $3.09 | $1.80 | |
| 20 | Planing asphalt concrete pavement(3") (354-7052) | SY | 148,439.55 | $8.75 | $4.30 | $3.48 | $2.95 |
| 21 | Planing asphalt concrete pavement(4") (354-7053) | SY | 24,039.44 | $15.04 | $5.54 | $7.27 | $4.00 |
| 22 | Planing asphalt concrete pavement(6") (354-7055) | SY | 2,926 | $14.36 | $15.33 | $8.00 | |
| 23 | Plan asphalt concrete pavement (0.75") (354-7079) | SY | 58,962.88 | $3.60 | $2.16 | $1.86 | $1.20 |
| 24 | Planing asphalt concrete pavement (0" to 0.75") (354-7085) | SY | 58,264.67 | $11.16 | $1.98 | $1.08 | $1.20 |
| 25 | Riprap (concrete)(6 in) (432-7003) | CY | 153 | $878.83 | $1,100.00 | $570.00 | |
| 26 | Riprap (mow strip)(4 in) (432-7013) | CY | 183.30 | $703.70 | $884.56 | $955.97 | $630.00 |
| 27 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 1,972 | $38.00 | $40.40 | $41.80 | $40.00 |
| 28 | Clean and seal JNTS (pan girders) (CL3) (438-7011) | LF | 1,562 | $40.40 | $56.10 | $53.00 | |
| 29 | Retrofit rail (type T222) (451-7006) | LF | 4,285 | $218.14 | $294.80 | $130.00 | |
| 30 | RC pipe (CL III)(24 in) (464-7005) | LF | 20 | $321.35 | $330.00 | $160.00 | |
| 31 | Set (type I)(S= 3 FT)(HW= 2 FT)(6:1)(C) (467-7038) | EACH | 1 | $20,938 | $5,500.00 | $14,100 | |
| 32 | Clean existing culverts (480-7001) | EACH | 1 | $4,094.18 | $9,185.62 | $4,500.00 | |
| 33 | Removing structure (set) (496-7004) | EACH | 1 | $1,987.60 | $1,100.00 | $1,000.00 | |
| 34 | Mobilization (500-7001) | LS | 1 | $2,950,000 | $603,302 | $1,234,192 | $2,390,000 |
| 35 | Barricades, signs and traffic handling (502-7001) | MO | 13 | $15,000 | $11,951 | $42,000 | $106,800 |
| 36 | Temporary sediment control fence (install) (506-7039) | LF | 405 | $13.14 | $7.70 | $5.00 | |
| 37 | Temporary sediment control fence (remove) (506-7041) | LF | 405 | $4.32 | $3.30 | $1.50 | |
| 38 | Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013) | LF | 3,000 | $19.44 | $12.37 | $21.85 | $100.00 |
| 39 | Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037) | LF | 3,000 | $12.95 | $11.77 | $20.89 | $33.00 |
| 40 | Fill milled asphalt rumble strips (shoulder) (533-7005) | LF | 2,740 | $12.40 | $6.17 | $5.50 | |
| 41 | Metal W-beam guard fence (steel post) (540-7002) | LF | 2,375 | $39.95 | $33.17 | $33.00 | $30.00 |
| 42 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 19 | $3,850.00 | $2,487.82 | $3,405.84 | $2,250.00 |
| 43 | Downstream anchor terminal section (540-7015) | EACH | 29 | $1,537.50 | $1,492.69 | $1,485.00 | $1,350.00 |
| 44 | Cable barrier system (relocate)(TL-4) (543-7020) | LF | 3,200 | $14.37 | $14.30 | $27.50 | |
| 45 | Cable barrier terminal sec (reloc)(TL-4) (543-7036) | EACH | 1 | $3,869.95 | $3,850.00 | $5,000.00 | |
| 46 | Guardrail end treatment (install) (544-7001) | EACH | 25 | $3,400.00 | $3,427.67 | $3,410.00 | $3,100.00 |
| 47 | Relocate lrsa (647-7002) | EACH | 1 | $3,040.67 | $2,750.00 | $5,000.00 | |
| 48 | Install overhead sign support(25 FT cant)(circ tube) (650-7024) | EACH | 1 | $171,383 | $155,000 | $77,000 | |
| 49 | Install overhead sign support(110 FT BRDG) (650-7119) | EACH | 1 | $132,684 | $120,000 | $75,000 | |
| 50 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BR) (658-7020) | EACH | 8 | $93.87 | $42.90 | $39.00 | |
| 51 | Remove delin & object marker assms (658-7078) | EACH | 465 | $22.23 | $34.65 | $20.00 | $20.00 |
| 52 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 2,754 | $2.15 | $1.05 | $1.12 | $1.00 |
| 53 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 52,098 | $2.00 | $1.16 | $0.94 | $1.00 |
| 54 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 9,381 | $5.50 | $5.75 | $3.03 | $6.50 |
| 55 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 4,356 | $10.39 | $6.60 | $9.50 | |
| 56 | Reflectorized pavement marking type I (Y)24"(solid)(100MIL) (666-7123) | LF | 138 | $11.50 | $11.00 | $12.50 | |
| 57 | RE PV marking type I(black)6"(shadow)(100MIL) (666-7138) | LF | 3,770 | $1.75 | $1.22 | $1.98 | $1.25 |
| 58 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 39,400 | $0.75 | $0.31 | $0.39 | $0.24 |
| 59 | Reflectorized pavement marking type II (W) 6" (DOT) (666-7173) | LF | 2,754 | $1.25 | $0.63 | $0.50 | $0.30 |
| 60 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 173,971 | $0.95 | $0.29 | $0.25 | $0.21 |
| 61 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 52,098 | $1.15 | $0.63 | $0.50 | $0.25 |
| 62 | Reflectorized pavement marking type II (W) 12" (solid) (666-7182) | LF | 9,321 | $2.80 | $1.66 | $0.72 | $3.00 |
| 63 | Reflectorized pavement marking type II (W) 24" (solid) (666-7184) | LF | 4,356 | $2.65 | $1.65 | $5.00 | |
| 64 | Reflectorized pavement marking type II (W) (arrow) (666-7186) | EACH | 20 | $71.87 | $49.50 | $80.00 | |
| 65 | Reflectorized pavement marking type II (W) (double arrow) (666-7187) | EACH | 3 | $88.46 | $165.00 | $125.00 | |
| 66 | Reflectorized pavement marking type II (W) (uturn arrow) (666-7189) | EACH | 2 | $127.16 | $220.00 | $150.00 | |
| 67 | Reflectorized pavement marking type II (W) (word) (666-7194) | EACH | 19 | $88.46 | $60.50 | $100.00 | |
| 68 | Reflectorized pavement marking type II (W) (RR crossing) (666-7198) | EACH | 13 | $221.14 | $352.00 | $300.00 | |
| 69 | Reflectorized pavement marking type II (W) 36" (yld tri) (666-7201) | EACH | 71 | $15.48 | $8.80 | $15.00 | |
| 70 | Reflectorized pavement marking type II (Y) 6" (broken) (666-7211) | LF | 3,780 | $0.32 | $0.39 | $0.25 | |
| 71 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 171,082 | $0.85 | $0.29 | $0.25 | $0.21 |
| 72 | Reflectorized pavement marking type II (Y) 24" (solid) (666-7217) | LF | 138 | $2.65 | $5.50 | $5.50 | |
| 73 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 170,899 | $1.86 | $0.92 | $1.05 | $1.00 |
| 74 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 170,582 | $1.86 | $0.92 | $1.05 | $1.00 |
| 75 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 39,400 | $5.25 | $0.64 | $0.83 | $0.81 |
| 76 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 3,072 | $0.62 | $1.05 | $0.85 | |
| 77 | Type I high perf PM (Y)6"(broken)(100MIL) (666-7302) | LF | 3,780 | $0.64 | $1.05 | $0.85 | |
| 78 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 500 | $0.62 | $1.05 | $0.85 | |
| 79 | Pavement sler 6" (666-7347) | LF | 2,260 | $0.83 | $0.88 | $0.55 | $1.00 |
| 80 | Prefabricated PM type B (W)(arrow) (668-7023) | EACH | 20 | $668.95 | $825.00 | $275.00 | |
| 81 | Prefabricated PM type B (W)(double arrow) (668-7024) | EACH | 3 | $1,022.77 | $1,210.00 | $400.00 | |
| 82 | Prefabricated PM type B (W)(uturn arrow) (668-7026) | EACH | 2 | $1,227.33 | $1,210.00 | $450.00 | |
| 83 | Prefabricated PM type B (W)(word) (668-7031) | EACH | 19 | $984.07 | $1,045.00 | $350.00 | |
| 84 | Prefabricated PM type B (W)(RR crossing) (668-7035) | EACH | 13 | $2,056.60 | $1,540.00 | $650.00 | |
| 85 | Prefabricated PM type B (W)(36")(yld tri) (668-7038) | EACH | 71 | $55.28 | $66.00 | $60.00 | |
| 86 | Reflectorized pavement marker type I-C (672-7002) | EACH | 242.05 | $5.92 | $5.50 | $5.00 | |
| 87 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 435 | $8.29 | $5.50 | $5.00 | |
| 88 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 4,400 | $7.80 | $5.92 | $4.57 | $4.50 |
| 89 | Pavement surface preparation for marking (6") (678-7002) | LF | 2,380 | $1.25 | $0.55 | $0.94 | $1.00 |
| 90 | Full - width mowing (730-7019) | CYC | 4 | $10,504 | $12,650 | $5,000.00 | |
| 91 | Litter removal (734-7002) | CYC | 4 | $9,398.44 | $11,550 | $4,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.