TxDOT contract A00196604 bid tabulation
Bridge Maintenance, Various (CHAMBERS & LIBERTY COUNTIES to .). Let by Texas DOT on July 1, 2026, Jefferson, Beaumont District. 5 bids received; low bid $3,928,544 by Garret Shields Infrastructure, -15% against the engineer's estimate of $4,638,269.
- Owner
- Texas DOT
- Letting
- 01 JUL 2026
- Pay items
- 64
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Garret Shields Infrastructure | $3,928,544 | Low | -15% |
| 2 | Ragle Construction, Inc. | $4,240,008 | +8.0% | -9.0% |
| 3 | Structural Integrity Group LLC | $5,013,521 | +28% | +8.0% |
| 4 | Isi Contracting, Inc. | $5,523,787 | +41% | +19% |
| 5 | Blacksmith Ventures LLC | $5,861,643 | +49% | +26% |
Engineer's estimate: $4,638,269.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Garret Shields Infrastructure | 2. Ragle Construction, Inc. | 3. Structural Integrity Group LLC | 4. Isi Contracting, Inc. | 5. Blacksmith Ventures LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7004) | CY | 447 | $45.00 | $100.00 | $140.00 | $25.00 | $116.90 | $180.00 |
| 2 | Removing concrete (riprap) (104-7007) | CY | 30 | $250.00 | $100.00 | $145.00 | $30.00 | $146.13 | $240.00 |
| 3 | Removing concrete (pile encasement) (104-7033) | CY | 3 | $800.00 | $1,000.00 | $1,000.00 | $7,500.00 | $2,811.61 | $3,000.00 |
| 4 | Remove (4") TRT/untrt base & asphalt pavement (105-7024) | SY | 48 | $7.00 | $40.00 | $20.00 | $130.00 | $5.84 | $150.00 |
| 5 | Embankment (final)(OC)(type C) (132-7005) | CY | 87 | $25.00 | $40.00 | $90.00 | $62.00 | $471.69 | $200.00 |
| 6 | Spec excavation work (backhoe) (158-7001) | HR | 40 | $200.00 | $100.00 | $80.00 | $95.00 | $50.88 | $200.00 |
| 7 | Spec excavation work (hyd excavator) (158-7002) | HR | 8 | $600.00 | $200.00 | $150.00 | $125.00 | $171.52 | $400.00 |
| 8 | Spec excavation work (front-end loader) (158-7003) | HR | 56 | $450.00 | $150.00 | $120.00 | $125.00 | $143.56 | $200.00 |
| 9 | Hydro mulch seed (permanent_rural_clay) (164-7018) | SY | 40 | $0.50 | $1.50 | $10.00 | $25.00 | $0.58 | $50.00 |
| 10 | Vegetative watering (168-7001) | TGL | 1 | $900.00 | $100.00 | $500.00 | $2,000.00 | $128.88 | $10,000 |
| 11 | Soil retention blankets (CL 1) (type B) (169-7043) | SY | 40 | $6.70 | $5.00 | $20.00 | $25.00 | $9.00 | $150.00 |
| 12 | Plan & text concrete pavement(0" to 1.5") (354-7026) | SY | 89 | $20.00 | $50.00 | $20.00 | $203.00 | $9.39 | $120.00 |
| 13 | Full - depth repair CRCP (13") (361-7008) | CY | 4 | $1,800.00 | $1,500.00 | $3,500.00 | $2,500.00 | $2,788.89 | $3,200.00 |
| 14 | Flowable backfill (401-7001) | CY | 64 | $450.00 | $300.00 | $500.00 | $250.00 | $766.41 | $500.00 |
| 15 | Temporary special shoring (cofferdam) (403-7002) | SF | 1,600 | $20.00 | $35.00 | $0.01 | $127.00 | $300.00 | $80.00 |
| 16 | Class C concrete(pile encasement) (420-7059) | LF | 90 | $1,600.00 | $1,000.00 | $1,500.00 | $580.00 | $3,544.73 | $2,000.00 |
| 17 | Concrete structure repair(deck rep(part depth)) (429-7003) | SF | 18 | $148.00 | $150.00 | $200.00 | $2,030.00 | $186.00 | $600.00 |
| 18 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 26 | $368.00 | $200.00 | $250.00 | $1,470.00 | $227.07 | $600.00 |
| 19 | Concrete structure repair (standard) (429-7009) | SF | 45 | $321.00 | $150.00 | $250.00 | $933.00 | $170.85 | $600.00 |
| 20 | Riprap (concrete)(5 in) (432-7002) | CY | 46 | $1,000.00 | $1,000.00 | $750.00 | $900.00 | $468.14 | $860.00 |
| 21 | Riprap (mow strip)(4 in) (432-7013) | CY | 666 | $620.00 | $600.00 | $600.00 | $655.00 | $666.70 | $700.00 |
| 22 | Riprap (stone common)(grout)(6 in) (432-7036) | CY | 11 | $500.00 | $500.00 | $650.00 | $125.00 | $202.52 | $800.00 |
| 23 | Riprap (stone protection)(12 in) (432-7041) | CY | 42 | $220.00 | $300.00 | $375.00 | $125.00 | $138.04 | $800.00 |
| 24 | Riprap (stone protection)(24 in) (432-7045) | CY | 260 | $230.00 | $200.00 | $375.00 | $250.00 | $350.00 | $400.00 |
| 25 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 562 | $82.00 | $40.00 | $18.00 | $40.00 | $19.40 | $70.00 |
| 26 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 19,544 | $40.00 | $35.00 | $20.00 | $35.00 | $33.60 | $60.00 |
| 27 | Multi-layer polymer overlay (439-7014) | SY | 25,420 | $30.00 | $34.00 | $37.25 | $31.25 | $35.23 | $36.00 |
| 28 | Retrofit rail (type T222) (451-7006) | LF | 480 | $400.00 | $200.00 | $145.00 | $252.00 | $276.81 | $280.00 |
| 29 | Retrofit rail (type T131RC) (451-7049) | LF | 322 | $250.00 | $200.00 | $190.00 | $356.00 | $249.86 | $35.00 |
| 30 | Shot blasting (483-7016) | SY | 25,420 | $3.00 | $4.00 | $3.00 | $3.00 | $5.63 | $4.00 |
| 31 | Remove STR (rail) (496-7017) | LF | 802 | $25.00 | $50.00 | $11.00 | $19.00 | $37.12 | $60.00 |
| 32 | Mobilization (500-7001) | LS | 1 | $713,225 | $300,000 | $430,000 | $529,000 | $300,000 | $700,000 |
| 33 | Barricades, signs and traffic handling (502-7001) | MO | 16 | $5,000.00 | $5,000.00 | $26,000 | $40,000 | $15,814 | $15,000 |
| 34 | Portable changeable message sign (503-7002) | EACH | 5 | $4,450.00 | $1,000.00 | $15,000 | $7,500.00 | $741.01 | $20,000 |
| 35 | TMA (stationary) (505-7001) | DAY | 405 | $270.00 | $300.00 | $350.00 | $1.00 | $1,363.59 | $200.00 |
| 36 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 630 | $90.00 | $80.00 | $150.00 | $35.00 | $150.78 | $90.00 |
| 37 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 630 | $20.00 | $20.00 | $10.00 | $145.00 | $4.15 | $10.00 |
| 38 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 630 | $40.00 | $20.00 | $18.00 | $30.00 | $13.88 | $10.00 |
| 39 | Metal W-beam guard fence (timber post) (540-7001) | LF | 5,587.50 | $30.00 | $30.00 | $28.50 | $21.00 | $20.20 | $35.00 |
| 40 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 33 | $2,200.00 | $1,500.00 | $2,015.00 | $2,067.00 | $2,064.94 | $2,500.00 |
| 41 | Downstream anchor terminal section (540-7015) | EACH | 17 | $1,800.00 | $1,500.00 | $1,165.00 | $2,549.00 | $2,585.55 | $2,500.00 |
| 42 | Metal beam guard fence trans (non - sym) (540-7016) | EACH | 4 | $800.00 | $1,000.00 | $1,250.00 | $7,346.00 | $7,593.33 | $2,500.00 |
| 43 | Remove metal beam guard fence (542-7001) | LF | 5,905 | $6.00 | $5.00 | $3.00 | $5.00 | $4.83 | $8.00 |
| 44 | Remove terminal anchor section (542-7002) | EACH | 43 | $300.00 | $500.00 | $220.00 | $638.00 | $662.95 | $300.00 |
| 45 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 4 | $350.00 | $500.00 | $260.00 | $6,867.00 | $7,126.62 | $500.00 |
| 46 | Guardrail end treatment (install) (544-7001) | EACH | 42 | $4,000.00 | $3,500.00 | $3,395.00 | $3,211.00 | $3,165.28 | $3,500.00 |
| 47 | Guardrail end treatment (remove) (544-7003) | EACH | 13 | $280.00 | $500.00 | $330.00 | $2,112.00 | $2,192.79 | $500.00 |
| 48 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 10 | $2,500.00 | $1,000.00 | $1,100.00 | $1,500.00 | $1,174.07 | $3,500.00 |
| 49 | Crash cushion attenuator (remove) (545-7004) | EACH | 10 | $1,200.00 | $1,000.00 | $1,000.00 | $800.00 | $478.43 | $2,000.00 |
| 50 | Crash cushion attenuator (install)(R)(N)(TL3) (545-7010) | EACH | 3 | $30,000 | $28,000 | $24,000 | $37,000 | $28,904 | $16,000 |
| 51 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 10 | $14,000 | $8,000.00 | $7,350.00 | $7,500.00 | $10,038 | $16,000 |
| 52 | Install delineator assembly (D-SW)SZ 1(WFLX)GF2(BI) (658-7002) | EACH | 350 | $35.00 | $20.00 | $30.00 | $30.00 | $25.94 | $200.00 |
| 53 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 36 | $22.00 | $20.00 | $24.00 | $30.00 | $40.56 | $200.00 |
| 54 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7052) | LF | 3,060 | $3.00 | $2.50 | $3.00 | $8.00 | $7.47 | $5.00 |
| 55 | Pavement sler 6" (666-7347) | LF | 4,810 | $0.50 | $0.85 | $0.35 | $1.00 | $0.58 | $2.00 |
| 56 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 4,020 | $0.70 | $1.75 | $2.00 | $3.00 | $1.41 | $2.00 |
| 57 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 190 | $0.70 | $2.50 | $2.00 | $3.00 | $1.12 | $2.00 |
| 58 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 600 | $0.70 | $2.50 | $2.00 | $3.00 | $1.41 | $2.00 |
| 59 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 77 | $5.00 | $10.00 | $7.50 | $12.00 | $8.15 | $30.00 |
| 60 | Eliminating existing PM & markers (4") (677-7001) | LF | 4,810 | $0.50 | $1.50 | $1.50 | $2.00 | $1.41 | $2.00 |
| 61 | Concrete rail repair (in-kind) (778-7001) | LF | 2 | $350.00 | $500.00 | $1,000.00 | $500.00 | $164.81 | $2,500.00 |
| 62 | CNC crack repair (discrete)(gravity) (780-7001) | LF | 100 | $35.00 | $30.00 | $50.00 | $75.00 | $33.90 | $120.00 |
| 63 | Rep steel bridge member(repl rivet/bolt) (784-7024) | EACH | 10 | $300.00 | $500.00 | $400.00 | $530.00 | $555.47 | $2,500.00 |
| 64 | Bridge joint repair (SEJ) (785-7005) | LF | 48 | $285.00 | $300.00 | $175.00 | $525.00 | $700.93 | $900.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 1, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way