TxDOT contract A00196909 bid tabulation
Hazard Elimination & Safety, IH 45 (South of Risinger Rd to Dallas County Line). Let by Texas DOT on October 7, 2026, Ellis, Dallas District. 8 bids received; low bid $3,761,164 by Xit Paving and Construction Inc., -17% against the engineer's estimate of $4,533,562.
- Owner
- Texas DOT
- Letting
- 07 OCT 2026
- Pay items
- 39
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Xit Paving and Construction Inc. | $3,761,164 | Low | -17% |
| 2 | Ed Bell Construction Company | $4,069,000 | +8.0% | -10% |
| 3 | Altus Construction LLC | $4,308,009 | +15% | -5.0% |
| 4 | JR West Texas Concrete LLC | $4,442,440 | +18% | -2.0% |
| 5 | Ragle Construction, Inc. | $4,779,478 | +27% | +5.0% |
| 6 | James Construction Group, LLC | $4,795,686 | +28% | +6.0% |
| 7 | Tucan Contracting, LLC | $5,183,617 | +38% | +14% |
| 8 | SCR Civil Construction, LLC | $5,697,478 | +51% | +26% |
Engineer's estimate: $4,533,562.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Xit Paving and Construction Inc. | 2. Ed Bell Construction Company | 3. Altus Construction LLC | 4. JR West Texas Concrete LLC | 5. Ragle Construction, Inc. | 6. James Construction Group, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7003) | SY | 6,545 | $15.00 | $9.00 | $10.00 | $16.96 | $18.00 | $8.50 | $20.00 |
| 2 | Embankment (final)(OC)(type A) (132-7001) | CY | 728 | $40.00 | $42.00 | $50.00 | $86.69 | $45.00 | $65.60 | $64.64 |
| 3 | Backfill (type A or B) (134-7004) | STA | 208 | $350.00 | $317.00 | $250.00 | $395.74 | $240.00 | $459.00 | $225.96 |
| 4 | Block sodding (162-7002) | SY | 17,827 | $5.00 | $4.00 | $8.00 | $5.91 | $4.12 | $6.90 | $5.88 |
| 5 | Vegetative watering (168-7001) | TGL | 2,649 | $8.00 | $9.00 | $10.00 | $1.00 | $9.75 | $0.50 | $28.16 |
| 6 | Riprap (concrete)(5 in) (432-7002) | CY | 961 | $550.00 | $525.00 | $500.00 | $315.32 | $525.00 | $540.00 | $600.00 |
| 7 | Riprap (concrete)(CL C) (432-7006) | CY | 24 | $750.00 | $664.00 | $1,200.00 | $671.40 | $650.00 | $530.00 | $882.43 |
| 8 | Riprap (mow strip)(4 in) (432-7013) | CY | 2 | $675.00 | $1,062.00 | $2,000.00 | $580.74 | $850.00 | $552.00 | $1,105.70 |
| 9 | Mobilization (500-7001) | LS | 1 | $395,778 | $180,000 | $388,820 | $428,644 | $275,000 | $477,000 | $470,000 |
| 10 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $30,000 | $4,400.00 | $31,500 | $18,789 | $31,200 | $79,500 | $25,000 |
| 11 | Portable changeable message sign (503-7002) | EACH | 2 | $10,000 | $8,000.00 | $5,000.00 | $9,553.55 | $20,000 | $7,600.00 | $25,000 |
| 12 | TMA (stationary) (505-7001) | DAY | 98 | $250.00 | $130.00 | $150.00 | $224.71 | $300.00 | $400.00 | $314.56 |
| 13 | TMA (mobile operation) (505-7003) | DAY | 49 | $400.00 | $140.00 | $750.00 | $224.71 | $375.00 | $616.00 | $689.89 |
| 14 | Rock filter dams (install) (type 2) (506-7002) | LF | 22 | $45.00 | $60.00 | $745.50 | $95.50 | $53.00 | $52.00 | $59.35 |
| 15 | Rock filter dams (remove) (506-7011) | LF | 22 | $10.00 | $23.00 | $42.60 | $49.01 | $12.00 | $20.00 | $36.21 |
| 16 | Construction exits (install) (type 1) (506-7020) | SY | 88 | $30.00 | $54.00 | $37.28 | $40.45 | $47.00 | $46.70 | $41.13 |
| 17 | Construction exits (remove) (506-7024) | SY | 88 | $8.00 | $17.00 | $18.64 | $22.47 | $22.00 | $15.00 | $35.21 |
| 18 | Temporary sediment control fence (install) (506-7039) | LF | 110 | $3.50 | $7.00 | $4.26 | $8.99 | $8.00 | $6.00 | $3.02 |
| 19 | Temporary sediment control fence (remove) (506-7041) | LF | 110 | $0.80 | $3.00 | $2.13 | $4.49 | $3.00 | $3.00 | $1.71 |
| 20 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 704 | $5.50 | $7.00 | $5.06 | $6.18 | $21.00 | $6.00 | $3.88 |
| 21 | Biodegradable erosion control logs (remove) (506-7046) | LF | 704 | $1.30 | $2.00 | $2.40 | $6.18 | $5.00 | $2.00 | $0.91 |
| 22 | Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005) | LF | 12,330 | $45.00 | $55.00 | $15.00 | $58.32 | $53.18 | $27.20 | $77.50 |
| 23 | Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029) | LF | 29,340 | $10.00 | $8.00 | $2.50 | $10.58 | $11.17 | $5.70 | $8.00 |
| 24 | Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053) | LF | 12,330 | $15.00 | $15.00 | $15.00 | $10.72 | $20.08 | $9.30 | $10.00 |
| 25 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 20,270 | $80.00 | $68.00 | $92.50 | $79.15 | $74.75 | $98.10 | $70.77 |
| 26 | Permanent CTB (tran SSCB to T501)(mod) (514-7042) | LF | 36 | $93.00 | $148.00 | $300.00 | $312.11 | $230.00 | $287.00 | $250.00 |
| 27 | Permanent CTB(SS)(42")(heb)(flex PVM) (514-7048) | LF | 450 | $200.00 | $170.00 | $175.00 | $252.93 | $182.00 | $200.00 | $300.00 |
| 28 | Remove metal beam guard fence (542-7001) | LF | 2,025 | $6.00 | $7.00 | $2.66 | $2.25 | $3.00 | $2.50 | $3.00 |
| 29 | Remove terminal anchor section (542-7002) | EACH | 3 | $210.00 | $230.00 | $159.75 | $224.71 | $250.00 | $150.00 | $220.00 |
| 30 | Remove downstream anchor terminal (542-7003) | EACH | 1 | $242.00 | $228.00 | $213.00 | $224.71 | $500.00 | $200.00 | $230.00 |
| 31 | Cable barrier terminal sec (install)(TL-4) (543-7018) | EACH | 2 | $5,500.00 | $6,696.00 | $10,861 | $5,087.06 | $10,560 | $8,832.34 | $5,165.00 |
| 32 | Cable barrier (remove) (543-7037) | LF | 19,633 | $9.00 | $4.00 | $3.73 | $2.93 | $4.25 | $3.80 | $3.90 |
| 33 | Cable barrier terminal section (remove) (543-7038) | EACH | 10 | $1,100.00 | $1,800.00 | $532.50 | $500.99 | $600.00 | $500.00 | $450.00 |
| 34 | Guardrail end treatment (remove) (544-7003) | EACH | 11 | $280.00 | $626.00 | $266.25 | $224.71 | $300.00 | $250.00 | $330.00 |
| 35 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 4 | $2,000.00 | $1,960.00 | $1,000.00 | $1,005.59 | $2,600.00 | $1,192.00 | $1,515.00 |
| 36 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $1,200.00 | $1,252.00 | $750.00 | $775.26 | $1,200.00 | $1,000.00 | $810.00 |
| 37 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 3 | $9,000.00 | $4,600.00 | $7,500.00 | $7,692.96 | $17,000 | $15,000 | $8,010.00 |
| 38 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 208 | $25.00 | $31.00 | $25.00 | $17.98 | $36.00 | $25.00 | $24.00 |
| 39 | Full - width mowing (730-7019) | CYC | 2 | $10,000 | $5,000.00 | $7,500.00 | $3,438.05 | $7,500.00 | $1,250.00 | $6,588.49 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 7, 2026. Compiled by Mirage Metrics.