TxDOT contract A00198367 bid tabulation
Rehabilitate Existing Roadway, FM 1160 (0.07 Mi S of FM 1300 W to 0.28 Mi N of FM 1300 W). Let by Texas DOT on January 6, 2026, Wharton, Yoakum District. 7 bids received; low bid $1,897,773 by Clark Construction of Texas, Inc., -2.2% against the engineer's estimate of $1,941,145.
- Owner
- Texas DOT
- Letting
- 06 JAN 2026
- Pay items
- 83
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Clark Construction of Texas, Inc. | $1,897,773 | Low | -2.0% |
| 2 | E-Z Bel Construction, LLC | $1,998,207 | +5.0% | +3.0% |
| 3 | STX Civil | $2,054,372 | +8.0% | +6.0% |
| 4 | Matagorda Construction & Materials | $2,122,809 | +12% | +9.0% |
| 5 | Hunter Industries, LTD. | $2,210,069 | +16% | +14% |
| 6 | CK Newberry, LLC | $2,287,882 | +21% | +18% |
| 7 | MB Western Industrial Contracting Co. | $3,148,997 | +66% | +62% |
Engineer's estimate: $1,941,145.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Clark Construction of Texas, Inc. | 2. E-Z Bel Construction, LLC | 3. STX Civil | 4. Matagorda Construction & Materials | 5. Hunter Industries, LTD. | 6. CK Newberry, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 15.97 | $3,000.00 | $3,875.87 | $4,822.00 | $1,400.00 | $1,000.00 | $854.65 | $5,000.00 |
| 2 | Removing concrete (riprap) (104-7007) | CY | 0.35 | $100.00 | $1,885.00 | $316.00 | $50.00 | $2,000.00 | $100.57 | $1,000.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 3,487 | $17.00 | $12.71 | $16.00 | $15.00 | $20.00 | $22.00 | $25.00 |
| 4 | Embankment (final)(OC)(type C) (132-7005) | CY | 1,632 | $30.00 | $19.96 | $15.00 | $28.00 | $20.00 | $25.30 | $20.00 |
| 5 | Embankment (vehicle)(OC)(type C) (132-7017) | CY | 25 | $35.00 | $35.00 | $37.00 | $35.00 | $40.00 | $52.80 | $100.00 |
| 6 | Blading (150-7002) | HR | 25 | $115.00 | $115.00 | $159.00 | $80.00 | $130.00 | $121.00 | $175.00 |
| 7 | Broadcast seed (temporary_warm) (164-7005) | SY | 992 | $0.60 | $0.25 | $1.00 | $0.25 | $1.00 | $0.62 | $0.25 |
| 8 | Broadcast seed (temporary_cool) (164-7006) | SY | 992 | $0.60 | $0.25 | $1.00 | $0.25 | $1.00 | $0.62 | $0.25 |
| 9 | Drill seed (permanent_rural_sand) (164-7009) | SY | 9,190 | $0.35 | $0.30 | $0.37 | $0.25 | $0.35 | $0.36 | $0.30 |
| 10 | Drill seed (temporary_warm) (164-7013) | SY | 2,298 | $0.35 | $0.28 | $0.37 | $0.25 | $0.35 | $0.36 | $0.28 |
| 11 | Drill seed (temporary_cool) (164-7014) | SY | 2,298 | $0.35 | $0.28 | $0.37 | $0.25 | $0.35 | $0.36 | $0.28 |
| 12 | Vegetative watering (168-7001) | TGL | 85.70 | $50.00 | $50.00 | $118.00 | $1.00 | $40.00 | $92.40 | $25.00 |
| 13 | FL BS (compacted in place)(tye GR1-2)(final pos) (247-7193) | CY | 2,803 | $95.00 | $104.93 | $115.00 | $65.00 | $95.00 | $92.40 | $115.00 |
| 14 | Rework BS metal (type C)(6")(ord comp) (251-7041) | STA | 16.54 | $2.00 | $1,224.24 | $605.00 | $5.00 | $2,000.00 | $330.00 | $800.00 |
| 15 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 142 | $325.00 | $350.00 | $500.00 | $400.00 | $400.00 | $385.00 | $400.00 |
| 16 | Lime TRT (subgrade) (8") (260-7020) | SY | 8,936 | $6.50 | $5.07 | $4.00 | $5.00 | $10.00 | $4.40 | $3.50 |
| 17 | Asphalt (RC-250) (316-7016) | GAL | 1,571 | $10.00 | $9.09 | $6.00 | $5.00 | $5.00 | $7.37 | $6.50 |
| 18 | Aggregate (type-E, GR-5)(sac-B) (316-7194) | CY | 56 | $500.00 | $227.86 | $350.00 | $500.00 | $500.00 | $163.47 | $300.00 |
| 19 | Aggregate (type-PE, GR-3)(sac-B) (316-7229) | CY | 93 | $500.00 | $213.28 | $280.00 | $450.00 | $400.00 | $197.29 | $225.00 |
| 20 | Aggregate (type-PE, GR-4)(sac-B) (316-7232) | CY | 73 | $500.00 | $245.69 | $335.00 | $600.00 | $400.00 | $189.20 | $250.00 |
| 21 | Asphalt (AC 20-5TR or AC-20XP or CRS-2P) (316-7264) | GAL | 6,383 | $8.00 | $4.88 | $5.15 | $6.00 | $3.50 | $4.84 | $4.50 |
| 22 | Flexible pavement structure repair(8") (351-7007) | SY | 100 | $75.00 | $102.55 | $100.00 | $100.00 | $140.00 | $116.60 | $200.00 |
| 23 | Cut & restoring pavement (400-7006) | SY | 443 | $135.00 | $38.00 | $43.00 | $170.00 | $128.00 | $140.00 | $45.00 |
| 24 | Cem stabil BKFL (400-7010) | CY | 245 | $225.00 | $140.00 | $300.00 | $175.00 | $150.00 | $210.00 | $275.00 |
| 25 | Trench excavation protection (402-7001) | LF | 86 | $12.00 | $12.00 | $25.00 | $5.00 | $10.00 | $105.00 | $65.00 |
| 26 | Temporary special shoring (403-7001) | SF | 632 | $20.00 | $25.00 | $5.00 | $15.00 | $25.00 | $10.00 | $25.00 |
| 27 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 50 | $250.00 | $167.10 | $231.00 | $183.81 | $350.00 | $180.47 | $195.00 |
| 28 | Riprap (concrete)(5 in) (432-7002) | CY | 50.20 | $700.00 | $600.00 | $420.00 | $650.00 | $1,100.00 | $800.00 | $700.00 |
| 29 | Riprap (concrete)(CL B) (432-7005) | CY | 1.75 | $900.00 | $667.00 | $1,014.00 | $700.00 | $2,000.00 | $1,000.00 | $1,500.00 |
| 30 | Riprap (stone protection)(18 in) (432-7043) | CY | 95 | $200.00 | $211.50 | $190.00 | $165.00 | $260.00 | $230.27 | $200.00 |
| 31 | CMP (gal steel 18 in) (460-7003) | LF | 8 | $100.00 | $182.00 | $257.00 | $95.00 | $150.00 | $275.00 | $160.00 |
| 32 | Concrete box culvert (12 FT X 5 FT) (462-7048) | LF | 311 | $1,600.00 | $1,668.00 | $1,690.00 | $2,200.00 | $1,800.00 | $1,850.00 | $2,000.00 |
| 33 | RC pipe (CL III)(18 in) (464-7003) | LF | 72 | $135.00 | $119.00 | $97.00 | $85.00 | $100.00 | $135.00 | $100.00 |
| 34 | Set (type I)(S= 12 FT)(HW= 6 FT)(4:1)(C) (467-7273) | EACH | 10 | $10,000 | $10,855 | $8,500.00 | $17,000 | $24,000 | $35,000 | $12,000 |
| 35 | Set (type II) (18 in) (CMP) (6: 1) (P) (467-7304) | EACH | 2 | $1,400.00 | $2,400.00 | $1,297.00 | $1,500.00 | $1,100.00 | $1,900.00 | $3,500.00 |
| 36 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 6 | $1,600.00 | $2,000.00 | $1,528.00 | $1,600.00 | $1,500.00 | $2,300.00 | $3,000.00 |
| 37 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 2 | $3,000.00 | $2,210.00 | $1,755.00 | $3,100.00 | $3,000.00 | $2,750.00 | $3,250.00 |
| 38 | Set (type II) (30 in) (TP) (6: 1) (P) (467-7352) | EACH | 2 | $3,500.00 | $2,400.00 | $2,565.00 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 |
| 39 | Removing structure (box culvert) (496-7001) | EACH | 1 | $15,000 | $29,780 | $4,560.00 | $15,000 | $65,000 | $35,000 | $18,500 |
| 40 | Removing structure (small) (496-7036) | EACH | 2 | $1,500.00 | $1,300.00 | $522.00 | $500.00 | $500.00 | $2,000.00 | $2,200.00 |
| 41 | Mobilization (500-7001) | LS | 1 | $110,000 | $128,750 | $150,000 | $152,000 | $40,000 | $213,132 | $225,000 |
| 42 | Barricades, signs and traffic handling (502-7001) | MO | 5 | $5,000.00 | $8,740.00 | $3,000.00 | $2,500.00 | $8,000.00 | $2,473.19 | $25,000 |
| 43 | Portable changeable message sign (503-7002) | EACH | 5 | $8,000.00 | $8,000.00 | $8,800.00 | $7,000.00 | $1,800.00 | $2,041.30 | $5,000.00 |
| 44 | TMA (stationary) (505-7001) | DAY | 10 | $200.00 | $125.00 | $302.00 | $165.00 | $250.00 | $153.10 | $200.00 |
| 45 | TMA (mobile operation) (505-7003) | DAY | 10 | $400.00 | $300.00 | $596.00 | $165.00 | $1,300.00 | $306.20 | $200.00 |
| 46 | Rock filter dams (install) (type 1) (506-7001) | LF | 25 | $50.00 | $45.00 | $58.00 | $1.00 | $40.00 | $58.00 | $50.00 |
| 47 | Rock filter dams (remove) (506-7011) | LF | 25 | $12.00 | $20.00 | $14.00 | $1.00 | $10.00 | $14.00 | $25.00 |
| 48 | Sandbags for erosion control (506-7035) | EACH | 100 | $15.00 | $3.00 | $18.00 | $1.00 | $10.00 | $17.50 | $3.00 |
| 49 | Temporary sediment control fence (install) (506-7039) | LF | 530 | $4.00 | $3.75 | $5.00 | $1.00 | $5.00 | $4.75 | $4.00 |
| 50 | Temporary sediment control fence (remove) (506-7041) | LF | 530 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.40 | $1.00 |
| 51 | Driveways (surface treat) (530-7016) | SY | 255 | $30.00 | $41.80 | $255.00 | $45.00 | $45.00 | $30.80 | $75.00 |
| 52 | Remove RD IL asm (trans-base) (610-7009) | EACH | 1 | $550.00 | $354.31 | $3,118.00 | $390.00 | $600.00 | $354.31 | $350.00 |
| 53 | In RD IL (type SA) 50T-10 (400W EQ) LED (610-7198) | EACH | 5 | $6,200.00 | $5,777.43 | $6,028.00 | $6,355.00 | $6,400.00 | $5,777.43 | $6,000.00 |
| 54 | Temporary RD IL setup and remove (617-7001) | EACH | 1 | $7,500.00 | $7,586.56 | $8,700.00 | $8,345.00 | $8,200.00 | $7,586.56 | $7,500.00 |
| 55 | Temporary RD IL maintain system (617-7002) | MO | 5 | $5,500.00 | $354.32 | $1,574.92 | $390.00 | $1,300.00 | $354.32 | $350.00 |
| 56 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 808 | $15.00 | $16.20 | $19.00 | $18.00 | $23.00 | $16.20 | $16.00 |
| 57 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 331 | $20.00 | $24.47 | $29.00 | $27.00 | $55.00 | $24.47 | $25.00 |
| 58 | Electrical conductor (no.8) bare (620-7007) | LF | 1,139 | $2.00 | $2.12 | $2.00 | $2.50 | $3.00 | $2.12 | $2.20 |
| 59 | Electrical conductor (no.8) insulated (620-7008) | LF | 1,648 | $2.50 | $2.64 | $2.00 | $3.00 | $3.00 | $2.64 | $2.75 |
| 60 | Ground box type A (122311)W/apron (624-7002) | EACH | 6 | $1,300.00 | $1,402.77 | $1,097.00 | $1,545.00 | $2,300.00 | $1,402.77 | $1,500.00 |
| 61 | Remove ground box (624-7013) | EACH | 1 | $500.00 | $142.11 | $560.00 | $155.00 | $500.00 | $142.11 | $145.00 |
| 62 | Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148) | EACH | 1 | $8,500.00 | $7,822.11 | $8,800.00 | $8,600.00 | $7,000.00 | $7,822.11 | $8,000.00 |
| 63 | Aluminum signs (type A) (636-7001) | SF | 16 | $37.00 | $35.00 | $136.00 | $45.00 | $58.00 | $35.00 | $35.00 |
| 64 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 2 | $900.00 | $1,200.00 | $895.00 | $900.00 | $1,000.00 | $895.29 | $900.00 |
| 65 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 2 | $1,000.00 | $1,300.00 | $1,060.00 | $900.00 | $1,200.00 | $1,060.04 | $1,100.00 |
| 66 | Install small roadside sign support and assembly TYS80(1)SA(U-1EXT) (644-7032) | EACH | 2 | $1,200.00 | $1,400.00 | $1,352.00 | $1,000.00 | $1,200.00 | $1,352.04 | $1,300.00 |
| 67 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 4 | $600.00 | $650.00 | $507.00 | $600.00 | $530.00 | $507.36 | $500.00 |
| 68 | Remove SM RD SN sup&AM (644-7073) | EACH | 10 | $105.00 | $175.00 | $130.00 | $50.00 | $100.00 | $130.00 | $150.00 |
| 69 | Install object marker assembly (OM-2Z)(yflx)GNDHH(BI) (658-7255) | EACH | 4 | $25.00 | $125.00 | $225.00 | $35.00 | $250.00 | $125.00 | $225.00 |
| 70 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 11,940 | $0.35 | $0.75 | $1.00 | $0.83 | $0.50 | $0.75 | $0.45 |
| 71 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 10 | $0.35 | $0.75 | $1.00 | $0.83 | $0.50 | $0.75 | $0.45 |
| 72 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 11,076 | $0.35 | $0.75 | $1.00 | $0.83 | $0.50 | $0.75 | $0.45 |
| 73 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 560 | $1.75 | $1.80 | $3.00 | $0.44 | $2.00 | $1.60 | $0.80 |
| 74 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 4,068 | $1.75 | $3.50 | $2.00 | $1.72 | $2.50 | $1.56 | $2.50 |
| 75 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 4,024 | $1.75 | $3.50 | $2.00 | $1.72 | $2.50 | $1.56 | $2.50 |
| 76 | Reflectorized profile pavement marking type I(Y)6"(broken)(100MIL) (666-7274) | LF | 10 | $3.00 | $3.50 | $2.00 | $1.72 | $24.00 | $1.56 | $3.00 |
| 77 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 46 | $20.00 | $25.00 | $22.00 | $24.31 | $24.00 | $22.10 | $20.00 |
| 78 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 52 | $6.00 | $8.00 | $10.00 | $11.00 | $10.00 | $10.00 | $10.00 |
| 79 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 2 | $250.00 | $243.66 | $303.00 | $268.03 | $350.00 | $243.66 | $250.00 |
| 80 | Traffic signal CBL (type A)(14 AWG)(4 conductor) (684-7030) | LF | 435 | $3.00 | $2.75 | $2.00 | $3.03 | $2.50 | $2.75 | $2.75 |
| 81 | Install RDSD flash beacon assembly (685-7001) | EACH | 1 | $5,500.00 | $4,757.37 | $4,974.00 | $5,233.11 | $6,500.00 | $4,757.37 | $4,800.00 |
| 82 | Removing RDSD FLSH BCN AM (solar PWRD) (685-7006) | EACH | 1 | $1,800.00 | $147.63 | $1,282.00 | $162.39 | $1,100.00 | $147.63 | $150.00 |
| 83 | TMSP radar speed control monitor (6025-7001) | EACH | 2 | $10,000 | $12,000 | $6,000.00 | $12,500 | $2,300.00 | $5,103.25 | $5,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 6, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.