TxDOT contract A00199643 bid tabulation
Construct Pedestrian Infrastructure, Various (DISTRICTWIDE to .). Let by Texas DOT on July 1, 2025, Brown, Brownwood District. 9 bids received; low bid $1,364,489 by Westfield Insurance Company, -7.9% against the engineer's estimate of $1,481,086.
- Owner
- Texas DOT
- Letting
- 01 JUL 2025
- Pay items
- 41
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Westfield Insurance Company | $1,364,489 | Low | -8.0% |
| 2 | STX Civil | $1,456,908 | +7.0% | -2.0% |
| 3 | 3LW Civil LLC | $1,466,143 | +7.0% | -1.0% |
| 4 | Delgado'S Contractors, LLC | $1,555,816 | +14% | +5.0% |
| 5 | Xit Paving and Construction Inc. | $1,563,045 | +15% | +6.0% |
| 6 | O. Trevino Construction, LLC | $1,578,591 | +16% | +7.0% |
| 7 | Ti-Zack Concrete, LLC | $1,595,212 | +17% | +8.0% |
| 8 | Grey Sky Construction LLC | $1,685,794 | +24% | +14% |
| 9 | Prater Dirt Work LLC | $1,708,775 | +25% | +15% |
Engineer's estimate: $1,481,086.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Westfield Insurance Company | 2. STX Civil | 3. 3LW Civil LLC | 4. Delgado'S Contractors, LLC | 5. Xit Paving and Construction Inc. | 6. O. Trevino Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 90 | $53.00 | $15.40 | $18.00 | $25.00 | $20.00 | $56.00 | $35.00 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 2,404.50 | $25.00 | $18.70 | $20.00 | $30.00 | $25.00 | $32.00 | $30.00 |
| 3 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 1,526.50 | $25.00 | $19.80 | $17.00 | $25.00 | $15.00 | $29.00 | $30.00 |
| 4 | Removing concrete (curb) (104-7016) | LF | 1,012 | $10.00 | $3.81 | $6.00 | $17.00 | $10.00 | $0.50 | $7.00 |
| 5 | Removing concrete (curb & gutter) (104-7017) | LF | 548 | $18.00 | $16.94 | $7.00 | $17.00 | $10.00 | $33.00 | $14.00 |
| 6 | Removing concrete (gutter) (104-7019) | LF | 1,536 | $12.00 | $9.90 | $13.00 | $17.00 | $10.00 | $32.00 | $14.00 |
| 7 | Removing concrete (retaining walls) (104-7025) | SY | 9.50 | $125.00 | $60.50 | $225.00 | $30.00 | $50.00 | $307.00 | $95.00 |
| 8 | Removing concrete (miscellaneous) (104-7046) | SY | 6.90 | $32.00 | $27.50 | $130.00 | $25.00 | $50.00 | $455.00 | $2,000.00 |
| 9 | Embankment (final)(DC)(type C) (132-7006) | CY | 35 | $25.00 | $29.70 | $125.00 | $100.00 | $80.00 | $73.00 | $200.00 |
| 10 | Class A concrete (miscellaneous) (420-7002) | CY | 6.60 | $800.00 | $1,554.30 | $3,000.00 | $673.84 | $1,800.00 | $1,350.00 | $2,000.00 |
| 11 | Retaining wall (cast-in-place) (423-7016) | SF | 235.50 | $145.00 | $110.00 | $95.00 | $85.00 | $100.00 | $75.00 | $140.00 |
| 12 | Riprap (concrete)(4 in) (432-7001) | CY | 74.35 | $825.00 | $588.50 | $650.00 | $673.84 | $650.00 | $688.00 | $725.00 |
| 13 | STR steel (miscellaneous non-bridge) (442-7007) | LB | 732 | $45.00 | $14.41 | $60.00 | $35.00 | $20.00 | $29.00 | $15.00 |
| 14 | Rail (handrail)(type C) (450-7060) | LF | 159.50 | $200.00 | $117.52 | $300.00 | $186.00 | $220.00 | $189.00 | $164.00 |
| 15 | Rail (handrail)(type E) (450-7062) | LF | 139 | $220.00 | $139.26 | $300.00 | $213.60 | $220.00 | $218.00 | $186.00 |
| 16 | Rail (handrail)(type F) (450-7063) | LF | 42 | $220.00 | $159.95 | $200.00 | $240.00 | $220.00 | $286.00 | $252.00 |
| 17 | CMP AR (gal steel des 3) (460-7018) | LF | 120 | $180.00 | $121.77 | $300.00 | $100.00 | $125.00 | $143.00 | $85.00 |
| 18 | RC pipe (CL III)(24 in) (464-7005) | LF | 39.50 | $200.00 | $69.63 | $450.00 | $151.21 | $140.00 | $220.21 | $190.00 |
| 19 | Set (type II) (24 in) (CMP) (6: 1) (P) (467-7324) | EACH | 4 | $2,500.00 | $852.50 | $2,000.00 | $2,982.72 | $2,250.00 | $3,320.00 | $3,000.00 |
| 20 | Removing structure (pipe) (496-7007) | LF | 116 | $45.00 | $50.08 | $1.00 | $35.00 | $10.00 | $27.00 | $20.00 |
| 21 | Mobilization (500-7001) | LS | 1 | $136,000 | $100,909 | $115,000 | $140,000 | $120,000 | $75,000 | $98,500 |
| 22 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $4,000.00 | $3,300.00 | $2,300.00 | $8,326.00 | $5,000.00 | $22,000 | $10,000 |
| 23 | TMA (stationary) (505-7001) | DAY | 93 | $200.00 | $330.00 | $1.00 | $125.00 | $500.00 | $10.00 | $188.00 |
| 24 | Landscape pavers (528-7001) | SY | 36 | $200.00 | $165.62 | $350.00 | $180.00 | $150.00 | $135.00 | $586.00 |
| 25 | Concrete curb & gutter (type I) (529-7008) | LF | 1,934.50 | $50.00 | $38.50 | $55.00 | $40.63 | $50.00 | $41.00 | $46.00 |
| 26 | Concrete curb & gutter (type II) (529-7009) | LF | 223.50 | $58.00 | $37.95 | $65.00 | $40.63 | $50.00 | $52.00 | $50.00 |
| 27 | Driveways (concrete) (530-7006) | SY | 2,612.30 | $115.00 | $104.50 | $105.00 | $105.00 | $125.00 | $108.00 | $105.00 |
| 28 | Concrete sidewalks (4") (531-7001) | SY | 4,049.90 | $76.00 | $86.90 | $95.00 | $80.94 | $95.00 | $93.00 | $93.00 |
| 29 | Concrete sidewalks (6") (531-7003) | SY | 36 | $160.00 | $107.80 | $110.00 | $90.84 | $125.00 | $108.00 | $175.00 |
| 30 | Curb ramps (type 1) (531-7015) | SY | 172 | $215.00 | $176.00 | $120.00 | $147.21 | $325.00 | $216.00 | $315.00 |
| 31 | Curb ramps (type 2) (531-7016) | SY | 13.50 | $250.00 | $185.90 | $120.00 | $147.21 | $350.00 | $141.00 | $285.00 |
| 32 | Curb ramps (type 5) (531-7018) | SY | 6.50 | $300.00 | $220.00 | $120.00 | $147.21 | $350.00 | $381.00 | $400.00 |
| 33 | Curb ramps (type 7) (531-7020) | SY | 499.10 | $180.00 | $213.40 | $100.00 | $147.21 | $200.00 | $138.00 | $235.00 |
| 34 | Curb ramps (type 10) (531-7021) | SY | 19 | $300.00 | $188.10 | $120.00 | $147.21 | $325.00 | $176.00 | $325.00 |
| 35 | Remove ground box (624-7013) | EACH | 1 | $1,000.00 | $352.00 | $1.00 | $250.00 | $550.00 | $745.00 | $2,000.00 |
| 36 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 2 | $800.00 | $770.00 | $600.00 | $618.00 | $1,250.00 | $337.00 | $1,450.00 |
| 37 | Remove SM RD SN sup&AM (644-7073) | EACH | 6 | $188.00 | $220.00 | $200.00 | $132.00 | $250.00 | $168.00 | $115.00 |
| 38 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 216 | $20.00 | $24.20 | $10.00 | $26.40 | $55.00 | $25.00 | $28.00 |
| 39 | Pedestrian detect push button (APS) (688-7001) | EACH | 16 | $1,410.00 | $2,431.00 | $1,500.00 | $3,650.00 | $1,000.00 | $2,831.00 | $2,400.00 |
| 40 | Removal of pedestrian push buttons (690-7030) | EACH | 16 | $90.00 | $37.95 | $300.00 | $700.00 | $100.00 | $39.00 | $300.00 |
| 41 | Spot tree trimming / brush removal (752-7002) | LF | 157 | $50.00 | $220.00 | $100.00 | $65.00 | $25.00 | $82.00 | $3.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 1, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.