TxDOT contract A00206078 bid tabulation
BRIDGE PREVENTATIVE MAINTENANCE, IH0040 (VARIOUS LOCATIONS ~ SEE PLAN SHEETS to VARIOUS LOCATIONS ~ SEE PLAN SHEETS). Let by Texas DOT on February 6, 2025, Potter, Amarillo District. 7 bids received; low bid $1,595,496 by Built Right Construction of Oklahoma, LLC, -20% against the engineer's estimate of $2,003,276.
- Owner
- Texas DOT
- Letting
- 06 FEB 2025
- Pay items
- 38
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Built Right Construction of Oklahoma, LLC | $1,595,496 | Low | -20% |
| 2 | The Truesdell Corporation | $1,958,958 | +23% | -2.0% |
| 3 | SCR Civil Construction, LLC | $2,244,811 | +41% | +12% |
| 4 | MB Western Industrial Contracting Co. | $2,320,724 | +45% | +16% |
| 5 | Ti-Zack Concrete, LLC | $2,222,924 | +39% | +11% |
| 6 | B & MS Construction, Inc. | $2,397,783 | +50% | +20% |
| 7 | Icos Management, LLC | $3,239,847 | +103% | +62% |
Engineer's estimate: $2,003,276.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Built Right Construction of Oklahoma, LLC | 2. The Truesdell Corporation | 3. SCR Civil Construction, LLC | 4. MB Western Industrial Contracting Co. | 5. Ti-Zack Concrete, LLC | 6. B & MS Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7007) | CY | 28 | $38.00 | $25.00 | $275.00 | $200.00 | $450.00 | $144.00 | $75.00 |
| 2 | Removing concrete (curb) (104-7016) | LF | 8 | $15.00 | $10.00 | $275.00 | $48.00 | $15.00 | $600.00 | $5.00 |
| 3 | Embankment (final)(DC)(type E)(csbe_FND impr) (132-7037) | CY | 12 | $100.00 | $25.00 | $525.00 | $108.00 | $500.00 | $912.00 | $85.00 |
| 4 | Flowable backfill (401-7001) | CY | 5 | $500.00 | $400.00 | $850.00 | $1,200.00 | $750.00 | $660.00 | $385.00 |
| 5 | Class C concrete (rail foundation) (420-7052) | CY | 18 | $865.00 | $1,000.00 | $575.00 | $2,076.00 | $900.00 | $780.00 | $1,200.00 |
| 6 | Class C concrete(pile encasement) (420-7059) | LF | 142 | $1,650.00 | $500.00 | $1,300.00 | $1,633.00 | $2,358.00 | $300.00 | $520.00 |
| 7 | Epoxy waterproof finish (type X) (427-7005) | SF | 1,840 | $15.00 | $20.00 | $13.00 | $14.40 | $15.00 | $18.00 | $22.50 |
| 8 | Penetrating concrete surface treatment (428-7001) | SY | 2,338 | $11.00 | $25.00 | $10.00 | $18.00 | $18.50 | $30.00 | $22.50 |
| 9 | Concrete structure repair(deck rep(part depth)) (429-7003) | SF | 257 | $98.00 | $325.00 | $150.00 | $89.00 | $182.00 | $240.00 | $350.00 |
| 10 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 108 | $300.00 | $275.00 | $320.00 | $200.00 | $268.00 | $276.00 | $298.00 |
| 11 | Riprap (concrete)(5 in) (432-7002) | CY | 95 | $870.00 | $800.00 | $1,450.00 | $2,090.00 | $800.00 | $1,020.00 | $495.00 |
| 12 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 518 | $77.00 | $50.00 | $50.00 | $62.00 | $110.00 | $48.00 | $60.00 |
| 13 | Cleaning existing joints (438-7008) | LF | 967 | $35.00 | $15.00 | $20.00 | $33.00 | $42.00 | $102.00 | $3.50 |
| 14 | Multi-layer polymer overlay (439-7014) | SY | 13,551 | $55.00 | $49.00 | $39.00 | $46.00 | $70.00 | $66.00 | $70.00 |
| 15 | Rail (type T221) (450-7004) | LF | 90 | $166.00 | $300.00 | $1,000.00 | $681.00 | $650.00 | $540.00 | $600.00 |
| 16 | Gabions (galvanized) (459-7001) | CY | 15 | $205.00 | $300.00 | $375.00 | $1,143.00 | $350.00 | $660.00 | $320.00 |
| 17 | Gabion mattresses (galvanized)(9 in) (459-7006) | SY | 40 | $180.00 | $300.00 | $275.00 | $641.00 | $200.00 | $186.00 | $265.00 |
| 18 | Shot blasting (483-7016) | SY | 13,551 | $8.25 | $8.00 | $7.00 | $22.00 | $10.00 | $10.80 | $50.00 |
| 19 | Mobilization (500-7001) | LS | 1 | $160,000 | $150,000 | $501,274 | $216,000 | $200,000 | $150,000 | $35,000 |
| 20 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $25,000 | $3,500.00 | $3,700.00 | $7,500.00 | $2,500.00 | $18,000 | $4,000.00 |
| 21 | Concrete curb (type II) (529-7002) | LF | 40 | $110.00 | $75.00 | $210.00 | $240.00 | $45.00 | $78.00 | $65.00 |
| 22 | Metal W-beam guard fence (steel post) (540-7002) | LF | 375 | $37.00 | $50.00 | $40.00 | $43.50 | $47.00 | $138.00 | $35.00 |
| 23 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,940.00 | $4,000.00 | $3,100.00 | $3,779.00 | $3,690.00 | $12,000 | $1,900.00 |
| 24 | Remove metal beam guard fence (542-7001) | LF | 975 | $3.50 | $8.00 | $4.25 | $5.00 | $5.00 | $30.00 | $12.00 |
| 25 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,645.00 | $4,000.00 | $4,100.00 | $4,580.00 | $4,920.00 | $6,000.00 | $550.00 |
| 26 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $318.00 | $850.00 | $320.00 | $344.00 | $370.00 | $3,000.00 | $300.00 |
| 27 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 41 | $2.00 | $0.01 | $10.00 | $7.00 | $2.00 | $18.00 | $2.50 |
| 28 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 299 | $2.00 | $0.01 | $8.00 | $7.00 | $2.00 | $26.40 | $8.00 |
| 29 | Type I high perf PM (W)6"(broken)(090MIL) (666-7289) | LF | 120 | $6.00 | $8.00 | $7.00 | $6.87 | $7.50 | $6.60 | $6.50 |
| 30 | Type I high perf PM (W)6"(solid)(090MIL) (666-7292) | LF | 2,160 | $6.00 | $8.00 | $6.00 | $6.87 | $7.50 | $6.60 | $9.00 |
| 31 | Type I high perf PM (Y)6"(solid)(090MIL) (666-7304) | LF | 5,972 | $6.00 | $8.00 | $6.00 | $6.87 | $7.50 | $6.60 | $8.50 |
| 32 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 36 | $16.00 | $60.00 | $55.00 | $57.25 | $62.00 | $55.00 | $5.50 |
| 33 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 1 | $250.00 | $650.00 | $700.00 | $573.00 | $615.00 | $550.00 | $120.00 |
| 34 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 2 | $392.00 | $750.00 | $700.00 | $687.00 | $738.00 | $660.00 | $95.00 |
| 35 | Tree removal (4" - 12" diameter) (752-7005) | EACH | 7 | $260.00 | $500.00 | $600.00 | $535.00 | $750.00 | $600.00 | $2,500.00 |
| 36 | Tree removal (12" - 18" diameter) (752-7006) | EACH | 2 | $450.00 | $500.00 | $1,000.00 | $940.00 | $750.00 | $960.00 | $3,500.00 |
| 37 | Bridge joint repair (header) (785-7002) | LF | 31 | $600.00 | $350.00 | $750.00 | $815.00 | $360.00 | $1,020.00 | $250.00 |
| 38 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 61 | $1,500.00 | $500.00 | $525.00 | $1,935.00 | $1,700.00 | $600.00 | $1,450.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 6, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.