TxDOT contract A00206578 bid tabulation
Hazard Elimination & Safety, US 385 (US 87 to SH 354 IN CHANNING). Let by Texas DOT on December 2, 2025, Hartley, Amarillo District. 6 bids received; low bid $15,925,814 by J. Lee Milligan, Inc., -19% against the engineer's estimate of $19,781,316.
- Owner
- Texas DOT
- Letting
- 02 DEC 2025
- Pay items
- 82
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | J. Lee Milligan, Inc. | $15,925,814 | Low | -19% |
| 2 | RK Hall, LLC | $17,606,323 | +11% | -11% |
| 3 | FNF Construction, Inc. | $18,297,530 | +15% | -8.0% |
| 4 | Overland Corporation | $18,809,187 | +18% | -5.0% |
| 5 | Duininck, Inc. | $19,717,866 | +24% | 0.0% |
| 6 | A. L. Helmcamp, Inc. | $19,882,143 | +25% | +1.0% |
Engineer's estimate: $19,781,316.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. J. Lee Milligan, Inc. | 2. RK Hall, LLC | 3. FNF Construction, Inc. | 4. Overland Corporation | 5. Duininck, Inc. | 6. A. L. Helmcamp, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 933 | $11.65 | $10.55 | $25.00 | $75.00 | $13.25 | $500.00 | |
| 2 | Removing concrete (riprap) (104-7006) | SY | 2 | $690.00 | $103.00 | $2,000.00 | $500.00 | $500.00 | $1,000.00 | |
| 3 | Remove (18") TRT/untrt base & asphalt pavement (105-7038) | SY | 12,872 | $14.00 | $9.15 | $14.64 | $7.50 | $18.25 | $17.00 | $20.00 |
| 4 | Excavation (roadway) (110-7001) | CY | 2,671 | $16.00 | $29.70 | $17.04 | $4.00 | $30.00 | $20.50 | $12.00 |
| 5 | Embankment (final)(DC)(type B) (132-7004) | CY | 4,739 | $30.00 | $20.30 | $22.50 | $15.00 | $53.00 | $30.00 | $35.00 |
| 6 | Backfill (type A) (134-7001) | STA | 933 | $185.00 | $206.07 | $235.00 | $210.00 | $310.00 | $730.00 | |
| 7 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 13,111 | $0.25 | $0.23 | $0.25 | $0.22 | $0.22 | $0.24 | |
| 8 | Drill seed (permanent_rural_sand) (164-7009) | SY | 222,761 | $0.20 | $0.15 | $0.12 | $0.13 | $0.12 | $0.12 | $0.13 |
| 9 | Soil ret BLKT(SL_mod_sand_long) (169-7004) | SY | 618 | $3.75 | $3.61 | $3.75 | $3.50 | $3.50 | $4.00 | |
| 10 | FL BS (compacted in place)(type A or B GR 4)(12") (247-7133) | SY | 23,370 | $45.00 | $27.65 | $29.45 | $25.25 | $27.00 | $31.50 | $23.00 |
| 11 | Cement (275-7001) | TON | 274 | $350.00 | $250.00 | $258.51 | $300.00 | $275.00 | $300.00 | $230.00 |
| 12 | Cement TRT (existing material)(8") (275-7003) | SY | 23,370 | $8.00 | $3.35 | $4.84 | $4.00 | $4.00 | $5.00 | $4.20 |
| 13 | Prime coat (MC-30) (310-7004) | GAL | 6,125 | $8.00 | $4.70 | $4.85 | $5.25 | $4.50 | $5.75 | $7.00 |
| 14 | Emuls asphalt (erosion control)(multi) (314-7018) | GAL | 23,587 | $6.00 | $3.50 | $4.57 | $3.75 | $3.50 | $3.90 | $4.50 |
| 15 | Fog seal (CSS-1H) (315-7004) | GAL | 2,435 | $4.35 | $5.64 | $5.00 | $4.75 | $4.50 | $7.00 | |
| 16 | SP mixes SP-D sac-A PG70-28 (344-7057) | TON | 77,395 | $120.00 | $98.00 | $127.96 | $121.00 | $131.00 | $133.50 | $122.82 |
| 17 | Tack coat (344-7077) | GAL | 37,697 | $6.00 | $5.90 | $5.39 | $6.50 | $4.25 | $7.00 | $5.50 |
| 18 | Flexible pavement structure repair(3") (351-7002) | SY | 34,664 | $27.80 | $23.31 | $25.00 | $32.50 | $30.00 | $42.00 | |
| 19 | Planing asphalt concrete pavement(0" to 1") (354-7031) | SY | 889 | $6.30 | $6.55 | $4.00 | $9.00 | $6.00 | $5.00 | |
| 20 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 7,404 | $4.85 | $5.83 | $1.75 | $5.50 | $7.25 | $5.00 | |
| 21 | Planing asphalt concrete pavement(2") (354-7051) | SY | 6,352 | $5.95 | $5.74 | $3.50 | $5.25 | $6.55 | $5.00 | |
| 22 | Planing asphalt concrete pavement (0" to 1.5") (354-7073) | SY | 8,333 | $4.25 | $5.45 | $1.25 | $4.25 | $6.70 | $5.00 | |
| 23 | Flowable backfill (401-7001) | CY | 3 | $1,100.00 | $360.50 | $1,300.00 | $1,450.00 | $1,100.00 | $400.00 | |
| 24 | Class A concrete (collar) (420-7008) | EACH | 5 | $1,645.00 | $1,794.72 | $2,000.00 | $1,500.00 | $1,500.00 | $1,800.00 | |
| 25 | Epoxy waterproof finish (type X) (427-7005) | SF | 7,297 | $3.60 | $14.42 | $10.00 | $6.95 | $6.95 | $28.00 | |
| 26 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 515 | $38.00 | $234.84 | $230.00 | $162.00 | $165.00 | $210.00 | |
| 27 | Riprap (concrete)(CL B) (432-7005) | CY | 16 | $1,335.00 | $824.00 | $1,000.00 | $800.00 | $725.00 | $900.00 | |
| 28 | Riprap (mow strip)(4 in) (432-7013) | CY | 20 | $1,015.00 | $957.18 | $1,100.00 | $800.00 | $800.00 | $900.00 | |
| 29 | Cleaning existing joints (438-7008) | LF | 156 | $18.00 | $35.02 | $23.00 | $10.00 | $10.00 | $12.00 | |
| 30 | RC pipe (CL III)(24 in) (464-7005) | LF | 26 | $250.00 | $251.26 | $400.00 | $210.00 | $210.00 | $230.00 | |
| 31 | RC pipe (CL III)(36 in) (464-7009) | LF | 4 | $465.00 | $454.66 | $950.00 | $380.00 | $380.00 | $420.00 | |
| 32 | RC pipe (CL III)(48 in) (464-7011) | LF | 14 | $450.00 | $628.15 | $500.00 | $525.00 | $525.00 | $580.00 | |
| 33 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 3 | $2,800.00 | $1,675.07 | $2,500.00 | $1,400.00 | $1,400.00 | $1,600.00 | |
| 34 | Set (type II) (36 in) (RCP) (3: 1) (C) (467-7365) | EACH | 1 | $5,000.00 | $2,871.55 | $4,000.00 | $2,400.00 | $2,400.00 | $2,700.00 | |
| 35 | Set (type II) (48 in) (RCP) (3: 1) (C) (467-7389) | EACH | 1 | $7,200.00 | $6,580.63 | $7,000.00 | $5,500.00 | $5,500.00 | $6,500.00 | |
| 36 | Pipe (PVC) (schedule 40) (4 in) (481-7011) | LF | 30 | $100.00 | $103.00 | $55.00 | $70.00 | $70.00 | $85.00 | |
| 37 | Removing structure (set) (496-7004) | EACH | 1 | $1,100.00 | $1,196.48 | $1,300.00 | $1,000.00 | $1,000.00 | $1,100.00 | |
| 38 | Removing structure (headwall) (496-7006) | EACH | 4 | $1,100.00 | $1,196.48 | $2,000.00 | $1,000.00 | $1,000.00 | $1,100.00 | |
| 39 | Removing structure (pipe) (496-7007) | LF | 22 | $255.00 | $23.93 | $250.00 | $20.00 | $20.00 | $25.00 | |
| 40 | Mobilization (500-7001) | LS | 1 | $1,600,000 | $1,450,000 | $600,000 | $1,825,000 | $1,308,000 | $2,000,000 | $1,650,000 |
| 41 | Barricades, signs and traffic handling (502-7001) | MO | 11 | $45,000 | $20,000 | $25,000 | $45,000 | $17,000 | $30,000 | $10,000 |
| 42 | Portable changeable message sign (503-7002) | EACH | 2 | $13,225 | $5,000.00 | $6,000.00 | $18,000 | $12,500 | $15,000 | |
| 43 | TMA (stationary) (505-7001) | DAY | 326 | $250.00 | $512.61 | $200.00 | $480.00 | $250.00 | $250.00 | |
| 44 | TMA (mobile operation) (505-7002) | HR | 56 | $95.00 | $111.21 | $500.00 | $110.00 | $100.00 | $100.00 | |
| 45 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 8,000 | $10.00 | $7.15 | $3.07 | $3.50 | $2.98 | $3.00 | $3.50 |
| 46 | Biodegradable erosion control logs (remove) (506-7046) | LF | 8,000 | $2.00 | $4.15 | $1.03 | $1.10 | $1.00 | $1.00 | $1.00 |
| 47 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 222,303 | $0.30 | $0.25 | $0.15 | $0.15 | $0.15 | $0.14 | $0.27 |
| 48 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 94,757 | $0.30 | $0.25 | $0.15 | $0.20 | $0.15 | $0.15 | $0.27 |
| 49 | Metal W-beam guard fence (steel post) (540-7002) | LF | 1,650 | $35.75 | $28.84 | $40.00 | $28.00 | $28.00 | $31.00 | |
| 50 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $3,075.00 | $2,951.49 | $5,000.00 | $2,285.00 | $2,900.00 | $2,600.00 | |
| 51 | Remove metal beam guard fence (542-7001) | LF | 1,700 | $4.25 | $3.09 | $4.75 | $3.00 | $3.00 | $3.30 | |
| 52 | Guardrail end treatment (install) (544-7001) | EACH | 6 | $4,160.00 | $3,476.25 | $4,500.00 | $3,375.00 | $3,400.00 | $3,800.00 | |
| 53 | Guardrail end treatment (remove) (544-7003) | EACH | 6 | $425.00 | $309.00 | $475.00 | $300.00 | $300.00 | $330.00 | |
| 54 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 3 | $817.00 | $925.00 | $1,033.09 | $1,000.00 | $1,091.10 | $1,010.00 | $960.00 |
| 55 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 11 | $560.00 | $720.00 | $833.27 | $800.00 | $880.06 | $810.00 | $750.00 |
| 56 | Remove SM RD SN sup&AM (644-7073) | EACH | 3 | $110.00 | $103.00 | $120.00 | $108.78 | $125.00 | $110.00 | |
| 57 | Install delineator assembly (D-DW)SZ 1(WFLX)GND (658-7045) | EACH | 148 | $175.00 | $139.00 | $147.29 | $150.00 | $155.56 | $145.00 | $145.00 |
| 58 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 5 | $139.00 | $151.41 | $150.00 | $159.91 | $150.00 | $145.00 | |
| 59 | Install OM SM RD sign (1-OM-PW)Y (658-7317) | EACH | 2 | $1.00 | $11.00 | $16.48 | $12.00 | $17.41 | $16.00 | $12.00 |
| 60 | Install OM SM RD sign (1-OM-PW)R (658-7318) | EACH | 1 | $1.00 | $11.00 | $16.48 | $12.00 | $17.41 | $16.00 | $12.00 |
| 61 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 11,364 | $1.15 | $0.35 | $0.31 | $0.35 | $0.30 | $0.30 | $0.33 |
| 62 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 2,967 | $1.35 | $1.81 | $1.00 | $1.50 | $1.50 | $0.52 | |
| 63 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 10,753 | $2.00 | $1.40 | $1.81 | $1.00 | $1.50 | $1.50 | $0.52 |
| 64 | Reflectorized pavement marking type I (W)6"(DOT)(090MIL) (666-7008) | LF | 3,611 | $0.85 | $0.82 | $0.80 | $0.80 | $0.80 | $0.87 | |
| 65 | Reflectorized pavement marking type I (W)8"(DOT)(090MIL) (666-7017) | LF | 321 | $1.00 | $1.00 | $0.98 | $1.00 | $0.95 | $0.95 | $1.03 |
| 66 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 4,567 | $1.00 | $1.00 | $0.98 | $1.00 | $0.95 | $0.95 | $1.03 |
| 67 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 522 | $11.10 | $10.71 | $12.00 | $10.40 | $10.50 | $11.50 | |
| 68 | Reflectorized pavement marking type I (W)(RR crossing)(090MIL) (666-7080) | EACH | 1 | $685.00 | $659.20 | $700.00 | $640.00 | $640.00 | $710.00 | |
| 69 | Reflectorized pavement marking type I(Y)(med nose)(090MIL) (666-7131) | EACH | 8 | $155.00 | $225.00 | $216.30 | $225.00 | $210.00 | $210.00 | $230.00 |
| 70 | Type I high perf PM (W)6"(broken)(090MIL) (666-7289) | LF | 16,995 | $0.70 | $0.67 | $0.70 | $0.65 | $0.65 | $0.71 | |
| 71 | Type I high perf PM (W)6"(solid)(090MIL) (666-7292) | LF | 248,709 | $0.80 | $0.62 | $0.60 | $0.65 | $0.58 | $0.58 | $0.63 |
| 72 | Type I high perf PM (Y)6"(broken)(090MIL) (666-7301) | LF | 10,563 | $0.70 | $0.67 | $0.70 | $0.65 | $0.65 | $0.71 | |
| 73 | Type I high perf PM (Y)6"(solid)(090MIL) (666-7304) | LF | 210,846 | $0.80 | $0.62 | $0.60 | $0.65 | $0.58 | $0.58 | $0.63 |
| 74 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 12 | $300.00 | $225.00 | $216.30 | $225.00 | $210.00 | $210.00 | $230.00 |
| 75 | Prefabricated PM type C (W)(LN reduct arrow) (668-7100) | EACH | 14 | $345.00 | $334.75 | $375.00 | $325.00 | $325.00 | $360.00 | |
| 76 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 12 | $400.00 | $330.00 | $319.30 | $350.00 | $310.00 | $310.00 | $350.00 |
| 77 | Recessed reflectorized pavement marker type I-C (672-7023) | EACH | 1,105 | $38.00 | $40.00 | $38.63 | $45.00 | $37.50 | $37.50 | $42.00 |
| 78 | Recessed reflectorized pavement marker type II-A-A (672-7025) | EACH | 3,521 | $38.00 | $40.00 | $38.63 | $45.00 | $37.50 | $37.50 | $42.00 |
| 79 | Eliminating existing PM & markers (6") (677-7002) | LF | 20,296 | $0.90 | $0.88 | $1.00 | $0.85 | $0.85 | $1.00 | |
| 80 | JT / CRCK seal (hot - poured rubber) (712-7002) | LF | 330 | $20.00 | $49.44 | $50.00 | $44.00 | $44.00 | $40.00 | |
| 81 | Reinforced fab for asphalt PVMNT overlays (3002-7001) | SY | 401,443 | $6.35 | $6.22 | $6.00 | $6.00 | $6.00 | $6.50 | |
| 82 | Asphalt for reinforced fab (PG70-28) (3002-7003) | GAL | 88,317 | $2.85 | $3.70 | $4.75 | $4.85 | $3.45 | $4.40 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of December 2, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.