TxDOT contract A00207258 bid tabulation
Bridge Replacement, FM 835 (FM 835 to at NFK DBL MTN FK Brazos River). Let by Texas DOT on April 7, 2026, Lubbock, Lubbock District. 2 bids received; low bid $5,991,100 by Webber, LLC, +34% against the engineer's estimate of $4,462,426.
- Owner
- Texas DOT
- Letting
- 07 APR 2026
- Pay items
- 86
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Webber, LLC | $5,991,100 | Low | +34% |
| 2 | FNF Construction, Inc. | $8,396,937 | +40% | +88% |
Engineer's estimate: $4,462,426.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Webber, LLC | 2. FNF Construction, Inc. |
|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 7 | $9,000.00 | $82,800 | $4,000.00 |
| 2 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 7 | $2,500.00 | $1,550.00 | $1,400.00 |
| 3 | Preparation row (tree remove) (24"-36" diameter) (100-7005) | EACH | 2 | $3,000.00 | $2,900.00 | $2,500.00 |
| 4 | Preparation row (tree remove) (36"-48" diameter) (100-7006) | EACH | 3 | $5,000.00 | $3,875.00 | $3,000.00 |
| 5 | Removing concrete (riprap) (104-7006) | SY | 1,658 | $35.00 | $16.00 | $20.00 |
| 6 | Remove (12") TRT/untrt base & asphalt pavement (105-7032) | SY | 2,818 | $14.00 | $20.70 | $22.00 |
| 7 | Excavation (roadway) (110-7001) | CY | 1,302 | $32.00 | $18.70 | $6.00 |
| 8 | Embankment (final)(DC)(type C) (132-7006) | CY | 922 | $40.00 | $15.00 | $11.00 |
| 9 | Drill seed (permanent_rural_sand) (164-7009) | SY | 3,200 | $0.25 | $2.00 | $1.25 |
| 10 | Proof rolling (216-7001) | HR | 10 | $250.00 | $85.50 | $115.00 |
| 11 | Prime coat (AE-P) (310-7001) | GAL | 609 | $5.25 | $14.00 | $5.50 |
| 12 | Emuls asphalt (erosion control)(CSS-1H) (314-7011) | GAL | 832 | $3.40 | $5.50 | $3.25 |
| 13 | D-GR HMA type D sac-A PG70-28 (341-7053) | TON | 237 | $280.00 | $255.00 | $500.00 |
| 14 | Tack coat (341-7082) | GAL | 961 | $4.25 | $6.00 | $8.00 |
| 15 | D-GR HMA type-B sac-B PG70-28 (341-7083) | TON | 1,313 | $240.00 | $200.00 | $275.00 |
| 16 | Flowable backfill (401-7001) | CY | 205 | $400.00 | $255.00 | $400.00 |
| 17 | Temporary special shoring (cofferdam) (403-7002) | SF | 625 | $20.00 | $46.00 | $579.00 |
| 18 | Drilled shaft (24 in) (416-7004) | LF | 120 | $340.00 | $195.00 | $600.00 |
| 19 | Drilled shaft (36 in) (416-7006) | LF | 548 | $375.00 | $240.00 | $500.00 |
| 20 | Class C concrete (abutment)(HPC) (420-7013) | CY | 56.80 | $2,000.00 | $3,600.00 | $5,000.00 |
| 21 | Class C concrete (cap) (420-7022) | CY | 19.20 | $1,800.00 | $2,400.00 | $7,000.00 |
| 22 | Class C concrete (cap)(HPC) (420-7023) | CY | 27.60 | $2,500.00 | $2,900.00 | $4,000.00 |
| 23 | Class C concrete (column)(HPC) (420-7039) | CY | 12.50 | $2,800.00 | $2,550.00 | $3,000.00 |
| 24 | Approach slab (HPC) (422-7014) | CY | 107 | $1,000.00 | $1,500.00 | $1,000.00 |
| 25 | Slab span (422-7017) | CY | 32.60 | $950.00 | $2,200.00 | $2,500.00 |
| 26 | Reinforced concrete slab (precast super assem) (422-7023) | SF | 6,790 | $65.00 | $95.50 | $140.00 |
| 27 | Epoxy waterproof finish (type X) (427-7005) | SF | 1,622 | $15.00 | $17.00 | $25.00 |
| 28 | Riprap (concrete)(5 in) (432-7002) | CY | 232 | $700.00 | $750.00 | $1,400.00 |
| 29 | Riprap (mow strip)(5 in) (432-7014) | CY | 49 | $600.00 | $700.00 | $600.00 |
| 30 | Riprap (stone common)(dry)(18 in) (432-7033) | CY | 15 | $350.00 | $1,200.00 | $260.00 |
| 31 | Multi-layer polymer overlay (439-7014) | SY | 1,078 | $55.00 | $40.00 | $90.00 |
| 32 | Rail (type T223) (450-7008) | LF | 390 | $220.00 | $140.00 | $350.00 |
| 33 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 106 | $250.00 | $256.00 | $350.00 |
| 34 | Concrete box culvert (8 FT X 3 FT) (462-7020) | LF | 64 | $850.00 | $825.00 | $1,200.00 |
| 35 | Wingwall (SW - 0) (HW=4 FT) (466-7203) | EACH | 1 | $15,000 | $15,002 | $27,000 |
| 36 | Set (type I)(S= 8 FT)(HW= 4 FT)(6:1)(P) (467-7182) | EACH | 1 | $30,000 | $25,000 | $35,000 |
| 37 | Diamond grinding slab (abc) (483-7019) | SY | 1,078 | $12.00 | $14.00 | $31.00 |
| 38 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $250,000 | $650,000 | $325,000 |
| 39 | Mobilization (500-7001) | LS | 1 | $402,300 | $590,000 | $833,000 |
| 40 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $13,500 | $7,000.00 | $30,000 |
| 41 | Portable changeable message sign (503-7001) | DAY | 177 | $85.00 | $72.00 | $50.00 |
| 42 | TMA (stationary) (505-7001) | DAY | 25 | $250.00 | $350.00 | $200.00 |
| 43 | TMA (mobile operation) (505-7003) | DAY | 3 | $200.00 | $600.00 | $1,000.00 |
| 44 | Rock filter dams (install) (type 1) (506-7001) | LF | 280 | $45.00 | $40.00 | $50.00 |
| 45 | Rock filter dams (remove) (506-7011) | LF | 280 | $15.00 | $15.00 | $23.00 |
| 46 | Construction exits (install) (type 1) (506-7020) | SY | 444 | $40.00 | $25.00 | $50.00 |
| 47 | Construction exits (remove) (506-7024) | SY | 444 | $15.00 | $10.00 | $30.00 |
| 48 | Temporary sediment control fence (install) (506-7039) | LF | 3,592 | $8.00 | $5.00 | $6.00 |
| 49 | Temporary sediment control fence (remove) (506-7041) | LF | 3,592 | $4.00 | $0.50 | $0.50 |
| 50 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 120 | $9.00 | $16.00 | $23.00 |
| 51 | Biodegradable erosion control logs (remove) (506-7046) | LF | 120 | $2.50 | $3.50 | $5.00 |
| 52 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 90 | $60.00 | $50.00 | $65.00 |
| 53 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 60 | $25.00 | $20.00 | $9.00 |
| 54 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 90 | $30.00 | $25.00 | $65.00 |
| 55 | Metal W-beam guard fence (steel post) (540-7002) | LF | 150 | $30.00 | $36.00 | $64.00 |
| 56 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 3 | $2,100.00 | $2,400.00 | $5,300.00 |
| 57 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 1 | $990.00 | $1,500.00 | $4,000.00 |
| 58 | Metal beam guard fence (long span system) (540-7027) | EACH | 1 | $1,500.00 | $1,630.00 | $4,000.00 |
| 59 | Remove metal beam guard fence (542-7001) | LF | 413 | $4.00 | $4.00 | $14.00 |
| 60 | Guardrail end treatment (install) (544-7001) | EACH | 6 | $3,500.00 | $3,600.00 | $5,500.00 |
| 61 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $180.00 | $350.00 | $2,150.00 |
| 62 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 1 | $780.00 | $1,350.00 | $1,800.00 |
| 63 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 1 | $960.00 | $1,500.00 | $2,100.00 |
| 64 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 1 | $880.00 | $1,450.00 | $1,800.00 |
| 65 | Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034) | EACH | 1 | $1,350.00 | $2,000.00 | $2,450.00 |
| 66 | Remove SM RD SN sup&AM (644-7073) | EACH | 4 | $120.00 | $100.00 | $180.00 |
| 67 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 5 | $65.00 | $200.00 | $260.00 |
| 68 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 9 | $25.00 | $200.00 | $260.00 |
| 69 | Install OM SM RD sign (1-OM-PW)Y (658-7317) | EACH | 3 | $15.00 | $100.00 | $120.00 |
| 70 | Install OM SM RD sign (1-OM-PW)R (658-7318) | EACH | 1 | $15.00 | $100.00 | $120.00 |
| 71 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 2,740 | $0.25 | $1.50 | $2.00 |
| 72 | Reflectorized pavement marking type II (W) 12" (solid) (666-7182) | LF | 318 | $2.30 | $7.50 | $10.00 |
| 73 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 3,092 | $0.25 | $1.50 | $2.00 |
| 74 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 18 | $16.00 | $20.00 | $28.00 |
| 75 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 20 | $4.25 | $10.00 | $14.00 |
| 76 | Pavement surface preparation for marking (6") (678-7002) | LF | 2,916 | $2.00 | $2.50 | $3.50 |
| 77 | Pavement surface preparation for marking (12") (678-7006) | LF | 159 | $4.20 | $4.00 | $5.50 |
| 78 | Pavement surface preparation for marking (24") (678-7008) | LF | 18 | $5.00 | $6.00 | $8.50 |
| 79 | Litter pickup (751-7019) | CYC | 1 | $1,500.00 | $500.00 | $1,000.00 |
| 80 | Mowing, trimming, and edging (751-7028) | CYC | 1 | $1,200.00 | $1,000.00 | $13,500 |
| 81 | Reinforced fab for asphalt PVMNT overlays (3002-7001) | SY | 1,364 | $7.00 | $7.00 | $14.00 |
| 82 | Asphalt for reinforced fab (PG76-28) (3002-7002) | GAL | 205 | $4.00 | $325.00 | $8.50 |
| 83 | Temporary construction access (4006-7001) | LS | 1 | $250,000 | $755,000 | $800,000 |
| 84 | Rapid setting fiber reinforced concrete (RSFRC) (4054-7001) | CY | 18.40 | $7,500.00 | $5,000.00 | $6,500.00 |
| 85 | STR steel (press brake) (4067-7001) | LB | 187,386 | $4.10 | $3.00 | $9.50 |
| 86 | Dewatering reports (5050-7001) | EACH | 20 | $60.00 | $60.00 | $60.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 7, 2026. Compiled by Mirage Metrics.