TxDOT contract A00209704 bid tabulation
Bridge Maintenance, IH 30 (At Clendeling Creek to .). Let by Texas DOT on January 7, 2026, Hopkins, Paris District. 6 bids received; low bid $2,279,665 by THK Construction LLC, -21% against the engineer's estimate of $2,874,516.
- Owner
- Texas DOT
- Letting
- 07 JAN 2026
- Pay items
- 61
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | THK Construction LLC | $2,279,665 | Low | -21% |
| 2 | Highway 19 Construction LLC | $2,645,676 | +16% | -8.0% |
| 3 | Built Right Construction of Oklahoma, LLC | $3,084,601 | +35% | +7.0% |
| 4 | Gibson & Associates, Inc. | $3,261,637 | +43% | +13% |
| 5 | Granite Construction Company | $4,176,194 | +83% | +45% |
| 6 | Hodges and Son Construction Company, Inc. | $4,600,065 | +102% | +60% |
Engineer's estimate: $2,874,516.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. THK Construction LLC | 2. Highway 19 Construction LLC | 3. Built Right Construction of Oklahoma, LLC | 4. Gibson & Associates, Inc. | 5. Granite Construction Company | 6. Hodges and Son Construction Company, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7007) | CY | 247.60 | $225.00 | $40.00 | $25.00 | $25.00 | $55.00 | $420.00 | $185.00 |
| 2 | D-GR HMA type D sac-A PG64-22 (exempt) (341-7062) | TON | 72 | $250.00 | $225.00 | $500.00 | $300.00 | $579.70 | $180.00 | $450.00 |
| 3 | Tack coat (347-7011) | GAL | 132 | $2.00 | $20.00 | $10.00 | $30.00 | $1.65 | $10.00 | $2.00 |
| 4 | Flowable backfill (401-7001) | CY | 2 | $1,500.00 | $500.00 | $400.00 | $1,000.00 | $1,250.00 | $900.00 | |
| 5 | Reinforced concrete slab (422-7001) | SF | 9,329 | $40.00 | $27.00 | $40.00 | $45.00 | $42.90 | $98.00 | $48.00 |
| 6 | Approach slab (422-7013) | CY | 47 | $875.00 | $850.00 | $750.00 | $400.00 | $1,320.00 | $1,500.00 | $900.00 |
| 7 | Penetrating concrete surface treatment (428-7001) | SY | 540 | $15.00 | $15.00 | $34.00 | $25.00 | $19.80 | $20.00 | $25.00 |
| 8 | Concrete structure repair(clean & coat WTH epoxy) (429-7001) | SF | 82 | $225.00 | $150.00 | $140.00 | $275.00 | $66.00 | $140.00 | $200.00 |
| 9 | Concrete structure repair(deck rep(part depth)) (429-7003) | SF | 1,535 | $175.00 | $150.00 | $45.00 | $304.00 | $35.00 | $50.00 | $190.00 |
| 10 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 255 | $200.00 | $140.00 | $165.00 | $250.00 | $176.00 | $250.00 | $300.00 |
| 11 | Riprap (mow strip)(4 in) (432-7013) | CY | 35.20 | $500.00 | $800.00 | $550.00 | $600.00 | $770.00 | $1,200.00 | $700.00 |
| 12 | Riprap (stone protection)(18 in) (432-7043) | CY | 1,504.60 | $195.00 | $190.00 | $180.00 | $225.00 | $214.50 | $235.00 | $270.00 |
| 13 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 504 | $60.00 | $34.24 | $35.00 | $60.00 | $13.20 | $26.00 | $35.00 |
| 14 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 772 | $50.00 | $47.08 | $55.00 | $60.00 | $33.00 | $33.00 | $45.00 |
| 15 | Concrete overlay (2 in) (439-7002) | SY | 2,892 | $90.00 | $40.00 | $90.00 | $90.00 | $130.00 | $110.00 | $200.00 |
| 16 | Clean & paint existing STR (special protection sys) (446-7003) | LS | 1 | $125,000 | $42,800 | $70,000 | $65,000 | $44,000 | $85,000 | $60,000 |
| 17 | Rail (type T221) (450-7004) | LF | 580 | $100.00 | $170.00 | $180.00 | $115.00 | $220.00 | $200.00 | $170.00 |
| 18 | Armor joint (sealed) (454-7003) | LF | 90 | $150.00 | $150.00 | $180.00 | $175.00 | $275.00 | $250.00 | $200.00 |
| 19 | Hydro-demolition (3/4 in) (483-7007) | SY | 116 | $80.00 | $70.00 | $150.00 | $70.00 | $126.50 | $200.00 | $400.00 |
| 20 | Hydro-demolition (2 in) (483-7010) | SY | 2,892 | $120.00 | $102.00 | $75.00 | $125.00 | $126.50 | $125.00 | $290.00 |
| 21 | Removing structure (bridge slab) (496-7013) | EACH | 1 | $100,000 | $100,000 | $160,000 | $125,000 | $342,000 | $300,000 | $300,000 |
| 22 | Removing structure (approach slab) (496-7022) | EACH | 2 | $18,000 | $10,000 | $5,000.00 | $5,000.00 | $7,500.00 | $8,500.00 | $10,000 |
| 23 | Mobilization (500-7001) | LS | 1 | $260,000 | $200,000 | $300,000 | $156,000 | $315,000 | $400,000 | $415,000 |
| 24 | Barricades, signs and traffic handling (502-7001) | MO | 18 | $6,500.00 | $4,126.78 | $5,000.00 | $5,000.00 | $9,500.00 | $26,000 | $10,000 |
| 25 | Portable changeable message sign (503-7001) | DAY | 266 | $75.00 | $50.00 | $50.00 | $65.00 | $95.00 | $75.00 | $100.00 |
| 26 | TMA (stationary) (505-7001) | DAY | 218 | $250.00 | $150.00 | $200.00 | $300.00 | $350.00 | $180.00 | $300.00 |
| 27 | TMA (mobile operation) (505-7003) | DAY | 49 | $150.00 | $300.00 | $500.00 | $300.00 | $350.00 | $1,050.00 | $300.00 |
| 28 | Temporary sediment control fence (install) (506-7039) | LF | 3,306 | $4.00 | $3.85 | $4.00 | $5.00 | $3.96 | $5.00 | $1.00 |
| 29 | Temporary sediment control fence (remove) (506-7041) | LF | 3,306 | $1.50 | $1.18 | $1.00 | $2.00 | $1.21 | $1.10 | $1.00 |
| 30 | One-way traffic control (flagger cont) (510-7001) | HR | 344 | $45.00 | $25.00 | $180.00 | $15.00 | $200.00 | $75.00 | $430.00 |
| 31 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 840 | $50.00 | $25.00 | $97.00 | $100.00 | $36.00 | $1.00 | $80.00 |
| 32 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 840 | $10.00 | $15.00 | $25.00 | $15.00 | $11.00 | $20.00 | $12.00 |
| 33 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 840 | $15.00 | $20.00 | $25.00 | $30.00 | $15.00 | $1.00 | $45.00 |
| 34 | Metal W-beam guard fence (steel post) (540-7002) | LF | 600 | $30.00 | $26.75 | $27.00 | $32.00 | $35.20 | $26.00 | $26.00 |
| 35 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,000.00 | $2,059.75 | $2,500.00 | $2,700.00 | $2,420.00 | $1,880.00 | $2,000.00 |
| 36 | Remove metal beam guard fence (542-7001) | LF | 800 | $15.00 | $2.14 | $4.00 | $4.00 | $3.85 | $2.00 | $2.00 |
| 37 | RM metal beam guard fence trans (TL-2) (542-7006) | EACH | 4 | $250.00 | $160.50 | $350.00 | $400.00 | $165.00 | $200.00 | $300.00 |
| 38 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,000.00 | $3,103.00 | $3,200.00 | $4,000.00 | $3,410.00 | $2,840.00 | $3,200.00 |
| 39 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $275.00 | $214.00 | $290.00 | $400.00 | $302.50 | $200.00 | $500.00 |
| 40 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 5 | $2,500.00 | $2,140.00 | $2,000.00 | $1,500.00 | $1,831.50 | $5,000.00 | $2,000.00 |
| 41 | Crash cushion attenuator (remove) (545-7004) | EACH | 5 | $1,000.00 | $856.00 | $1,000.00 | $1,000.00 | $891.00 | $500.00 | $2,000.00 |
| 42 | Crash cushion attenuator (install)(S)(W)(TL3) (545-7016) | EACH | 5 | $10,000 | $9,095.00 | $5,000.00 | $10,000 | $8,728.50 | $8,000.00 | $9,000.00 |
| 43 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 132 | $30.00 | $10.00 | $25.00 | $10.00 | $13.00 | $10.00 | |
| 44 | RE PV marking type I(black)6"(shadow)(100MIL) (666-7138) | LF | 470 | $2.00 | $5.35 | $5.00 | $6.00 | $5.50 | $5.00 | $10.00 |
| 45 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 470 | $0.50 | $5.35 | $5.00 | $6.00 | $5.50 | $5.00 | $10.00 |
| 46 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 1,334 | $0.50 | $5.35 | $5.00 | $6.00 | $5.50 | $5.00 | $5.00 |
| 47 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 2,300 | $0.50 | $5.35 | $5.00 | $6.00 | $5.50 | $5.00 | $4.00 |
| 48 | Pavement sler 6" (666-7347) | LF | 4,184 | $0.30 | $2.68 | $2.50 | $3.00 | $2.75 | $2.50 | $0.75 |
| 49 | Reflectorized pavement marker type I-A (672-7001) | EACH | 168 | $5.00 | $10.70 | $10.00 | $15.00 | $11.00 | $10.00 | $15.00 |
| 50 | Reflectorized pavement marker type I-C (672-7002) | EACH | 247 | $4.00 | $10.70 | $10.00 | $15.00 | $11.00 | $10.00 | $10.00 |
| 51 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 55 | $10.70 | $10.00 | $15.00 | $11.00 | $10.00 | $15.00 | |
| 52 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 52 | $5.00 | $10.70 | $10.00 | $15.00 | $11.00 | $10.00 | $15.00 |
| 53 | Traffic button type W (672-7007) | EACH | 740 | $2.50 | $7.49 | $7.00 | $10.00 | $7.70 | $7.00 | $10.00 |
| 54 | Traffic button type Y (672-7008) | EACH | 669 | $2.50 | $7.49 | $7.00 | $10.00 | $7.70 | $7.00 | $10.00 |
| 55 | Eliminating existing PM & markers (6") (677-7002) | LF | 2,064 | $0.50 | $2.68 | $2.50 | $3.00 | $2.75 | $2.50 | $2.00 |
| 56 | Pavement surface preparation for marking (6") (678-7002) | LF | 4,184 | $0.50 | $0.54 | $1.00 | $0.75 | $0.55 | $0.50 | $0.50 |
| 57 | Pavement surface preparation for marking (RPM) (678-7033) | EACH | 1,931 | $1.00 | $1.07 | $1.00 | $1.40 | $1.10 | $1.00 | $0.50 |
| 58 | Crack cleaning and sealing (JCP) (713-7004) | LF | 40 | $45.00 | $100.00 | $10.00 | $93.50 | $65.00 | $50.00 | |
| 59 | Concrete rail repair (in-kind) (778-7001) | LF | 8 | $1,500.00 | $100.00 | $300.00 | $632.50 | $500.00 | $400.00 | |
| 60 | CNC crack repair (discrete)(gravity) (780-7001) | LF | 80 | $50.00 | $75.00 | $100.00 | $25.00 | $55.00 | $70.00 | $300.00 |
| 61 | Carbon fiber reinforced polymer protection (786-7001) | SF | 80 | $150.00 | $180.00 | $100.00 | $101.20 | $130.00 | $300.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.