BRIDGE PREVENTATIVE MAINTENANCE, RM0963 (VARIOUS LOCATIONS IN to THE AUSTIN DISTRICT). Let by Texas DOT on April 9, 2025, Burnet, Austin District. 7 bids received; low bid $347,061 by Taylor Bridge LLC, -32% against the engineer's estimate of $509,574.
- Owner
- Texas DOT
- Letting
- 09 APR 2025
- Pay items
- 28
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Taylor Bridge LLC | $347,061 | Low | -32% |
| 2 | Structural Integrity Group LLC | $398,960 | +15% | -22% |
| 3 | BK Field Operations LLC | $424,245 | +22% | -17% |
| 4 | MPB, Inc. | $426,146 | +23% | -16% |
| 5 | Built Right Construction of Oklahoma, LLC | $476,505 | +37% | -6.0% |
| 6 | Premier Contractors LLC | $501,338 | +44% | -2.0% |
| 7 | SCR Civil Construction, LLC | $660,500 | +90% | +30% |
Engineer's estimate: $509,574.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Taylor Bridge LLC | 2. Structural Integrity Group LLC | 3. BK Field Operations LLC | 4. MPB, Inc. | 5. Built Right Construction of Oklahoma, LLC | 6. Premier Contractors LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Furn & place topsoil (4") (160-7002) | SY | 2,000 | $3.00 | $2.00 | $15.00 | $9.00 | $15.50 | $20.00 | $5.00 |
| 2 | Drill seed (permanent_rural_sand) (164-7009) | SY | 2,000 | $0.71 | $0.50 | $5.00 | $2.50 | $8.00 | $2.50 | $2.00 |
| 3 | Vegetative watering (168-7001) | TGL | 33.60 | $106.00 | $100.00 | $400.00 | $50.00 | $425.00 | $200.00 | $120.00 |
| 4 | Flowable backfill (401-7001) | CY | 14 | $950.00 | $1,000.00 | $760.00 | $600.00 | $1,300.00 | $500.00 | $1,000.00 |
| 5 | Class C concrete(pile encasement) (420-7059) | LF | 35 | $1,635.00 | $1,500.00 | $400.00 | $1,200.00 | $650.00 | $3,500.00 | $1,200.00 |
| 6 | Concrete structure repair(clean & coat WTH epoxy) (429-7001) | SF | 39 | $240.00 | $250.00 | $125.00 | $150.00 | $225.00 | $350.00 | $500.00 |
| 7 | Concrete structure repair(deck rep (full depth)) (429-7005) | SF | 4 | $550.00 | $1,000.00 | $1,100.00 | $650.00 | $850.00 | $750.00 | $500.00 |
| 8 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 64 | $250.00 | $1,500.00 | $260.00 | $180.00 | $150.00 | $350.00 | $500.00 |
| 9 | Riprap (concrete)(5 in) (432-7002) | CY | 6 | $780.00 | $1,500.00 | $1,500.00 | $1,000.00 | $3,000.00 | $1,500.00 | $1,000.00 |
| 10 | Riprap (stone protection)(24 in) (432-7045) | CY | 44 | $260.00 | $500.00 | $325.00 | $230.00 | $825.00 | $350.00 | $500.00 |
| 11 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 643 | $55.00 | $65.00 | $70.00 | $55.00 | $42.00 | $75.00 | $220.00 |
| 12 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 28 | $55.00 | $125.00 | $50.00 | $55.00 | $25.00 | $75.00 | $150.00 |
| 13 | Cleaning & sealing existing joint (SEJ) (438-7013) | LF | 56 | $85.00 | $50.00 | $115.00 | $95.00 | $95.00 | $125.00 | $200.00 |
| 14 | Mobilization (500-7001) | LS | 1 | $145,593 | $40,000 | $63,000 | $100,000 | $35,000 | $46,000 | $40,000 |
| 15 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $6,500.00 | $1.00 | $16,000 | $8,000.00 | $8,500.00 | $4,000.00 | $1.00 |
| 16 | Portable changeable message sign (503-7001) | DAY | 340 | $222.00 | $1.00 | $1.00 | $80.00 | $100.00 | $10.00 | $1.00 |
| 17 | TMA (stationary) (505-7001) | DAY | 100 | $495.00 | $1.00 | $1.00 | $1.00 | $150.00 | $100.00 | $1.00 |
| 18 | Temporary sediment control fence (install) (506-7039) | LF | 2,180 | $4.00 | $1.00 | $5.00 | $10.00 | $8.00 | $5.00 | $5.00 |
| 19 | Temporary sediment control fence (remove) (506-7041) | LF | 2,180 | $1.00 | $1.00 | $1.00 | $5.00 | $2.00 | $2.00 | $5.00 |
| 20 | Tree removal (4" - 12" diameter) (752-7005) | EACH | 1 | $400.00 | $50.00 | $400.00 | $500.00 | $500.00 | $1,500.00 | $200.00 |
| 21 | Drain inlet cleaning (764-7001) | EACH | 2 | $90.00 | $50.00 | $800.00 | $750.00 | $500.00 | $5,000.00 | $550.00 |
| 22 | Replace timber post W/O concrete FND (770-7006) | EACH | 72 | $30.00 | $50.00 | $145.00 | $100.00 | $245.00 | $500.00 | $1,000.00 |
| 23 | Repair steel post with base plate (770-7019) | EACH | 1 | $410.00 | $1,000.00 | $1,250.00 | $500.00 | $575.00 | $1,500.00 | $2,000.00 |
| 24 | CNC crack repair (discrete)(inject) (780-7002) | LF | 30 | $250.00 | $200.00 | $165.00 | $65.00 | $215.00 | $150.00 | $500.00 |
| 25 | Rep steel bridge MBR (anchor bolt nuts) (784-7021) | EACH | 1 | $900.00 | $5,000.00 | $495.00 | $5,000.00 | $1,000.00 | $350.00 | $10,000 |
| 26 | Rep steel bridge MBR (weld repair) (784-7022) | EACH | 1 | $2,500.00 | $15,000 | $5,050.00 | $20,000 | $8,850.00 | $5,000.00 | $10,000 |
| 27 | Bridge joint repair (SEJ) (785-7005) | LF | 28 | $150.00 | $100.00 | $745.00 | $900.00 | $750.00 | $500.00 | $500.00 |
| 28 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 2 | $2,000.00 | $2,500.00 | $625.00 | $500.00 | $500.00 | $1,500.00 | $1,200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.