TxDOT contract A00213103 bid tabulation

METAL BEAM GUARD FENCE REPAIR, US0377 (DISTRICT-WIDE to DISTRICT-WIDE). Let by Texas DOT on February 6, 2025, Brown, Brownwood District. 7 bids received; low bid $1,320,359 by Ross Sa Enterprise LLC, -33% against the engineer's estimate of $1,972,330.

Owner
Texas DOT
Letting
06 FEB 2025
Pay items
51
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Ross Sa Enterprise LLC$1,320,359Low-33%
2BK Field Operations LLC$1,344,870+2.0%-32%
3T&L Cleaning Services LLC$1,389,159+5.0%-30%
4Lakey, Inc.$1,744,890+32%-12%
5HJC Farms, Inc.$1,911,715+45%-3.0%
6B & MS Construction, Inc.$1,973,030+49%0.0%
7Above All Contracting LLC$2,143,015+62%+9.0%
TxDOT contract A00213103: bids by rank

Engineer's estimate: $1,972,330.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Ross Sa Enterprise LLC2. BK Field Operations LLC3. T&L Cleaning Services LLC4. Lakey, Inc.5. HJC Farms, Inc.6. B & MS Construction, Inc.
1Riprap (mow strip)(4 in) (432-7013)CY5$477.76$450.00$300.00$500.00$700.00$500.00$489.00
2Mobilization (callout) (500-7002)EACH10$4,000.00$1.00$1.00$1.00$100.00$10,000$3,500.00
3TMA (stationary) (505-7001)DAY130$334.94$2,000.00$1.00$1.00$205.00$200.00$310.00
4Metal W-beam guard fence (timber post) (540-7001)LF2,500$29.87$10.00$11.00$21.00$28.65$10.00$45.00
5Metal W-beam guard fence (steel post) (540-7002)LF5,000$37.22$10.00$15.00$24.00$33.00$30.00$55.00
6Metal beam guard fence trans (thrie-beam) (540-7005)EACH10$2,444.55$1,350.00$1,000.00$1,500.00$2,370.00$2,500.00$2,000.00
7Metal beam guard fence trans (T101) (540-7007)EACH2$889.23$500.00$500.00$100.00$1,000.00$10.00$1,850.00
8Short radius (28") (540-7013)LF100$277.24$20.00$20.00$20.00$382.70$25.00$75.00
9Downstream anchor terminal section (540-7015)EACH5$1,618.23$1,000.00$1,100.00$1,500.00$1,500.00$1,000.00$1,850.00
10Metal W - beam guard fence (low fill culvert) (540-7018)LF25$92.80$50.00$70.00$20.00$95.00$75.00$35.00
11Metal beam guard fence (long span system) (540-7027)EACH5$1,432.60$1.00$500.00$100.00$867.41$1,500.00$1,350.00
12Metal beam guard fence trans (31"-28")(25') (540-7031)EACH30$1,676.11$450.00$150.00$100.00$1,400.00$500.00$700.00
13Terminal anchor section (540-7041)EACH5$1,464.77$1.00$1.00$100.00$1,600.00$1.00$800.00
14Remove metal beam guard fence (542-7001)LF2,000$4.49$1.00$14.00$0.01$3.00$1.00$5.00
15Remove terminal anchor section (542-7002)EACH10$385.52$1.00$1.00$1.00$236.14$1.00$350.00
16Remove downstream anchor terminal (542-7003)EACH10$220.78$1.00$1.00$1.00$170.00$1.00$350.00
17Guardrail end TRTMNT(retro)(steel post) (544-7008)EACH2$4,067.00$1.00$500.00$1.00$2,000.00$250.00$1,100.00
18Guardrail end TRTMNT(retro)(wood post) (544-7009)EACH2$5,580.00$1.00$500.00$1.00$2,000.00$250.00$750.00
19Replace rail element (W-beam) (770-7001)LF4,500$23.00$5.00$11.00$18.00$23.00$27.50$35.00
20Repl rail elmnt(thrie-BM trans to W-BM) (770-7003)EACH25$52.00$10.00$750.00$20.00$20.00$300.00$30.00
21Replace timber post W/O concrete FND (770-7006)EACH250$69.02$1.00$100.00$20.00$5.50$50.00$60.00
22Replace steel post W/O concrete FND (770-7007)EACH300$68.90$85.00$70.00$40.00$52.50$75.00$55.00
23Replace timber post W/ concrete FND (770-7008)EACH20$33.30$85.00$20.00$25.00$5.50$50.00$45.00
24Replace steel post W/ concrete FND (770-7009)EACH300$79.05$85.00$100.00$45.00$65.00$75.00$55.00
25Realign posts (770-7010)EACH150$41.71$95.00$1.00$5.00$22.50$10.00$30.00
26Rem obsolete get & repl W/ SGT (770-7013)EACH150$3,965.23$3,000.00$3,400.00$4,000.00$4,200.00$3,700.00$3,600.00
27Repl single gdrail terminal impact head (770-7015)EACH25$1,036.32$750.00$625.00$750.00$925.00$1,250.00$1,200.00
28Replace single gdrail terminal rail (770-7016)LF500$31.69$50.00$50.00$20.00$27.50$50.00$35.00
29Replace single gdrail terminal post (770-7017)EACH100$155.00$1.00$60.00$20.00$165.00$100.00$150.00
30Replace blockout (770-7018)EACH300$56.04$85.00$250.00$10.00$20.00$15.00$32.00
31Repair steel post with base plate (770-7019)EACH5$178.88$100.00$100.00$200.00$65.00$5.00$350.00
32Reset SGT impact head (770-7020)EACH25$267.15$100.00$80.00$1.00$100.00$150.00$150.00
33Replace SGT object marker (770-7021)EACH5$91.99$1.00$25.00$30.00$1.00$50.00$45.00
34Replace SGT cable anchor (770-7022)EACH10$52.73$1.00$60.00$1.00$1.00$75.00$78.00
35Replace SGT cable assembly (770-7023)EACH10$53.75$1.00$60.00$1.00$1.00$75.00$78.00
36Replace SGT strut (770-7024)EACH10$73.95$1.00$60.00$1.00$1.00$75.00$80.00
37Replace downstream anchor terminal (770-7026)EACH10$1,265.00$1,000.00$750.00$1,500.00$1,175.00$1,200.00$1,650.00
38Replace posts (TL-3)(gibraltar) (771-7001)EACH1,500$58.00$6.00$140.00$80.00$115.00$200.00$75.00
39Replace posts (TL-3)(trinity) (771-7003)EACH1,500$147.00$8.00$1.00$130.00$1.00$200.00$170.00
40Replace posts (TL-4)(gibraltar) (771-7005)EACH500$310.00$184.00$180.00$160.00$200.00$100.00$190.00
41Cable splice / turnbuckle (TL-3) (771-7009)EACH10$183.73$100.00$90.00$1.00$127.63$1.00$190.00
42Cable splice / turnbuckle (TL-4) (771-7010)EACH10$120.09$100.00$90.00$1.00$50.00$1.00$275.00
43Repair or replace cable barrier terminal sec(TL-3) (771-7013)EACH20$1,159.42$1,200.00$2,000.00$500.00$1,500.00$2,500.00$1,600.00
44Repair or replace cable barrier terminal sec(TL-4) (771-7014)EACH10$2,058.66$1,450.00$1,500.00$1,000.00$1,350.00$1,000.00$900.00
45Replace cable (TL-3) (771-7015)LF50$1.21$234.00$100.00$1.00$0.75$0.50$125.00
46Replace post hardware (TL-3) (771-7019)EACH100$23.00$1,421.00$150.00$20.00$525.00$20.00$165.00
47Replace post hardware (TL-4) (771-7020)EACH100$762.50$141.00$150.00$20.00$1,000.00$1.00$190.00
48Repair (T101) (776-7006)LF50$20.00$1.00$1.00$20.00$45.00$5.00$75.00
49Repair (steel post W/ base plate)(T101) (776-7007)EACH5$118.57$1.00$1.00$100.00$110.00$50.00$275.00
50Repair steel post W/ base plate (T6) (776-7015)EACH5$128.39$200.00$150.00$100.00$100.00$50.00$180.00
51Replace(steel rail) (776-7024)LF25$292.00$1.00$40.00$20.00$307.00$5.00$390.00
TxDOT contract A00213103: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of February 6, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy