TxDOT contract A00213214 bid tabulation
BRIDGE REPAIR, SH0081 (Various locations to Across the Waco District). Let by Texas DOT on November 5, 2025, Hill, Waco District. 7 bids received; low bid $1,179,951 by Taylor Bridge LLC, -24% against the engineer's estimate of $1,552,814.
- Owner
- Texas DOT
- Letting
- 05 NOV 2025
- Pay items
- 48
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Taylor Bridge LLC | $1,179,951 | Low | -24% |
| 2 | Pathfield Investments LLC | $1,327,095 | +12% | -15% |
| 3 | Structural Integrity Group LLC | $1,516,730 | +29% | -2.0% |
| 4 | Built Right Construction of Oklahoma, LLC | $2,139,555 | +81% | +38% |
| 5 | Ragle Construction, Inc. | $2,205,165 | +87% | +42% |
| 6 | SCR Civil Construction, LLC | $2,216,814 | +88% | +43% |
| 7 | Hodges and Son Construction Company, Inc. | $2,243,050 | +90% | +44% |
Engineer's estimate: $1,552,814.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Taylor Bridge LLC | 2. Pathfield Investments LLC | 3. Structural Integrity Group LLC | 4. Built Right Construction of Oklahoma, LLC | 5. Ragle Construction, Inc. | 6. SCR Civil Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 12 | $3,226.10 | $1,750.00 | $2,000.00 | $2,000.00 | $250.00 | $1,500.00 | $3,600.00 |
| 2 | Preparation row (tree remove) (0"-12" diameter) (100-7003) | EACH | 55 | $200.00 | $250.00 | $200.00 | $400.00 | $200.00 | $700.00 | $500.00 |
| 3 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 7 | $400.00 | $500.00 | $500.00 | $1,000.00 | $750.00 | $1,110.00 | $550.00 |
| 4 | Removing concrete (riprap) (104-7007) | CY | 19.50 | $200.00 | $750.00 | $200.00 | $146.00 | $100.00 | $110.00 | $500.00 |
| 5 | Excavation (channel) (110-7002) | CY | 800 | $65.14 | $25.00 | $45.00 | $50.00 | $150.00 | $59.00 | $38.50 |
| 6 | Full - depth repair CRCP (15") (361-7010) | CY | 10 | $1,500.00 | $900.00 | $2,100.00 | $900.00 | $2,500.00 | $1,660.00 | $2,600.00 |
| 7 | Full-depth rep(BR appr slab)(9"-13") (361-7068) | SY | 8 | $650.00 | $500.00 | $2,300.00 | $325.00 | $250.00 | $946.00 | $1,700.00 |
| 8 | Flowable backfill (401-7001) | CY | 33 | $288.61 | $750.00 | $450.00 | $560.00 | $400.00 | $415.00 | $955.00 |
| 9 | Temporary special shoring (403-7001) | SF | 1,630 | $25.00 | $5.00 | $25.00 | $46.00 | $85.00 | $45.00 | $69.30 |
| 10 | Class C concrete (miscellaneous) (420-7067) | CY | 0.54 | $3,000.00 | $2,000.00 | $5,000.00 | $18,000 | $2,500.00 | $5,100.00 | $30,000 |
| 11 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 199 | $164.23 | $200.00 | $250.00 | $231.00 | $250.00 | $150.00 | $350.00 |
| 12 | Riprap (stone protection)(18 in) (432-7043) | CY | 497 | $197.67 | $200.00 | $180.00 | $130.00 | $250.00 | $210.00 | $181.50 |
| 13 | Riprap (stone protection)(24 in) (432-7045) | CY | 1,442 | $221.25 | $200.00 | $200.00 | $130.00 | $275.00 | $195.00 | $181.50 |
| 14 | Elastomeric bearing (laminated) (434-7002) | EACH | 4 | $1,500.00 | $500.00 | $10,000 | $2,500.00 | $5,000.00 | $1,500.00 | $1,000.00 |
| 15 | Cleaning and sealing existing joints (438-7001) | LF | 240 | $25.00 | $100.00 | $55.00 | $44.00 | $60.00 | $30.00 | $33.00 |
| 16 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 116 | $49.69 | $100.00 | $75.00 | $40.00 | $65.00 | $33.00 | $36.30 |
| 17 | Cleaning & sealing existing joint (SEJ) (438-7013) | LF | 360 | $67.17 | $100.00 | $50.00 | $42.00 | $120.00 | $33.00 | $36.30 |
| 18 | STR steel (pedestal) (442-7010) | LB | 1,445 | $40.00 | $9.00 | $15.00 | $24.60 | $65.00 | $26.50 | $36.50 |
| 19 | Rail (type T631) (450-7020) | LF | 124 | $50.00 | $90.00 | $200.00 | $394.00 | $160.00 | $117.00 | $420.00 |
| 20 | Wingwall (FW - S) (HW=6 FT) (466-7162) | EACH | 1 | $7,500.00 | $21,000 | $18,000 | $74,000 | $5,000.00 | $28,000 | $28,600 |
| 21 | Wingwall (FW - S) (HW=11 FT) (466-7167) | EACH | 1 | $6,500.00 | $20,000 | $22,000 | $100,000 | $8,000.00 | $41,000 | $63,800 |
| 22 | Wingwall (FW - S) (HW=12 FT) (466-7168) | EACH | 1 | $8,000.00 | $30,000 | $22,000 | $107,000 | $10,000 | $73,000 | $78,100 |
| 23 | Raising existing struct (495-7001) | LS | 2 | $50,000 | $15,000 | $20,000 | $4,630.00 | $85,750 | $250,000 | $31,000 |
| 24 | Removing structure (wingwall) (496-7005) | EACH | 3 | $1,165.48 | $1,000.00 | $5,000.00 | $2,725.00 | $1,500.00 | $1,500.00 | $2,750.00 |
| 25 | Remove STR (rail) (496-7017) | LF | 124 | $200.00 | $40.00 | $120.00 | $49.00 | $65.00 | $50.00 | $320.00 |
| 26 | Mobilization (500-7001) | LS | 1 | $169,821 | $25,000 | $130,000 | $157,500 | $230,000 | $220,000 | $345,000 |
| 27 | Barricades, signs and traffic handling (502-7001) | MO | 5 | $5,810.35 | $1.00 | $2,500.00 | $8,000.00 | $5,000.00 | $31,000 | $48,500 |
| 28 | Portable changeable message sign (503-7001) | DAY | 28 | $209.12 | $500.00 | $150.00 | $75.00 | $150.00 | $133.00 | $110.00 |
| 29 | TMA (stationary) (505-7001) | DAY | 70 | $195.84 | $250.00 | $10.00 | $1.00 | $300.00 | $346.00 | $350.00 |
| 30 | Temporary sediment control fence (install) (506-7039) | LF | 1,000 | $4.66 | $1.00 | $15.00 | $1.00 | $6.00 | $6.00 | $6.60 |
| 31 | Temporary sediment control fence (remove) (506-7041) | LF | 1,000 | $1.40 | $0.50 | $8.00 | $1.00 | $3.00 | $1.00 | $1.10 |
| 32 | Chain link fence (repair) (8') (550-7006) | LF | 18 | $135.00 | $100.00 | $250.00 | $90.00 | $75.00 | $45.00 | $200.00 |
| 33 | Wire fence (type C) (552-7003) | LF | 70 | $30.00 | $25.00 | $90.00 | $35.00 | $25.00 | $30.00 | $40.00 |
| 34 | Wire fence (remove) (552-7011) | LF | 108 | $2.25 | $2.00 | $30.00 | $10.00 | $5.00 | $5.00 | $10.00 |
| 35 | JT cleaning and sealing (expansion JTS) (713-7003) | LF | 20 | $50.00 | $150.00 | $400.00 | $38.00 | $55.00 | $50.00 | $55.00 |
| 36 | Driftwood removal (735-7060) | CY | 31 | $150.00 | $1,000.00 | $190.00 | $150.00 | $150.00 | $210.00 | $850.00 |
| 37 | Drain inlet cleaning (764-7001) | EACH | 1 | $69.60 | $1,000.00 | $3,000.00 | $5,700.00 | $1,500.00 | $1,000.00 | $2,500.00 |
| 38 | Steel structure repair (entire bridge) (784-7001) | LS | 1 | $150,000 | $25,000 | $40,000 | $30,000 | $150,000 | $50,000 | $33,500 |
| 39 | Rep steel bridge member (diaphragm) (784-7003) | EACH | 1 | $5,000.00 | $5,000.00 | $22,000 | $3,600.00 | $10,000 | $4,600.00 | $5,000.00 |
| 40 | Rep steel bridge MBR (weld repair) (784-7022) | EACH | 2 | $5,000.00 | $10,000 | $12,500 | $4,500.00 | $5,000.00 | $730.00 | $6,250.00 |
| 41 | Rep steel bridge member(repl rivet/bolt) (784-7024) | EACH | 8 | $4,000.00 | $1,500.00 | $1,250.00 | $3,500.00 | $350.00 | $300.00 | $1,600.00 |
| 42 | Replacing elastomeric bearing pads (787-7001) | EACH | 6 | $7,781.82 | $2,500.00 | $10,000 | $4,450.00 | $5,000.00 | $3,000.00 | $5,000.00 |
| 43 | Concrete beam repair (788-7001) | EACH | 4 | $5,500.00 | $3,500.00 | $2,600.00 | $5,800.00 | $15,000 | $3,000.00 | $3,500.00 |
| 44 | Steel bridge zone painting ref STR #1 (4010-7001) | EACH | 1 | $50,000 | $120,000 | $25,000 | $132,000 | $155,000 | $150,000 | $144,000 |
| 45 | Steel bridge zone painting ref STR #2 (4010-7003) | EACH | 1 | $50,000 | $32,000 | $25,000 | $35,200 | $42,000 | $65,000 | $38,400 |
| 46 | Steel bridge zone painting ref STR #3 (4010-7004) | EACH | 1 | $40,000 | $40,000 | $25,000 | $44,000 | $55,000 | $65,000 | $48,000 |
| 47 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 21 | $728.91 | $2,000.00 | $1,000.00 | $1,200.00 | $1,250.00 | $1,400.00 | $3,000.00 |
| 48 | Maintenance speed limit signing (7010-7002) | DAY | 40 | $250.00 | $100.00 | $10.00 | $100.00 | $15.00 | $200.00 | $100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.