TxDOT contract A00214045 bid tabulation
BRIDGE PREVENTATIVE MAINTENANCE, US0287 (Various Locations throughout to the WFAO and Gainesville AO). Let by Texas DOT on August 8, 2025, Wichita, Wichita Falls District. 9 bids received; low bid $1,492,330 by Built Right Construction of Oklahoma, LLC, +14% against the engineer's estimate of $1,305,072.
- Owner
- Texas DOT
- Letting
- 08 AUG 2025
- Pay items
- 40
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Built Right Construction of Oklahoma, LLC | $1,492,330 | Low | +14% |
| 2 | Scott Tucker Construction Company, LLC | $1,612,379 | +8.0% | +24% |
| 3 | Structural Integrity Group LLC | $1,628,897 | +9.0% | +25% |
| 4 | Premier Contractors LLC | $1,674,960 | +12% | +28% |
| 5 | Hodges and Son Construction Company, Inc. | $1,932,450 | +29% | +48% |
| 6 | Icos Management, LLC | $1,954,880 | +31% | +50% |
| 7 | Gibson & Associates, Inc. | $2,039,065 | +37% | +56% |
| 8 | O. Trevino Construction, LLC | $2,129,911 | +43% | +63% |
| 9 | Southern Road & Bridge, LLC | $2,343,605 | +57% | +80% |
Engineer's estimate: $1,305,072.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Built Right Construction of Oklahoma, LLC | 2. Scott Tucker Construction Company, LLC | 3. Structural Integrity Group LLC | 4. Premier Contractors LLC | 5. Hodges and Son Construction Company, Inc. | 6. Icos Management, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Embankment (final)(OC)(type B) (132-7003) | CY | 100 | $30.00 | $25.00 | $90.00 | $69.00 | $50.00 | $60.00 | $150.00 |
| 2 | Bulldozer work (156-7001) | HR | 8 | $165.00 | $150.00 | $439.00 | $147.00 | $300.00 | $30.00 | $250.00 |
| 3 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 800 | $20.00 | $32.00 | $34.00 | $41.00 | $150.00 | $30.00 | $15.00 |
| 4 | Flowable backfill (401-7001) | CY | 9 | $500.00 | $500.00 | $553.00 | $490.00 | $700.00 | $450.00 | $600.00 |
| 5 | Silicone resin paint finish (427-7004) | SF | 100 | $6.00 | $20.00 | $75.00 | $15.00 | $100.00 | $12.00 | $60.00 |
| 6 | Penetrating concrete surface treatment (428-7001) | SY | 855 | $25.00 | $18.00 | $13.00 | $15.00 | $20.00 | $5.00 | $32.00 |
| 7 | Concrete structure repair(deck rep(part depth)) (429-7003) | SF | 272 | $225.00 | $325.00 | $113.00 | $108.00 | $300.00 | $300.00 | $400.00 |
| 8 | Concrete structure repair(deck rep (full depth)) (429-7005) | SF | 10 | $250.00 | $325.00 | $505.00 | $162.00 | $700.00 | $800.00 | $900.00 |
| 9 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 1,054 | $200.00 | $210.00 | $186.00 | $200.00 | $400.00 | $250.00 | $200.00 |
| 10 | Riprap (stone protection)(12 in) (432-7041) | CY | 174 | $225.00 | $200.00 | $176.00 | $225.00 | $250.00 | $250.00 | $400.00 |
| 11 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 170 | $45.00 | $50.00 | $72.00 | $75.00 | $65.00 | $50.00 | $60.00 |
| 12 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 694 | $55.00 | $50.00 | $38.00 | $40.00 | $50.00 | $50.00 | $60.00 |
| 13 | Reinforced concrete overlay (3.5 in) (439-7011) | SY | 800 | $150.00 | $100.00 | $267.00 | $162.00 | $200.00 | $480.00 | $240.00 |
| 14 | Clean and paint existing STR (ref no. 9) (446-7028) | EACH | 1 | $50,000 | $205,000 | $111,674 | $184,200 | $100,000 | $60,000 | $160,000 |
| 15 | Hydro-demolition (2 1/2 in) (483-7011) | SY | 800 | $120.00 | $190.00 | $259.00 | $274.00 | $80.00 | $330.00 | $40.00 |
| 16 | Mobilization (500-7001) | LS | 1 | $115,007 | $100,000 | $161,284 | $99,500 | $80,000 | $175,000 | $180,000 |
| 17 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $10,000 | $24,000 | $20,998 | $17,450 | $1.00 | $25,000 | $8,000.00 |
| 18 | Portable changeable message sign (503-7001) | DAY | 66 | $110.00 | $150.00 | $144.00 | $65.00 | $1.00 | $100.00 | $100.00 |
| 19 | TMA (stationary) (505-7001) | DAY | 97 | $250.00 | $325.00 | $453.00 | $1.00 | $1.00 | $300.00 | $200.00 |
| 20 | Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013) | LF | 480 | $35.00 | $25.00 | $29.00 | $38.50 | $40.00 | $95.00 | $50.00 |
| 21 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 480 | $20.00 | $20.00 | $16.00 | $13.50 | $40.00 | $40.00 | $25.00 |
| 22 | Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037) | LF | 480 | $35.00 | $25.00 | $29.00 | $37.50 | $40.00 | $50.00 | $20.00 |
| 23 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 1 | $2,000.00 | $2,500.00 | $3,557.00 | $1,680.00 | $2,500.00 | $2,500.00 | $5,000.00 |
| 24 | Crash cushion attenuator (remove) (545-7004) | EACH | 1 | $1,000.00 | $2,000.00 | $895.00 | $1,375.00 | $1,000.00 | $2,000.00 | $5,000.00 |
| 25 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 1 | $10,000 | $12,000 | $11,647 | $7,000.00 | $5,000.00 | $18,000 | $12,000 |
| 26 | Work zone pavement marking removing (traffic BTN) type W (662-7057) | EACH | 1,860 | $5.00 | $7.00 | $4.00 | $3.00 | $5.00 | $5.00 | $2.00 |
| 27 | Work zone pavement marking removing (traffic BTN) type Y (662-7059) | EACH | 1,860 | $5.00 | $7.00 | $4.00 | $3.00 | $12.00 | $5.00 | $2.00 |
| 28 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 15 | $2.00 | $30.00 | $3.00 | $3.00 | $5.00 | $5.00 | $10.00 |
| 29 | Reflectorized pavement marking type I (W)4"(broken)(090MIL)(callout) (666-7141) | LF | 50 | $5.00 | $25.00 | $16.00 | $3.00 | $2.00 | $40.00 | $50.00 |
| 30 | Reflectorized pavement marking type I (W)4"(solid)(090MIL)(callout) (666-7142) | LF | 180 | $5.00 | $25.00 | $7.00 | $2.50 | $2.00 | $25.00 | $40.00 |
| 31 | Reflectorized pavement marking type I (Y)4"(solid)(090MIL)(callout) (666-7161) | LF | 180 | $5.00 | $25.00 | $7.00 | $2.50 | $2.00 | $25.00 | $40.00 |
| 32 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 3 | $5.00 | $65.00 | $6.00 | $6.00 | $2.00 | $500.00 | $150.00 |
| 33 | Driftwood removal (735-7060) | CY | 335 | $75.00 | $50.00 | $134.00 | $99.00 | $28.00 | $16.00 | $160.00 |
| 34 | Tree removal (4" - 12" diameter) (752-7005) | EACH | 2 | $300.00 | $300.00 | $1,775.00 | $3,000.00 | $1.00 | $2,000.00 | $800.00 |
| 35 | Bridge joint repair (concrete) (785-7001) | LF | 416 | $120.00 | $200.00 | $198.00 | $160.00 | $110.00 | $200.00 | $600.00 |
| 36 | Bridge joint replacement (concrete) (785-7009) | LF | 328 | $500.00 | $275.00 | $295.00 | $510.00 | $185.00 | $250.00 | $620.00 |
| 37 | Bridge joint replacement (header) (785-7013) | LF | 287 | $250.00 | $120.00 | $191.00 | $538.50 | $300.00 | $250.00 | $240.00 |
| 38 | Concrete beam repair (788-7001) | EACH | 7 | $5,000.00 | $5,000.00 | $5,344.00 | $3,500.00 | $20,000 | $3,200.00 | $18,000 |
| 39 | Remove lead-containing coating (other) (5011-7002) | LS | 1 | $20,000 | $27,000 | $24,073 | $21,400 | $40,000 | $20,000 | $15,000 |
| 40 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 3 | $1,000.00 | $500.00 | $1,022.00 | $800.00 | $10,000 | $1,000.00 | $1,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way