TxDOT contract A00214078 bid tabulation
Bridge Maintenance, SH 16 (Bridge Structure to Bridge Structure). Let by Texas DOT on October 9, 2025, Palo Pinto, Fort Worth District. 5 bids received; low bid $4,272,843 by Garret Shields Infrastructure, +3.2% against the engineer's estimate of $4,142,319.
- Owner
- Texas DOT
- Letting
- 09 OCT 2025
- Pay items
- 65
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Garret Shields Infrastructure | $4,272,843 | Low | +3.0% |
| 2 | Ragle Construction, Inc. | $4,539,238 | +6.0% | +10% |
| 3 | Southern Road & Bridge, LLC | $5,759,345 | +35% | +39% |
| 4 | Gibson & Associates, Inc. | $6,213,079 | +45% | +50% |
| 5 | Built Right Construction of Oklahoma, LLC | $7,211,509 | +69% | +74% |
Engineer's estimate: $4,142,319.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Garret Shields Infrastructure | 2. Ragle Construction, Inc. | 3. Southern Road & Bridge, LLC | 4. Gibson & Associates, Inc. | 5. Built Right Construction of Oklahoma, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 2 | $5,000.00 | $21,500 | $3,500.00 | $7,500.00 | $1,500.00 | |
| 2 | Removing concrete (riprap) (104-7006) | SY | 10 | $50.00 | $80.00 | $125.00 | $100.00 | $20.00 | |
| 3 | Embankment (final)(OC)(type B) (132-7003) | CY | 130 | $40.00 | $50.00 | $65.00 | $231.00 | $30.00 | |
| 4 | Compost manuf topsoil (4") (161-7002) | SY | 41 | $10.00 | $25.00 | $4.00 | $25.00 | $20.00 | |
| 5 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 41 | $10.00 | $10.00 | $4.00 | $15.00 | $3.00 | |
| 6 | Vegetative watering (168-7001) | TGL | 0.80 | $1,000.00 | $450.00 | $25,000 | $500.00 | $250.00 | |
| 7 | Soil ret BLKT(SL_steep_clay_short) (169-7005) | SY | 41 | $3.00 | $13.00 | $5.00 | $25.00 | $75.00 | |
| 8 | Flowable backfill (401-7001) | CY | 109 | $600.00 | $300.00 | $950.00 | $500.00 | $400.00 | |
| 9 | Temporary special shoring (403-7001) | SF | 1,540 | $50.00 | $60.00 | $48.00 | $82.50 | $95.00 | |
| 10 | Class C concrete (wingwalls) (420-7146) | CY | 28.70 | $2,500.00 | $1,600.00 | $3,850.00 | $3,960.00 | $1,500.00 | |
| 11 | Concrete structure repair(clean & coat WTH epoxy) (429-7001) | SF | 453 | $250.00 | $110.00 | $19.00 | $208.15 | $275.00 | |
| 12 | Concrete structure repair(deck rep(part depth)) (429-7003) | SF | 72 | $250.00 | $95.00 | $485.00 | $231.00 | $325.00 | |
| 13 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 2,101 | $280.00 | $200.00 | $110.00 | $500.00 | $224.25 | $250.00 |
| 14 | Concrete structure repair (standard) (429-7009) | SF | 72 | $150.00 | $110.00 | $485.00 | $113.85 | $250.00 | |
| 15 | Riprap (concrete)(4 in) (432-7001) | CY | 1.10 | $2,000.00 | $2,200.00 | $2,850.00 | $2,500.00 | $800.00 | |
| 16 | Riprap (stone protection)(24 in) (432-7045) | CY | 263 | $300.00 | $170.00 | $680.00 | $401.50 | $375.00 | |
| 17 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 996 | $60.00 | $50.00 | $18.00 | $95.00 | $17.25 | $65.00 |
| 18 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 3,929 | $50.00 | $23.00 | $95.00 | $33.35 | $65.00 | |
| 19 | Cleaning existing joints (438-7008) | LF | 215 | $50.00 | $23.00 | $35.00 | $20.70 | $50.00 | |
| 20 | Resizing and sealing joints (438-7009) | LF | 956 | $50.00 | $25.00 | $35.00 | $46.00 | $75.00 | |
| 21 | Clean and seal JNTS (pan girders) (CL3) (438-7011) | LF | 216 | $50.00 | $75.00 | $95.00 | $36.80 | $100.00 | |
| 22 | Clean and seal JNTS (pan girders) (CL7) (438-7012) | LF | 224 | $50.00 | $75.00 | $95.00 | $97.75 | $100.00 | |
| 23 | Multi-layer polymer overlay (439-7014) | SY | 1,739 | $60.00 | $75.00 | $80.00 | $95.00 | $99.00 | $62.00 |
| 24 | Clean and paint existing STR (ref no. 1) (446-7020) | EACH | 1 | $800,000 | $963,100 | $485,000 | $885,500 | $1,550,000 | |
| 25 | Clean and paint existing STR (ref no. 2) (446-7021) | EACH | 1 | $900,000 | $1,400,000 | $485,000 | $997,700 | $1,680,000 | |
| 26 | Header type expansion joint (454-7009) | CF | 109 | $500.00 | $225.00 | $1,195.00 | $1,100.00 | $750.00 | |
| 27 | Clean existing culverts (480-7001) | EACH | 1 | $5,000.00 | $2,300.00 | $2,500.00 | $5,500.00 | $25,000 | |
| 28 | Removing structure (wingwall) (496-7005) | EACH | 5 | $2,000.00 | $2,300.00 | $18,000 | $1,980.00 | $1,500.00 | |
| 29 | Mobilization (500-7001) | LS | 1 | $355,765 | $300,000 | $430,000 | $525,000 | $812,000 | $700,000 |
| 30 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $24,500 | $5,000.00 | $27,750 | $35,000 | $106,000 | $28,000 |
| 31 | Portable changeable message sign (503-7001) | DAY | 767 | $140.00 | $100.00 | $60.00 | $85.00 | $84.00 | $50.00 |
| 32 | TMA (stationary) (505-7001) | DAY | 297 | $410.00 | $300.00 | $240.00 | $200.00 | $360.00 | $300.00 |
| 33 | TMA (mobile operation) (505-7003) | DAY | 9 | $300.00 | $575.00 | $1,000.00 | $700.00 | $325.00 | |
| 34 | Rock filter dams (install) (type 3) (506-7003) | LF | 58 | $50.00 | $95.00 | $20.00 | $125.00 | $75.00 | |
| 35 | Rock filter dams (remove) (506-7011) | LF | 58 | $10.00 | $15.00 | $15.00 | $30.00 | $20.00 | |
| 36 | Temporary sediment control fence (install) (506-7039) | LF | 516 | $6.00 | $4.50 | $5.00 | $10.00 | $5.00 | |
| 37 | Temporary sediment control fence (remove) (506-7041) | LF | 516 | $1.00 | $1.00 | $2.00 | $5.00 | $3.00 | |
| 38 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 280 | $80.00 | $125.00 | $125.00 | $88.00 | $150.00 | |
| 39 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 280 | $20.00 | $15.00 | $68.00 | $50.00 | $50.00 | |
| 40 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $1,000.00 | $1,200.00 | $1,500.00 | $1,500.00 | $1,800.00 | |
| 41 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 2 | $10,000 | $7,600.00 | $9,500.00 | $9,800.00 | $12,000 | |
| 42 | Reflectorized pavement marking type II (W) 4" (solid) (666-7171) | LF | 868 | $1.00 | $2.70 | $2.00 | $3.00 | $5.50 | $2.20 |
| 43 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 33 | $40.00 | $2.50 | $4.00 | $5.50 | $3.00 | |
| 44 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 131 | $11.00 | $2.50 | $4.00 | $5.50 | $3.00 | |
| 45 | Reflectorized pavement marking type II (Y) 4" (solid) (666-7210) | LF | 868 | $1.00 | $2.75 | $2.00 | $4.00 | $5.50 | $2.20 |
| 46 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 131 | $11.50 | $2.50 | $3.00 | $5.50 | $3.00 | |
| 47 | Reflectorized pavement marking type II (BLK)(6")(shadow) (666-7229) | LF | 33 | $40.00 | $4.00 | $5.00 | $19.80 | $5.00 | |
| 48 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 11 | $10.00 | $120.00 | $10.00 | $15.00 | $38.50 | $12.00 |
| 49 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 2 | $630.00 | $10.00 | $15.00 | $38.50 | $12.00 | |
| 50 | JT cleaning and sealing(LNGT CNSTR JTS) (713-7002) | LF | 140 | $50.00 | $15.00 | $295.00 | $32.20 | $65.00 | |
| 51 | Driftwood removal (735-7060) | CY | 37 | $120.00 | $90.00 | $125.00 | $318.00 | $150.00 | |
| 52 | Spot tree trimming / brush removal (752-7002) | LF | 32 | $50.00 | $55.00 | $50.00 | $100.00 | $100.00 | |
| 53 | CNC crack repair (discrete)(inject) (780-7002) | LF | 276 | $50.00 | $65.00 | $225.00 | $103.50 | $125.00 | |
| 54 | Rep steel bridge MBR (anchor bolt nuts) (784-7021) | EACH | 14 | $1,700.00 | $150.00 | $450.00 | $50.00 | $400.00 | |
| 55 | Rep steel bridge MBR (cotter pin or bolt) (784-7023) | EACH | 1 | $10,000 | $6,350.00 | $3,500.00 | $1,000.00 | $500.00 | |
| 56 | Bridge joint replacement (concrete) (785-7009) | LF | 392 | $400.00 | $130.00 | $405.00 | $232.00 | $490.00 | |
| 57 | Bridge joint replacement (armor) (785-7010) | LF | 112 | $500.00 | $300.00 | $950.00 | $640.00 | $500.00 | |
| 58 | Replacing elastomeric bearing pads (787-7001) | EACH | 3 | $18,000 | $12,000 | $18,500 | $22,000 | $15,000 | |
| 59 | Concrete beam repair (CFRP) (788-7002) | EACH | 4 | $5,000.00 | $6,000.00 | $9,500.00 | $12,000 | $15,000 | |
| 60 | Tied-concrete block erosion control mat (2005-7001) | SF | 2,550 | $40.00 | $15.00 | $95.00 | $25.30 | $50.00 | |
| 61 | Steel bridge zone painting ref STR #1 (4010-7001) | EACH | 1 | $50,000 | $61,150 | $185,000 | $126,500 | $260,000 | |
| 62 | Steel bridge zone painting ref STR #2 (4010-7003) | EACH | 1 | $50,000 | $51,550 | $185,000 | $60,500 | $240,000 | |
| 63 | Install FTB (5002-7001) | LF | 175 | $60.00 | $50.00 | $70.00 | $65.00 | $60.00 | $30.00 |
| 64 | Remove FTB (5002-7002) | LF | 175 | $20.00 | $5.00 | $20.00 | $3.00 | $20.00 | $30.00 |
| 65 | Stone masonry repair (5013-7001) | SF | 636 | $170.00 | $45.00 | $70.00 | $78.00 | $200.00 | $75.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way