TxDOT contract A00214748 bid tabulation
Bridge Maintenance, Various (Districtwide to .). Let by Texas DOT on January 6, 2026, Ector, Odessa District. 12 bids received; low bid $498,387 by Premier Contractors LLC, -31% against the engineer's estimate of $727,300.
- Owner
- Texas DOT
- Letting
- 06 JAN 2026
- Pay items
- 16
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Premier Contractors LLC | $498,387 | Low | -31% |
| 2 | BK Field Operations LLC | $591,362 | +19% | -19% |
| 3 | MPB, Inc. | $630,895 | +27% | -13% |
| 4 | Relmco, Inc. | $719,890 | +44% | -1.0% |
| 5 | Pathfield Investments LLC | $723,778 | +45% | 0.0% |
| 6 | Beck-Reit & Sons, LTD. | $732,971 | +47% | +1.0% |
| 7 | Ragle Construction, Inc. | $781,040 | +57% | +7.0% |
| 8 | Ti-Zack Concrete, LLC | $784,600 | +57% | +8.0% |
| 9 | Blacksmith Ventures LLC | $866,950 | +74% | +19% |
| 10 | Grey Sky Construction LLC | $941,450 | +89% | +29% |
| 11 | SCR Civil Construction, LLC | $977,390 | +96% | +34% |
| 12 | Built Right Construction of Oklahoma, LLC | $1,115,600 | +124% | +53% |
Engineer's estimate: $727,300.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Premier Contractors LLC | 2. BK Field Operations LLC | 3. MPB, Inc. | 4. Relmco, Inc. | 5. Pathfield Investments LLC | 6. Beck-Reit & Sons, LTD. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Embankment (final)(OC)(type C) (132-7005) | CY | 59 | $100.00 | $100.00 | $250.00 | $150.00 | $110.00 | $110.00 | |
| 2 | Flexible pavement structure repair(2") (351-7001) | SY | 18 | $29.21 | $100.00 | $400.00 | $400.00 | $250.00 | $760.00 | $250.00 |
| 3 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 1,278 | $150.00 | $200.00 | $100.00 | $100.00 | $165.00 | $200.00 | $150.00 |
| 4 | Concrete structure repair (standard) (429-7009) | SF | 27 | $150.00 | $200.00 | $200.00 | $85.00 | $190.00 | $240.00 | $180.00 |
| 5 | Cleaning and sealing existing joints (438-7001) | LF | 365 | $35.00 | $45.00 | $55.00 | $37.00 | $55.00 | $25.00 | $65.00 |
| 6 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 170 | $44.95 | $45.00 | $60.00 | $106.00 | $72.00 | $65.00 | $55.00 |
| 7 | Gabion mattresses (galvanized) (24 in) (459-7009) | SY | 95 | $250.00 | $225.00 | $400.00 | $225.00 | $260.00 | $310.00 | |
| 8 | Gabions (PVC)( 3FT X 3 FT) (459-7011) | CY | 75 | $250.00 | $400.00 | $500.00 | $350.00 | $300.00 | $500.00 | |
| 9 | Clean existing culverts (480-7001) | EACH | 13 | $3,000.00 | $650.00 | $5,000.00 | $5,225.00 | $4,500.00 | $1,500.00 | $9,500.00 |
| 10 | Mobilization (500-7001) | LS | 1 | $61,015 | $50,000 | $55,000 | $57,000 | $60,000 | $70,000 | $85,000 |
| 11 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $15,000 | $1.00 | $1.00 | $750.00 | $5,000.00 | $1,000.00 | $1,200.00 |
| 12 | Portable changeable message sign (503-7001) | DAY | 140 | $130.00 | $1.00 | $1.00 | $50.00 | $200.00 | $1.00 | $11.00 |
| 13 | TMA (stationary) (505-7001) | DAY | 263 | $200.00 | $1.00 | $1.00 | $100.00 | $200.00 | $1.00 | $11.00 |
| 14 | Concrete rail repair (miscellaneous) (778-7002) | LF | 105 | $95.97 | $150.00 | $500.00 | $295.00 | $500.00 | $280.00 | $300.00 |
| 15 | CNC crack repair (discrete)(inject) (780-7002) | LF | 75 | $50.00 | $60.00 | $140.00 | $105.00 | $80.00 | $78.00 | $65.00 |
| 16 | Replacing elastomeric bearing pads (787-7001) | EACH | 24 | $6,000.00 | $3,500.00 | $7,500.00 | $7,000.00 | $4,500.00 | $10,000 | $6,887.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 6, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.