| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Aad Contracting Inc. | $461,459 | Low | +2.0% |
| 2 | Highway 19 Construction LLC | $512,778 | +11% | +14% |
| 3 | Ed Bell Construction Company | $578,945 | +25% | +28% |
| 4 | Garret Shields Infrastructure | $582,647 | +26% | +29% |
Engineer's estimate: $451,670.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Aad Contracting Inc. | 2. Highway 19 Construction LLC | 3. Ed Bell Construction Company | 4. Garret Shields Infrastructure |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 1 | $3,500.00 | $1,500.00 | $5,000.00 | $31,000 | $5,000.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 226 | $30.00 | $19.00 | $25.00 | $5.00 | $50.00 |
| 3 | Embankment (final)(DC)(type C) (132-7006) | CY | 240 | $20.00 | $70.00 | $50.00 | $40.00 | $50.00 |
| 4 | Block sodding (162-7002) | SY | 435 | $7.75 | $8.00 | $10.00 | $15.00 | $10.00 |
| 5 | Vegetative watering (168-7001) | TGL | 65 | $1.00 | $10.00 | $50.00 | $10.00 | $50.00 |
| 6 | Cut & restoring pavement (400-7006) | SY | 176 | $245.00 | $150.00 | $350.00 | $200.00 | $250.00 |
| 7 | Cem stabil BKFL (400-7010) | CY | 210 | $207.00 | $250.00 | $350.00 | $350.00 | $300.00 |
| 8 | Flowable backfill (401-7001) | CY | 134 | $366.00 | $250.00 | $350.00 | $350.00 | $400.00 |
| 9 | Trench excavation protection (402-7001) | LF | 41 | $18.00 | $30.00 | $5.00 | $75.00 | $15.00 |
| 10 | Temporary special shoring (403-7001) | SF | 2,606 | $6.01 | $15.00 | $22.00 | $1.00 | $40.00 |
| 11 | Riprap (concrete)(4 in) (432-7001) | CY | 13 | $588.00 | $600.00 | $750.00 | $800.00 | $600.00 |
| 12 | Riprap (stone protection)(12 in) (432-7041) | CY | 24 | $225.00 | $180.00 | $180.00 | $300.00 | $300.00 |
| 13 | Riprap (stone protection)(18 in) (432-7043) | CY | 74 | $225.00 | $220.00 | $180.00 | $300.00 | $300.00 |
| 14 | RC pipe (CL III)(48 in) (464-7011) | LF | 345 | $310.00 | $275.00 | $253.00 | $350.00 | $280.00 |
| 15 | Headwall (CH - FW - 45) (diameter= 48 in) (466-7056) | EACH | 2 | $25,000 | $25,000 | $12,000 | $25,000 | $20,000 |
| 16 | Removing structure (headwall) (496-7006) | EACH | 2 | $2,000.00 | $2,000.00 | $1,000.00 | $5,000.00 | $2,000.00 |
| 17 | Removing structure (pipe) (496-7007) | LF | 468 | $50.00 | $50.00 | $50.00 | $35.00 | $20.00 |
| 18 | Mobilization (500-7001) | LS | 1 | $37,294 | $50,000 | $50,000 | $57,500 | $50,000 |
| 19 | Barricades, signs and traffic handling (502-7001) | MO | 1 | $2,000.00 | $7,000.00 | $5,000.00 | $42,000 | $20,000 |
| 20 | Portable changeable message sign (503-7001) | DAY | 14 | $200.00 | $350.00 | $100.00 | $75.00 | $100.00 |
| 21 | TMA (stationary) (505-7001) | DAY | 14 | $400.00 | $350.00 | $500.00 | $100.00 | $300.00 |
| 22 | Rock filter dams (install) (type 2) (506-7002) | LF | 75 | $53.00 | $20.00 | $45.00 | $88.00 | $30.00 |
| 23 | Rock filter dams (install) (type 3) (506-7003) | LF | 25 | $65.90 | $25.00 | $80.00 | $100.00 | $30.00 |
| 24 | Rock filter dams (remove) (506-7011) | LF | 100 | $24.67 | $1.00 | $10.00 | $50.00 | $10.00 |
| 25 | Temporary sediment control fence (install) (506-7039) | LF | 206 | $8.02 | $4.00 | $5.00 | $6.00 | $6.00 |
| 26 | Temporary sediment control fence (remove) (506-7041) | LF | 206 | $3.24 | $1.00 | $1.00 | $3.00 | $1.00 |
| 27 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 10 | $5.94 | $4.50 | $10.00 | $10.00 | $6.00 |
| 28 | Biodegradable erosion control logs (remove) (506-7046) | LF | 10 | $1.35 | $1.00 | $1.00 | $5.00 | $1.00 |
| 29 | Driveways (ACP) (530-7010) | SY | 95 | $80.00 | $110.00 | $75.00 | $125.00 | $120.00 |
| 30 | Relocate existing mailbox (560-7012) | EACH | 1 | $350.00 | $300.00 | $250.00 | $500.00 | $500.00 |
| 31 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 1 | $850.00 | $300.00 | $350.00 | $800.00 | $1,000.00 |
| 32 | Install object marker assembly (OM-2Z)(WFLX)GNDLL (658-7248) | EACH | 2 | $50.00 | $90.00 | $35.00 | $300.00 | $60.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 15, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.