TxDOT contract A00216828 bid tabulation
Bridge Maintenance, Various (Various Bridge Locations: Bastrop to Bastrop County). Let by Texas DOT on March 5, 2026, Travis, Austin District. 13 bids received; low bid $327,386 by Taylor Bridge LLC, -37% against the engineer's estimate of $518,718.
- Owner
- Texas DOT
- Letting
- 05 MAR 2026
- Pay items
- 30
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Taylor Bridge LLC | $327,386 | Low | -37% |
| 2 | BK Field Operations LLC | $343,231 | +5.0% | -34% |
| 3 | Beck-Reit & Sons, LTD. | $361,165 | +10% | -30% |
| 4 | Roy Jorgensen Associates, Inc. | $390,327 | +19% | -25% |
| 5 | Icos Management, LLC | $425,689 | +30% | -18% |
| 6 | Garret Shields Infrastructure | $434,180 | +33% | -16% |
| 7 | Blacksmith Ventures LLC | $443,365 | +35% | -15% |
| 8 | Road Doctors LLC | $444,300 | +36% | -14% |
| 9 | Restek, Inc. | $593,415 | +81% | +14% |
| 10 | MPB, Inc. | $603,865 | +84% | +16% |
| 11 | SCR Civil Construction, LLC | $692,470 | +112% | +33% |
| 12 | Premier Contractors LLC | $807,350 | +147% | +56% |
| 13 | Built Right Construction of Oklahoma, LLC | $1,170,745 | +258% | +126% |
Engineer's estimate: $518,718.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Taylor Bridge LLC | 2. BK Field Operations LLC | 3. Beck-Reit & Sons, LTD. | 4. Roy Jorgensen Associates, Inc. | 5. Icos Management, LLC | 6. Garret Shields Infrastructure |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 6 | $1,000.00 | $500.00 | $300.00 | $100.00 | $1.00 | $535.00 | $1,000.00 |
| 2 | Preparation row (tree remove) (24"-36" diameter) (100-7005) | EACH | 6 | $1,200.00 | $750.00 | $850.00 | $150.00 | $1.00 | $1,070.00 | $2,000.00 |
| 3 | Flexible pavement structure repair(4") (351-7003) | SY | 45 | $460.50 | $200.00 | $240.00 | $350.00 | $250.00 | $856.00 | $40.00 |
| 4 | Flowable backfill (401-7001) | CY | 8 | $550.00 | $1,000.00 | $800.00 | $950.00 | $500.00 | $856.00 | $300.00 |
| 5 | Concrete structure repair(deck rep (full depth)) (429-7005) | SF | 25 | $450.00 | $400.00 | $450.00 | $650.00 | $250.00 | $642.00 | $300.00 |
| 6 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 193 | $240.00 | $150.00 | $120.00 | $125.00 | $100.00 | $214.00 | $200.00 |
| 7 | Riprap (concrete)(4 in) (432-7001) | CY | 3 | $460.00 | $1,000.00 | $1,000.00 | $1,100.00 | $700.00 | $856.00 | $600.00 |
| 8 | Riprap (stone common)(dry)(6 in) (432-7029) | CY | 3 | $250.00 | $1,000.00 | $600.00 | $1,300.00 | $300.00 | $428.00 | $200.00 |
| 9 | Riprap (stone protection)(18 in) (432-7043) | CY | 46 | $220.00 | $300.00 | $190.00 | $160.00 | $300.00 | $214.00 | $300.00 |
| 10 | Riprap (stone protection)(24 in) (432-7045) | CY | 437 | $220.00 | $190.00 | $190.00 | $160.00 | $200.00 | $193.00 | $250.00 |
| 11 | Cleaning and sealing existing joints (438-7001) | LF | 429 | $110.00 | $50.00 | $55.00 | $65.00 | $35.00 | $64.00 | $40.00 |
| 12 | Gabions (galvanized) (459-7001) | CY | 40 | $500.00 | $450.00 | $500.00 | $300.00 | $500.00 | $321.00 | $300.00 |
| 13 | Gabion mattresses (galvanized)(18 in) (459-7008) | SY | 80 | $185.00 | $195.00 | $350.00 | $275.00 | $250.00 | $257.00 | $300.00 |
| 14 | Set (replace pipe runner) (467-7004) | EACH | 13 | $1,500.00 | $1,000.00 | $1,000.00 | $1,300.00 | $1,000.00 | $1,605.00 | $1,000.00 |
| 15 | Clean existing culverts (480-7002) | CY | 75 | $75.00 | $250.00 | $120.00 | $85.00 | $250.00 | $214.00 | $150.00 |
| 16 | Mobilization (500-7001) | LS | 1 | $60,000 | $30,000 | $40,000 | $59,000 | $65,000 | $52,400 | $60,000 |
| 17 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $5,500.00 | $1.00 | $1.00 | $2,000.00 | $1,500.00 | $1.00 | $5,000.00 |
| 18 | Portable changeable message sign (503-7001) | DAY | 200 | $100.00 | $1.00 | $1.00 | $1.00 | $100.00 | $1.00 | $10.00 |
| 19 | TMA (stationary) (505-7001) | DAY | 100 | $100.00 | $1.00 | $1.00 | $1.00 | $250.00 | $1.00 | $300.00 |
| 20 | TMA (mobile operation) (505-7003) | DAY | 100 | $100.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $200.00 |
| 21 | Sandbags for erosion control (506-7035) | EACH | 100 | $10.00 | $10.00 | $15.00 | $1.00 | $1.00 | $11.00 | $2.00 |
| 22 | Pipe underdrains (type 1) (6") (556-7001) | LF | 10 | $150.00 | $50.00 | $250.00 | $150.00 | $45.00 | $214.00 | $50.00 |
| 23 | Pothole repair(standard)(0"-5" deep) (700-7001) | SY | 15 | $320.00 | $150.00 | $200.00 | $100.00 | $100.00 | $321.00 | $100.00 |
| 24 | Litter removal (734-7002) | CYC | 3 | $300.00 | $50.00 | $1,200.00 | $450.00 | $100.00 | $642.00 | $1,000.00 |
| 25 | Driftwood removal (735-7060) | CY | 40 | $200.00 | $250.00 | $120.00 | $80.00 | $80.00 | $214.00 | $120.00 |
| 26 | Realign posts (770-7010) | EACH | 2 | $100.00 | $1,000.00 | $500.00 | $2,500.00 | $200.00 | $642.00 | $10.00 |
| 27 | Repair (steel rail) (776-7001) | LF | 25 | $330.00 | $200.00 | $350.00 | $650.00 | $80.00 | $321.00 | $100.00 |
| 28 | CNC crack repair (flood)(gravity) (780-7005) | SF | 100 | $15.00 | $50.00 | $100.00 | $60.00 | $100.00 | $128.00 | $10.00 |
| 29 | Bridge joint repair (header) (785-7002) | LF | 5 | $634.00 | $2,100.00 | $800.00 | $500.00 | $300.00 | $535.00 | $500.00 |
| 30 | Concrete beam repair (788-7001) | EACH | 5 | $9,000.00 | $1,500.00 | $3,000.00 | $3,500.00 | $4,000.00 | $4,280.00 | $1,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 5, 2026. Compiled by Mirage Metrics.