TxDOT contract A00217764 bid tabulation
Landscape Development, Various (Various locations Bastrop County to SL 109; SH 21; US 290; FM 1704). Let by Texas DOT on August 6, 2026, Bastrop, Austin District. 8 bids received; low bid $224,027 by Apex Landscape & Irrigation, LLC, -37% against the engineer's estimate of $355,992.
- Owner
- Texas DOT
- Letting
- 06 AUG 2026
- Pay items
- 24
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Apex Landscape & Irrigation, LLC | $224,027 | Low | -37% |
| 2 | Tight Line Construction, LLC | $288,954 | +29% | -19% |
| 3 | Rare Earth Landscape Solutions LLC | $300,791 | +34% | -16% |
| 4 | Green Sage Services LLC | $309,324 | +38% | -13% |
| 5 | Texas Road Construction, LLC | $336,390 | +50% | -6.0% |
| 6 | Shalom Services Corporation | $608,790 | +172% | +71% |
| 7 | Central North Construction, LLC | $645,244 | +188% | +81% |
| 8 | Ratliff Hardscape, LTD. | $707,068 | +216% | +99% |
Engineer's estimate: $355,992.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Apex Landscape & Irrigation, LLC | 2. Tight Line Construction, LLC | 3. Rare Earth Landscape Solutions LLC | 4. Green Sage Services LLC | 5. Texas Road Construction, LLC | 6. Shalom Services Corporation |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Remove (14"-18") TRT/untrt base & asphalt pavement (105-7014) | SY | 336 | $18.00 | $16.00 | $30.00 | $25.75 | $75.00 | $25.00 | $15.00 |
| 2 | Embankment (vehicle)(OC)(type C) (132-7017) | CY | 5 | $31.00 | $160.00 | $100.00 | $0.10 | $90.00 | $100.00 | $65.00 |
| 3 | Furn & place topsoil (12") (160-7006) | SY | 781 | $35.00 | $8.50 | $17.00 | $19.40 | $12.00 | $50.00 | $65.00 |
| 4 | General use compost (vehicle) (161-7010) | CY | 78 | $40.00 | $47.50 | $70.00 | $92.75 | $45.00 | $80.00 | $30.00 |
| 5 | Vegetative watering (168-7001) | TGL | 2 | $10.00 | $6.00 | $100.00 | $0.10 | $200.00 | $1.00 | $70.00 |
| 6 | Irrigation system (loc A) (170-7008) | EACH | 1 | $40,000 | $6,400.00 | $25,000 | $24,000 | $15,500 | $30,000 | $100,000 |
| 7 | Irrigation system (loc B) (170-7009) | EACH | 1 | $22,000 | $10,600 | $15,000 | $24,000 | $19,000 | $35,000 | $150,000 |
| 8 | Wildflower seeding (180-7001) | ACRE | 18.89 | $1,030.00 | $1,760.00 | $1,100.00 | $566.00 | $1,820.00 | $1,000.00 | $1,250.00 |
| 9 | Mulch (192-7001) | CY | 66 | $56.00 | $20.00 | $65.00 | $75.20 | $50.00 | $50.00 | $100.00 |
| 10 | Plant bed preparation (192-7009) | SY | 781 | $6.00 | $4.00 | $6.00 | $31.67 | $6.00 | $5.00 | $50.00 |
| 11 | Plant material (1 gal) (192-7026) | EACH | 7,255 | $8.00 | $9.00 | $10.00 | $9.85 | $8.30 | $9.00 | $7.00 |
| 12 | Plant material (15 gal) (tree) (192-7037) | EACH | 2 | $174.00 | $180.00 | $250.00 | $342.60 | $200.00 | $300.00 | $1,000.00 |
| 13 | Plant material (100 gal) (tree) (192-7042) | EACH | 1 | $1,000.00 | $1,600.00 | $2,000.00 | $2,320.75 | $1,150.00 | $1,000.00 | $10,000 |
| 14 | Plant material (5 gal) (shrub) (192-7047) | EACH | 36 | $27.00 | $30.00 | $40.00 | $42.30 | $32.00 | $50.00 | $55.00 |
| 15 | Landscape establish (193-7001) | MO | 24 | $2,500.00 | $1,000.00 | $1,500.00 | $1,500.00 | $1,900.00 | $1,500.00 | $3,000.00 |
| 16 | Irrig sys oper and maintenance (193-7007) | MO | 24 | $2,250.00 | $1,000.00 | $1,000.00 | $850.00 | $1,000.00 | $1,000.00 | $2,500.00 |
| 17 | Riprap (stone common)(dry)(12 in) (432-7031) | CY | 6 | $170.00 | $250.00 | $250.00 | $369.00 | $350.00 | $1,500.00 | $1,000.00 |
| 18 | Bedding material (6 in) (432-7050) | CY | 4 | $230.00 | $45.00 | $200.00 | $356.00 | $355.00 | $1,000.00 | $200.00 |
| 19 | Mobilization (500-7001) | LS | 1 | $37,987 | $22,555 | $30,000 | $37,500 | $35,000 | $30,000 | $25,000 |
| 20 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $1,500.00 | $3,000.00 | $3,000.00 | $1,900.00 | $3,750.00 | $3,500.00 | $1.00 |
| 21 | Temporary sediment control fence (install) (506-7039) | LF | 356 | $4.06 | $0.10 | $1.00 | $0.10 | $2.50 | $5.00 | $1.00 |
| 22 | Temporary sediment control fence (remove) (506-7041) | LF | 356 | $1.07 | $0.10 | $1.00 | $0.10 | $1.30 | $1.00 | $1.00 |
| 23 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 818 | $8.00 | $0.10 | $8.00 | $0.10 | $6.50 | $3.00 | $1.00 |
| 24 | Biodegradable erosion control logs (remove) (506-7046) | LF | 818 | $1.00 | $0.10 | $2.00 | $0.10 | $1.00 | $1.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 6, 2026. Compiled by Mirage Metrics.