TxDOT contract A00217911 bid tabulation
Bridge Maintenance, US 80 (at Big Brushy Creek to .). Let by Texas DOT on August 5, 2026, Kaufman, Dallas District. 10 bids received; low bid $799,617 by Shalom Services Corporation, -38% against the engineer's estimate of $1,290,273.
- Owner
- Texas DOT
- Letting
- 05 AUG 2026
- Pay items
- 29
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shalom Services Corporation | $799,617 | Low | -38% |
| 2 | Jackson Excavation, LLC | $833,943 | +4.0% | -35% |
| 3 | Garret Shields Infrastructure | $1,032,635 | +29% | -20% |
| 4 | Icos Management, LLC | $1,075,320 | +34% | -17% |
| 5 | Texas Steel Industrial Placing, LLC | $1,115,555 | +40% | -14% |
| 6 | Tucan Contracting, LLC | $1,152,052 | +44% | -11% |
| 7 | Highway 19 Construction LLC | $1,178,670 | +47% | -9.0% |
| 8 | Road Doctors LLC | $1,278,224 | +60% | -1.0% |
| 9 | Pmco Construction LLC | $1,287,749 | +61% | 0.0% |
| 10 | Scout 5 Construction LLC | $1,795,936 | +125% | +39% |
Engineer's estimate: $1,290,273.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Shalom Services Corporation | 2. Jackson Excavation, LLC | 3. Garret Shields Infrastructure | 4. Icos Management, LLC | 5. Texas Steel Industrial Placing, LLC | 6. Tucan Contracting, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 3.11 | $5,000.00 | $1,500.00 | $1,000.00 | $5,000.00 | $2,100.00 | $1,000.00 | $3,300.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 380 | $12.00 | $22.00 | $10.00 | $30.00 | $32.50 | $30.00 | $220.00 |
| 3 | Excavation (channel) (110-7002) | CY | 4,695 | $18.00 | $8.00 | $10.00 | $25.00 | $23.10 | $16.00 | $16.50 |
| 4 | Embankment (final)(OC)(type C2) (132-7009) | CY | 9 | $20.00 | $20.00 | $50.00 | $40.00 | $420.00 | $115.00 | $27.50 |
| 5 | Block sodding (162-7002) | SY | 1,174 | $5.00 | $3.00 | $2.00 | $10.00 | $10.50 | $4.65 | $5.50 |
| 6 | Vegetative watering (168-7001) | TGL | 174 | $10.00 | $1.00 | $100.00 | $20.00 | $10.50 | $50.00 | $22.00 |
| 7 | Flowable backfill (401-7001) | CY | 12 | $400.00 | $400.00 | $400.00 | $300.00 | $472.50 | $200.00 | $275.00 |
| 8 | Riprap (mow strip)(4 in) (432-7013) | CY | 28 | $500.00 | $600.00 | $600.00 | $600.00 | $840.00 | $600.00 | $660.00 |
| 9 | Riprap (stone protection)(18 in) (432-7043) | CY | 3,995 | $182.00 | $142.00 | $155.00 | $150.00 | $141.75 | $145.00 | $165.00 |
| 10 | Gabion mattresses (galvanized) (24 in) (459-7009) | SY | 68 | $135.00 | $250.00 | $220.00 | $300.00 | $441.00 | $400.00 | $330.00 |
| 11 | Gabions (3' X 3')(galvanized) (459-7010) | CY | 160 | $425.00 | $400.00 | $240.00 | $300.00 | $472.50 | $400.00 | $550.00 |
| 12 | Removing rock riprap (496-7055) | CY | 620 | $225.00 | $35.00 | $20.00 | $40.00 | $84.00 | $123.00 | $44.00 |
| 13 | Mobilization (500-7001) | LS | 1 | $117,298 | $30,000 | $1,000.00 | $100,000 | $125,000 | $110,000 | $55,000 |
| 14 | Barricades, signs and traffic handling (502-7001) | MO | 3 | $10,000 | $1,500.00 | $2,500.00 | $5,000.00 | $1.10 | $2,500.00 | $3,300.00 |
| 15 | Portable changeable message sign (503-7002) | EACH | 2 | $8,000.00 | $1,000.00 | $10.00 | $1,000.00 | $4,200.00 | $30,000 | $11,000 |
| 16 | TMA (stationary) (505-7001) | DAY | 6 | $240.00 | $1.00 | $1,000.00 | $300.00 | $420.00 | $1,000.00 | $246.62 |
| 17 | Rock filter dams (install) (type 3) (506-7003) | LF | 220 | $50.00 | $1.00 | $6.00 | $20.00 | $21.00 | $85.00 | $66.00 |
| 18 | Rock filter dams (remove) (506-7011) | LF | 220 | $10.00 | $1.00 | $1.00 | $10.00 | $10.50 | $12.00 | $15.40 |
| 19 | Construction exits (install) (type 1) (506-7020) | SY | 440 | $35.00 | $1.00 | $10.00 | $20.00 | $10.50 | $35.00 | $41.80 |
| 20 | Construction exits (remove) (506-7024) | SY | 440 | $10.00 | $1.00 | $10.00 | $10.00 | $5.25 | $9.00 | $13.20 |
| 21 | Temporary sediment control fence (install) (506-7039) | LF | 550 | $4.00 | $1.00 | $1.00 | $5.00 | $2.10 | $3.55 | $4.95 |
| 22 | Temporary sediment control fence (remove) (506-7041) | LF | 550 | $1.00 | $1.00 | $1.00 | $1.00 | $1.10 | $1.10 | $0.98 |
| 23 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 220 | $5.00 | $1.00 | $3.00 | $5.00 | $10.50 | $5.85 | $7.70 |
| 24 | Biodegradable erosion control logs (remove) (506-7046) | LF | 220 | $1.00 | $1.00 | $2.00 | $1.00 | $5.25 | $1.25 | $2.20 |
| 25 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,000.00 | $3,000.00 | $6,000.00 | $3,500.00 | $3,990.00 | $3,669.00 | $3,520.00 |
| 26 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $300.00 | $500.00 | $500.00 | $500.00 | $525.00 | $275.00 | $330.00 |
| 27 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 4 | $40.00 | $25.00 | $30.00 | $20.00 | $52.50 | $20.00 | $22.00 |
| 28 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (BI) (658-7016) | EACH | 4 | $25.00 | $25.00 | $30.00 | $20.00 | $52.50 | $30.00 | $22.00 |
| 29 | Debris removal (spot debris) (735-7072) | MI | 0.05 | $500.00 | $1.00 | $4.00 | $10,000 | $68,250 | $10,000 | $220.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 5, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.