Conc. found. SSP-VA, 1'9" dia. X 4'6" deep, VDOT 700SD20-0046
Low bidders on VDOT contracts carried a median of $4,477.45 per EACH for this item, over the 24 months to 28 OCT 2026, across 3 low bids. Half of all 7 bids fell between $3,732.72 and $5,549.79.
- Owner
- Virginia DOT
- Item
- 700SD20-0046
- Unit
- EACH
- Data through
- 28 OCT 2026
VDOT prints this item as “CONC. FOUND. SSP-VA, 1'9" DIA. X 4'6" DEEP”.
VDOT has bid this work under more than one code: 50502 on lettings from 29 JAN 2002 to 27 OCT 2021 (265 bids); 700SD20-0046 on lettings from 22 OCT 2025 to 22 JUL 2026 (7 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 4 | 4 | $400.00 | 12 | $420.00 |
| 2003 | 5 | 5 | $400.00 | 13 | $430.00 |
| 2004 | 3 | 3 | $790.00 | 8 | $815.00 |
| 2005 | 2 | 2 | $409.82 | 6 | $487.50 |
| 2006 | 2 | 2 | $1,288.00 | 4 | $921.00 |
| 2007 | 6 | 6 | $1,075.00 | 11 | $1,085.00 |
| 2008 | 4 | 4 | $1,189.04 | 12 | $1,247.50 |
| 2009 | 1 | 1 | $270.00 | 3 | $401.00 |
| 2010 | 10 | 10 | $425.00 | 30 | $550.00 |
| 2011 | 14 | 14 | $549.00 | 41 | $600.00 |
| 2012 | 10 | 8 | $587.50 | 26 | $570.26 |
| 2013 | 10 | 10 | $822.38 | 25 | $700.00 |
| 2014 | 4 | 3 | $2,150.00 | 9 | $850.00 |
| 2015 | 7 | 7 | $1,140.55 | 18 | $1,149.07 |
| 2016 | 4 | 4 | $1,451.60 | 8 | $1,417.92 |
| 2017 | 3 | 3 | $1,948.16 | 9 | $1,500.00 |
| 2018 | 3 | 3 | $1,050.00 | 9 | $1,200.00 |
| 2019 | 2 | 2 | $1,960.14 | 6 | $1,418.55 |
| 2020 | 1 | 1 | $1,467.30 | 3 | $1,467.30 |
| 2021 | 2 | 2 | $1,940.00 | 6 | $1,458.97 |
| 2025 | 2 | 2 | $4,988.73 | 3 | $5,500.00 |
| 2026 | 1 | 1 | $2,475.53 | 4 | $4,047.13 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Hampton Roads | 20 | $653.00 | 57 | $659.00 |
| Salem | 22 | $923.50 | 53 | $935.00 |
| Northern Virginia | 15 | $525.00 | 45 | $600.00 |
| Fredericksburg | 13 | $434.00 | 38 | $542.50 |
| Culpeper | 9 | $1,100.00 | 23 | $830.00 |
| Staunton | 6 | $2,049.08 | 17 | $1,472.68 |
| Bristol | 7 | $1,157.58 | 17 | $1,157.58 |
| Richmond | 5 | $530.00 | 16 | $545.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 24 | $1,132.79 |
| 2 to 5 | 24 | $604.50 |
| 5 to 20 | 24 | $823.38 |
| 20 to 156 | 25 | $637.32 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Richardson-Wayland Electrical Co. LLC | 20 | 6 (30%) |
| Midasco Va LLC (Use N Va By: Midasco, LLC) | 14 | 6 (43%) |
| Branch Highways, Inc. | 6 | 5 (83%) |
| McClain & Co., Inc. | 17 | 4 (24%) |
| W-L Construction & Paving, Inc. | 5 | 3 (60%) |
| The Brothers Signal Company | 5 | 3 (60%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 JUL 2026 | C0000122147C01C | Richmond | 1 | $2,475.53 | $4,047.13 | 4 | Richardson-Wayland-Ferreira, LLC | VDOT |
| 19 NOV 2025 | C0000127310N01 | Staunton | 2 | $4,477.45 | $7,863.73 | 2 | Richardson-Wayland-Ferreira, LLC | VDOT |
| 22 OCT 2025 | C000117033M01D | Hampton Roads | 5 | $5,500.00 | $5,500.00 | 1 | Joseph B. Fay Co. | VDOT |
| 27 OCT 2021 | C0000119130C01 | Staunton | 1 | $2,900.00 | $2,900.00 | 3 | B & B Signal Co., L.L.C. | VDOT |
| 23 JUN 2021 | C0000118551N01 | Hampton Roads | 1 | $980.00 | $1,347.00 | 3 | Ces Consulting, LLC | VDOT |
| 26 AUG 2020 | C0000112923P01 | Hampton Roads | 1 | $1,467.30 | $1,467.30 | 3 | Aldridge Electric, Inc. | VDOT |
| 21 AUG 2019 | C00114881N01 | Hampton Roads | 1 | $1,500.00 | $1,337.09 | 3 | Curtis Contracting, Inc. | VDOT |
| 26 JUN 2019 | C0000108897N01 | Salem | 1 | $2,420.28 | $2,420.28 | 3 | Haymes Brothers, Inc. | VDOT |
| 19 DEC 2018 | C0000112897C01 | Hampton Roads | 6 | $1,050.00 | $1,050.00 | 3 | Allan Myers Va, Inc. | VDOT |
| 14 NOV 2018 | C0000000108004 | Richmond | 3 | $976.63 | $1,200.00 | 3 | Curtis Contracting, Inc. | VDOT |
| 28 MAR 2018 | C000108909M01 | Salem | 1 | $1,789.00 | $1,450.00 | 3 | E. C. Pace Company, Inc. | VDOT |
| 20 DEC 2017 | C0000109436C01 | Bristol | 2 | $2,750.00 | $2,750.00 | 3 | Elk Knob, Inc. | VDOT |
| 26 APR 2017 | C0000107044C01 | Hampton Roads | 1 | $750.00 | $873.43 | 3 | Branch Civil, Inc. | VDOT |
| 22 FEB 2017 | C0000108057C01B | Staunton | 2 | $1,948.16 | $1,500.00 | 3 | Phillips Construction, LLC | VDOT |
| 21 DEC 2016 | C0000099542M01 | Salem | 2 | $1,576.80 | $1,500.00 | 3 | Phillips Construction, LLC | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.