VDOT contract C0000115716M01 bid tabulation
Smart scale - park and ride lot improvements. Let by Virginia DOT on May 27, 2026, Shenandoah, Staunton. 6 bids received; low bid $1,650,777 by Shirley Contracting Company, LLC.
- Owner
- Virginia DOT
- Letting
- 27 MAY 2026
- Pay items
- 85
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Shirley Contracting Company, LLC | $1,650,777 | Low |
| 2 | G. B. Foltz Contracting, Inc. | $1,699,097 | +3.0% |
| 3 | General Excavation, Inc. | $1,895,845 | +15% |
| 4 | Sagres Construction Corporation | $1,944,752 | +18% |
| 5 | Independence Excavating, Inc. | $2,052,925 | +24% |
| 6 | W-L Construction & Paving, Inc. | $2,086,493 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shirley Contracting Company, LLC | 2. G. B. Foltz Contracting, Inc. | 3. General Excavation, Inc. | 4. Sagres Construction Corporation | 5. Independence Excavating, Inc. | 6. W-L Construction & Paving, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001-0010 | Const rec docs SWM facility construction record documents (105SP20-0002) | LS | 1 | $2,500.00 | $5,890.00 | $5,940.00 | $15,000 | $10,000 | $31,000 |
| 0001-0020 | Endwall EW-12 (302SD20-0013) | EACH | 1 | $1,000.00 | $973.00 | $2,167.00 | $2,000.00 | $600.00 | $1,020.00 |
| 0001-0030 | 15" pipe (302SD20-0023) | LF | 94 | $325.00 | $196.32 | $176.00 | $355.00 | $250.00 | $125.00 |
| 0001-0040 | 24" pipe (302SD20-0037) | LF | 139 | $400.00 | $269.82 | $281.00 | $395.00 | $350.00 | $163.00 |
| 0001-0050 | 24" conc. pipe (302SD20-0039) | LF | 24 | $450.00 | $388.58 | $283.00 | $395.00 | $400.00 | $163.00 |
| 0001-0060 | 30" X 19" elliptical conc. pipe (302SD20-0135) | LF | 46 | $500.00 | $468.17 | $313.00 | $435.00 | $700.00 | $250.00 |
| 0001-0070 | 15" end section ES-1 or 2 (302SD20-0198) | EACH | 2 | $1,500.00 | $2,991.25 | $2,364.00 | $3,750.00 | $3,000.00 | $1,100.00 |
| 0001-0080 | 24" end section ES-1 or 2 (302SD20-0204) | EACH | 1 | $2,000.00 | $3,466.25 | $2,832.00 | $6,500.00 | $3,500.00 | $1,400.00 |
| 0001-0090 | Drop inlet DI-7 (302SD20-0447) | EACH | 1 | $8,000.00 | $9,153.00 | $7,778.00 | $17,500 | $12,000 | $4,400.00 |
| 0001-0100 | Stormwater man.drain.STR.SWM-1 (302SD20-0673) | LF | 6 | $3,200.00 | $3,228.33 | $1,952.00 | $3,000.00 | $2,000.00 | $800.00 |
| 0001-0110 | Grading (303SD20-0004) | LS | 1 | $447,308 | $338,848 | $359,520 | $360,000 | $525,000 | $614,597 |
| 0001-0120 | Borrow excavation (303SD20-0007) | CY | 600 | $8.00 | $112.60 | $61.00 | $110.00 | $70.00 | $80.50 |
| 0001-0130 | Check dam rock TY. I (303SD20-0022) | EACH | 26 | $1,100.00 | $533.77 | $3,034.00 | $450.00 | $700.00 | $1,000.00 |
| 0001-0140 | Check dam rock TY. II (303SD20-0023) | EACH | 10 | $500.00 | $837.25 | $843.00 | $450.00 | $800.00 | $1,000.00 |
| 0001-0150 | Siltation control excavation (303SD20-0029) | CY | 142 | $5.00 | $14.37 | $22.00 | $50.00 | $30.00 | $5.00 |
| 0001-0160 | Inlet protection type A (303SD20-0030) | EACH | 1 | $335.00 | $109.00 | $638.00 | $250.00 | $1,000.00 | $1,400.00 |
| 0001-0170 | Inlet protection type B (303SD20-0031) | EACH | 2 | $775.00 | $143.00 | $416.00 | $250.00 | $1,500.00 | $550.00 |
| 0001-0180 | NS geotextile fabric subgrade separation (303SX20-0008) | SY | 5,022 | $4.00 | $3.37 | $3.50 | $10.00 | $7.00 | $1.25 |
| 0001-0190 | Lime (306SD20-0001) | TON | 3.80 | $450.00 | $665.79 | $316.00 | $1,000.00 | $325.00 | $1,100.00 |
| 0001-0200 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 1,689 | $40.00 | $37.63 | $66.00 | $70.00 | $80.00 | $52.00 |
| 0001-0210 | Select material type ogb (309SP20-0001) | TON | 1,689 | $50.00 | $57.53 | $49.00 | $85.00 | $118.00 | $48.00 |
| 0001-0220 | Asphalt concrete TY. SM- 12.5A const (315SD20-0001) | TON | 605 | $130.00 | $145.00 | $129.00 | $250.00 | $155.00 | $160.00 |
| 0001-0230 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 25 | $345.00 | $167.00 | $592.00 | $200.00 | $280.00 | $460.00 |
| 0001-0240 | Saw-cut asphalt concrete full depth (315SD20-0104) | LF | 200 | $3.00 | $7.45 | $8.00 | $3.00 | $10.00 | $5.81 |
| 0001-0250 | Erosion CTRL. stone CL. A1, EC-1 (414SD20-0001) | TON | 73 | $225.00 | $99.78 | $191.00 | $150.00 | $120.00 | $132.00 |
| 0001-0260 | Erosion CTRL. stone CL. I, EC-1 (414SD20-0003) | TON | 25 | $225.00 | $90.88 | $218.00 | $150.00 | $115.00 | $132.00 |
| 0001-0270 | NS BRG. lighting system remove exist. parking lot lighting sys. (419SX20-0009) | LS | 1 | $15,000 | $11,111 | $11,200 | $18,000 | $5,000.00 | $28,786 |
| 0001-0280 | Crossdrain CD-2 (501SD20-0007) | LF | 65 | $50.00 | $31.38 | $52.00 | $50.00 | $70.00 | $60.00 |
| 0001-0290 | Outlet pipe (501SD20-0009) | LF | 10 | $160.00 | $7.80 | $102.00 | $55.00 | $100.00 | $100.00 |
| 0001-0300 | Concrete class A3 misc. (504SD20-0001) | CY | 10.57 | $2,000.00 | $1,007.35 | $1,983.00 | $2,000.00 | $2,500.00 | $3,500.00 |
| 0001-0310 | CG-12 detectable warning surface (504SD20-0002) | SY | 7 | $2,500.00 | $1,117.50 | $303.00 | $500.00 | $270.00 | $306.82 |
| 0001-0320 | Hydr. cement conc. sidewalk 4" (504SD20-0003) | SY | 90 | $150.00 | $73.20 | $121.00 | $220.00 | $115.00 | $130.00 |
| 0001-0330 | NS concrete conc parking lot wheel stop (504SX20-0007) | EACH | 83 | $225.00 | $706.00 | $286.00 | $300.00 | $500.00 | $635.18 |
| 0001-0340 | Fence FE-CL (507SD20-0005) | LF | 275 | $65.00 | $33.00 | $62.00 | $125.00 | $35.00 | $29.00 |
| 0001-0350 | Line brace unit FE-CL (507SD20-0007) | EACH | 2 | $325.00 | $445.00 | $1,000.00 | $3,000.00 | $400.00 | $400.00 |
| 0001-0360 | Corner brace unit FE-CL (507SD20-0009) | EACH | 2 | $325.00 | $500.00 | $1,200.00 | $3,000.00 | $450.00 | $450.00 |
| 0001-0370 | Demo. of pavement flexible (508SD20-0004) | SY | 1,395 | $12.00 | $10.42 | $42.00 | $20.00 | $15.00 | $8.50 |
| 0001-0380 | NS remove exist. storm pipe (510SX20-0039) | LF | 49 | $200.00 | $40.71 | $110.00 | $230.00 | $100.00 | $82.00 |
| 0001-0390 | NS remove exist. control center (510SX20-0040) | EACH | 1 | $1,700.00 | $1,666.00 | $1,680.00 | $1,800.00 | $1,500.00 | $1,763.05 |
| 0001-0400 | NS remove exist. junction box (510SX20-0040) | EACH | 2 | $600.00 | $585.00 | $588.00 | $650.00 | $700.00 | $671.26 |
| 0001-0410 | Allaying dust (511SD20-0001) | HR | 60 | $55.00 | $38.67 | $129.00 | $100.00 | $120.00 | $120.00 |
| 0001-0420 | Type 3 barricade 8' (512SD20-0013) | EACH | 7 | $700.00 | $280.00 | $697.00 | $500.00 | $275.00 | $1,200.00 |
| 0001-0430 | Temporary sign (512SD20-0014) | SF | 250 | $80.00 | $24.00 | $60.00 | $45.00 | $22.00 | $63.00 |
| 0001-0440 | Truck mounted attenuator (512SD20-0023) | HR | 250 | $22.00 | $36.67 | $32.00 | $20.00 | $55.00 | $62.00 |
| 0001-0450 | Group 2 channelizing devices (512SD20-0024) | DAY | 1,800 | $3.00 | $0.30 | $1.60 | $2.00 | $1.00 | $2.96 |
| 0001-0460 | Electronic arrow board (512SD20-0026) | HR | 250 | $3.00 | $3.18 | $7.00 | $16.00 | $4.00 | $20.00 |
| 0001-0470 | Flagger service (512SD20-0027) | HR | 960 | $12.00 | $150.00 | $69.00 | $35.00 | $61.00 | $35.00 |
| 0001-0480 | Portable temporary rumble strip array (512SP20-0001) | DAY | 40 | $225.00 | $95.00 | $471.00 | $35.00 | $85.00 | $172.00 |
| 0001-0490 | Mobilization (513SD20-0001) | LS | 1 | $112,500 | $108,693 | $124,790 | $100,000 | $130,000 | $220,000 |
| 0001-0500 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 480 | $10.00 | $8.50 | $10.00 | $30.00 | $19.00 | $12.00 |
| 0001-0510 | Construction surveying constr. (517SD20-0001) | LS | 1 | $50,000 | $24,700 | $132,991 | $45,000 | $50,000 | $20,000 |
| 0001-0520 | Storm water management low permeability liner (523SP20-0002) | SY | 417 | $25.00 | $39.76 | $141.00 | $35.00 | $75.00 | $62.00 |
| 0001-0530 | Topsoil class B 12" SWM (602SD20-0004) | CY | 139 | $35.00 | $131.51 | $137.00 | $90.00 | $30.00 | $60.50 |
| 0001-0540 | Topsoil class B 3" (602SD20-0004) | CY | 278 | $35.00 | $123.11 | $137.00 | $90.00 | $28.00 | $60.50 |
| 0001-0550 | Temporary seed (603SD20-0002) | LB | 69 | $20.00 | $5.56 | $14.00 | $12.00 | $6.00 | $15.72 |
| 0001-0560 | Regular seed (603SD20-0003) | LB | 276 | $11.00 | $7.50 | $8.00 | $10.00 | $7.00 | $15.72 |
| 0001-0570 | Overseeding (603SD20-0004) | LB | 221 | $11.00 | $9.72 | $8.00 | $10.00 | $9.00 | $15.72 |
| 0001-0580 | Hydraulic erosion control product type 2 (603SD20-0008) | SY | 4,175 | $1.00 | $0.65 | $1.20 | $3.00 | $0.75 | $2.23 |
| 0001-0590 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 3,340 | $1.00 | $10.30 | $1.50 | $3.00 | $1.00 | $2.23 |
| 0001-0600 | Fertilizer nitrogen - N (603SD20-0014) | LB | 69 | $2.00 | $4.14 | $2.00 | $5.00 | $3.50 | $5.05 |
| 0001-0610 | Fertilizer phosphorous - P (603SD20-0015) | LB | 48 | $2.00 | $3.75 | $2.00 | $5.00 | $3.60 | $5.05 |
| 0001-0620 | Fertilizer potassium - K (603SD20-0016) | LB | 48 | $2.00 | $3.75 | $2.00 | $5.00 | $3.70 | $5.05 |
| 0001-0630 | Rolled erosion CTRL product EC-2 type 1 (606SD20-0001) | SY | 649 | $7.00 | $4.38 | $5.00 | $3.50 | $10.00 | $2.85 |
| 0001-0640 | Rolled erosion CTRL product EC-3 type 1 (606SD20-0005) | SY | 214 | $10.00 | $11.62 | $14.00 | $5.50 | $20.00 | $7.63 |
| 0001-0650 | Relocate EX. 1 post GRND mount SGN panel (700SD20-0012) | EACH | 2 | $450.00 | $390.00 | $392.00 | $500.00 | $480.00 | $450.00 |
| 0001-0660 | Sign post STP-1, 2 1/2", 12 gauge (700SD20-0037) | LF | 270 | $25.00 | $22.50 | $23.00 | $25.00 | $42.00 | $40.00 |
| 0001-0670 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 20 | $645.00 | $556.00 | $561.00 | $750.00 | $500.00 | $525.00 |
| 0001-0680 | 8 conductor cable (700SD20-0144) | LF | 4,400 | $3.00 | $2.50 | $3.00 | $3.00 | $2.00 | $6.16 |
| 0001-0690 | 8 conductor cable egc (700SD20-0148) | LF | 1,900 | $3.00 | $2.30 | $3.00 | $3.00 | $2.10 | $4.09 |
| 0001-0700 | Conc. found. LF-1, TY. A (700SD20-0149) | EACH | 13 | $2,100.00 | $2,353.00 | $2,100.00 | $2,500.00 | $3,000.00 | $4,596.15 |
| 0001-0710 | Lighting pole LP-2 type D (700SD20-0156) | EACH | 13 | $5,200.00 | $5,225.00 | $5,265.00 | $6,250.00 | $7,000.00 | $6,878.42 |
| 0001-0720 | Electrical service SE-8, TY. A (700SD20-0170) | EACH | 1 | $4,200.00 | $4,280.00 | $4,312.00 | $5,000.00 | $4,000.00 | $6,633.65 |
| 0001-0730 | Electrical service work pad (700SD20-0174) | EACH | 1 | $3,600.00 | $3,556.00 | $3,585.00 | $4,250.00 | $1,600.00 | $1,342.53 |
| 0001-0740 | Junction box JB-S1 (700SD20-0177) | EACH | 3 | $2,000.00 | $2,102.00 | $1,880.00 | $2,100.00 | $1,700.00 | $2,726.50 |
| 0001-0750 | Elect. ser. GRD. electrode 10' (700SD20-0181) | EACH | 5 | $355.00 | $362.00 | $365.00 | $400.00 | $400.00 | $223.57 |
| 0001-0760 | Bored conduit 2" (700SD20-0191) | LF | 325 | $42.00 | $40.00 | $41.00 | $45.00 | $65.00 | $230.00 |
| 0001-0770 | Conduit PVC 2" (700SD20-0194) | LF | 1,810 | $15.00 | $13.50 | $14.00 | $15.00 | $16.00 | $9.58 |
| 0001-0780 | Trench excavation eci-1 (700SD20-0197) | LF | 1,450 | $45.00 | $28.00 | $28.00 | $37.50 | $22.00 | $12.08 |
| 0001-0790 | Sign panel (701SD20-0001) | SF | 89 | $50.00 | $53.00 | $54.00 | $60.00 | $50.00 | $48.00 |
| 0001-0800 | Type A PVMT line MRKG 4" (704SD20-0001) | LF | 800 | $2.00 | $7.80 | $3.00 | $2.50 | $7.00 | $7.00 |
| 0001-0810 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 3,432 | $3.00 | $7.80 | $3.00 | $2.50 | $6.00 | $7.00 |
| 0001-0820 | Type B class II PVMT line MRKG 24" (704SD20-0015) | LF | 110 | $20.00 | $30.00 | $25.00 | $27.50 | $26.00 | $27.00 |
| 0001-0830 | MRKG int'L accessibility symb TY B CL II (704SD20-0093) | EACH | 5 | $325.00 | $500.00 | $252.00 | $300.00 | $400.00 | $450.00 |
| 0001-0840 | Control center CCW-1 type C (705SD20-0003) | EACH | 1 | $18,000 | $19,695 | $18,845 | $25,000 | $15,000 | $11,490 |
| 0001-0850 | NS luminaire luminaire LED 160 W (4000K) (705SX20-0001) | EACH | 13 | $1,200.00 | $1,085.00 | $1,093.00 | $1,250.00 | $1,500.00 | $1,068.09 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of May 27, 2026. Compiled by Mirage Metrics.