NS asphalt concrete SM- 9.5AL, VDOT 315SX20-0007
Low bidders on VDOT contracts carried a median of $315.00 per TON for this item, over the 24 months to 28 OCT 2026, across 1 low bids. Half of all 7 bids fell between $407.50 and $710.00.
- Owner
- Virginia DOT
- Item
- 315SX20-0007
- Unit
- TON
- Data through
- 28 OCT 2026
VDOT prints this item as “NS ASPHALT CONCRETE SM- 9.5AL”.
VDOT has bid this work under more than one code: 10598 on lettings from 26 FEB 2002 to 28 JUL 2021 (532 bids); 315SX20-0007 on lettings from 22 APR 2026 to 22 APR 2026 (7 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 16 | 16 | $42.50 | 46 | $43.75 |
| 2003 | 26 | 28 | $45.00 | 78 | $47.16 |
| 2004 | 19 | 22 | $45.45 | 57 | $47.00 |
| 2005 | 16 | 17 | $57.00 | 42 | $58.29 |
| 2006 | 15 | 15 | $83.24 | 36 | $79.98 |
| 2007 | 8 | 8 | $70.11 | 23 | $68.20 |
| 2008 | 4 | 4 | $89.88 | 8 | $89.38 |
| 2009 | 14 | 16 | $108.25 | 43 | $106.00 |
| 2010 | 10 | 10 | $84.53 | 23 | $82.00 |
| 2011 | 3 | 3 | $109.73 | 9 | $110.73 |
| 2012 | 10 | 14 | $109.88 | 41 | $115.00 |
| 2013 | 7 | 7 | $170.00 | 12 | $172.50 |
| 2014 | 6 | 9 | $135.00 | 25 | $135.00 |
| 2015 | 12 | 13 | $169.06 | 32 | $107.25 |
| 2016 | 13 | 13 | $175.00 | 18 | $175.18 |
| 2017 | 8 | 8 | $171.81 | 12 | $171.81 |
| 2018 | 2 | 2 | $141.00 | 6 | $148.00 |
| 2019 | 1 | 1 | $324.00 | 3 | $324.00 |
| 2020 | 5 | 6 | $74.10 | 15 | $145.69 |
| 2021 | 1 | 1 | $100.00 | 3 | $100.00 |
| 2026 | 1 | 1 | $315.00 | 7 | $500.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Bristol | 121 | $68.20 | 317 | $67.50 |
| Richmond | 33 | $100.81 | 96 | $111.69 |
| Staunton | 31 | $170.00 | 53 | $170.16 |
| Salem | 10 | $112.52 | 21 | $94.00 |
| Fredericksburg | 6 | $70.50 | 16 | $69.66 |
| Culpeper | 5 | $59.00 | 13 | $59.00 |
| Northern Virginia | 4 | $105.55 | 12 | $125.00 |
| Hampton Roads | 4 | $122.22 | 11 | $81.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 7 to 214 | 53 | $186.73 |
| 230 to 880 | 54 | $55.50 |
| 882 to 2,625 | 53 | $72.01 |
| 2,765 to 38,616 | 54 | $73.37 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| W-L Construction & Paving, Inc. | 47 | 27 (57%) |
| Mac Const., Inc. | 31 | 24 (77%) |
| Estes Bros. Const., Inc. | 22 | 13 (59%) |
| Lee Hy Paving Corporation | 19 | 8 (42%) |
| Mega Contractors, Inc. | 10 | 8 (80%) |
| Elk Knob, Inc. | 60 | 7 (12%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 APR 2026 | C0000117024B05 | Staunton | 38 | $315.00 | $500.00 | 7 | Fairfield-Echols, LLC | VDOT |
| 28 JUL 2021 | C0000092652M01 | Richmond | 50 | $100.00 | $100.00 | 3 | Allan Myers Va, Inc. | VDOT |
| 24 JUN 2020 | C0000114697P01B | Richmond | 100 | $25.00 | $145.69 | 3 | Devcon Contracting, Inc. | VDOT |
| 24 JUN 2020 | C0000114697P01B | Richmond | 100 | $25.00 | $145.69 | 3 | Devcon Contracting, Inc. | VDOT |
| 22 APR 2020 | C220PMJ116382B | Salem | 761 | $131.04 | $131.04 | 1 | Adams Construction Company | VDOT |
| 25 MAR 2020 | C0000018003C01 | Staunton | 1,161 | $92.20 | $101.10 | 2 | General Excavation, Inc. | VDOT |
| 25 MAR 2020 | CM420PM1115256 | Richmond | 600 | $56.00 | $1,194.77 | 3 | Allan Myers Va, Inc. | VDOT |
| 22 JAN 2020 | C0000108905M01B | Salem | 8 | $560.00 | $560.00 | 3 | Sowers Construction Co., Inc. | VDOT |
| 13 NOV 2019 | C0000113639B20 | Richmond | 326 | $324.00 | $324.00 | 3 | Wagman Heavy Civil, Inc. | VDOT |
| 19 DEC 2018 | C000098960B91 | Staunton | 204 | $132.00 | $135.19 | 3 | Kanawha Stone Company, Inc. | VDOT |
| 24 JAN 2018 | C000109813C01B | Northern Virginia | 31 | $150.00 | $285.00 | 3 | Ardent Company, LLC | VDOT |
| 20 DEC 2017 | C0000111225B11 | Fredericksburg | 3,433 | $507.13 | $653.57 | 2 | Allan Myers Va, Inc. | VDOT |
| 26 JUL 2017 | C0000103320C01 | Bristol | 9,816 | $76.23 | $82.00 | 3 | W-L Construction & Paving, Inc. | VDOT |
| 22 MAR 2017 | CM817LME109887 | Staunton | 1,386 | $178.62 | $178.62 | 1 | Slurry Pavers, Inc. | VDOT |
| 22 FEB 2017 | CM817PMK107826 | Staunton | 53 | $120.00 | $222.00 | 2 | B & S Contracting, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.