Concrete entrance pave. 7", VDOT 316SD20-0030
Low bidders on VDOT contracts carried a median of $382.63 per SY for this item, over the 24 months to 28 OCT 2026, across 3 low bids. Half of all 7 bids fell between $269.88 and $381.31.
- Owner
- Virginia DOT
- Item
- 316SD20-0030
- Unit
- SY
- Data through
- 28 OCT 2026
VDOT has bid this work under more than one code: 11040 on lettings from 24 SEP 2002 to 15 DEC 2021 (214 bids); 316SD20-0030 on lettings from 04 FEB 2026 to 22 JUL 2026 (7 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 2 | 2 | $50.25 | 6 | $51.70 |
| 2003 | 3 | 2 | $47.50 | 6 | $47.50 |
| 2004 | 2 | 2 | $45.00 | 4 | $50.00 |
| 2005 | 3 | 3 | $67.19 | 6 | $71.09 |
| 2006 | 2 | 2 | $83.82 | 6 | $56.50 |
| 2007 | 2 | 2 | $56.40 | 6 | $64.50 |
| 2008 | 6 | 6 | $57.20 | 18 | $64.08 |
| 2009 | 2 | 2 | $57.95 | 6 | $65.20 |
| 2010 | 7 | 7 | $70.00 | 20 | $75.00 |
| 2011 | 4 | 4 | $74.50 | 12 | $74.90 |
| 2012 | 4 | 4 | $55.00 | 12 | $69.00 |
| 2013 | 3 | 3 | $71.00 | 9 | $65.00 |
| 2014 | 10 | 10 | $85.77 | 28 | $85.00 |
| 2015 | 6 | 6 | $75.89 | 17 | $80.00 |
| 2016 | 4 | 4 | $91.25 | 11 | $100.00 |
| 2017 | 6 | 6 | $115.50 | 16 | $115.50 |
| 2018 | 1 | 1 | $95.00 | 3 | $95.00 |
| 2019 | 4 | 4 | $125.50 | 9 | $130.00 |
| 2020 | 5 | 5 | $125.00 | 14 | $143.96 |
| 2021 | 2 | 2 | $125.00 | 5 | $130.00 |
| 2026 | 3 | 3 | $382.63 | 7 | $350.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Salem | 12 | $85.00 | 36 | $85.50 |
| Hampton Roads | 14 | $65.75 | 36 | $71.80 |
| Richmond | 10 | $93.50 | 29 | $82.50 |
| Staunton | 10 | $58.45 | 26 | $65.00 |
| Bristol | 9 | $85.00 | 26 | $84.40 |
| Northern Virginia | 9 | $67.00 | 25 | $81.00 |
| Fredericksburg | 8 | $81.45 | 22 | $80.20 |
| Lynchburg | 6 | $105.00 | 15 | $98.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 5 to 46 | 20 | $92.25 |
| 47 to 103 | 20 | $82.50 |
| 103 to 236 | 20 | $67.73 |
| 241 to 2,239 | 20 | $65.95 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Fielder'S Choice Enterprises, Inc. | 12 | 6 (50%) |
| J. L. Kent & Sons, Inc. | 8 | 3 (38%) |
| E. V. Williams, Inc. | 6 | 3 (50%) |
| General Excavation, Inc. | 6 | 2 (33%) |
| Elk Knob, Inc. | 5 | 2 (40%) |
| Estes Bros. Const., Inc. | 5 | 2 (40%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 JUL 2026 | C0000120710C01 | Lynchburg | 74 | $125.00 | $226.41 | 2 | Caton Construction Group, Inc. | VDOT |
| 22 APR 2026 | C0000119163C01 | Lynchburg | 56 | $390.00 | $300.98 | 2 | Allegheny Construction Company, Inc. | VDOT |
| 04 FEB 2026 | C0000120758M01 | Salem | 166 | $382.63 | $380.00 | 3 | E. C. Pace Company, Inc. | VDOT |
| 15 DEC 2021 | C0000112638C01 | Hampton Roads | 47 | $120.00 | $167.50 | 2 | Gray and Sons Construction, Inc. | VDOT |
| 27 OCT 2021 | C000110913C01B | Fredericksburg | 33 | $130.00 | $130.00 | 3 | A & M Concrete Corp. | VDOT |
| 16 DEC 2020 | C0000101034C01 | Richmond | 40 | $125.00 | $125.00 | 3 | Allan Myers Va, Inc. | VDOT |
| 16 DEC 2020 | C0000116581C01 | Northern Virginia | 15 | $50.00 | $237.50 | 2 | North Construction, Inc. | VDOT |
| 18 NOV 2020 | C0000109814C01 | Northern Virginia | 7 | $125.00 | $144.90 | 3 | Tavares Concrete Co., Inc. | VDOT |
| 24 JUN 2020 | C0000111708C01 | Hampton Roads | 99 | $100.00 | $178.11 | 3 | Shamrock Construction Corporation | VDOT |
| 22 APR 2020 | C0000107061C01 | Salem | 116 | $143.02 | $143.02 | 3 | Kanawha Stone Company, Inc. | VDOT |
| 18 DEC 2019 | C0000086601B61 | Bristol | 71 | $130.00 | $170.94 | 3 | Elk Knob, Inc. | VDOT |
| 20 MAR 2019 | C0000111711C01 | Hampton Roads | 1,219 | $80.00 | $84.75 | 2 | Allan Myers Va, Inc. | VDOT |
| 27 FEB 2019 | C0000000673B03 | Salem | 201 | $135.00 | $135.00 | 3 | Brayman Construction Corporation | VDOT |
| 23 JAN 2019 | C000112282C501 | Northern Virginia | 15 | $121.00 | $121.00 | 1 | M & F Concrete, Inc. | VDOT |
| 22 AUG 2018 | C0000090018C01 | Richmond | 173 | $95.00 | $95.00 | 3 | J. L. Kent & Sons, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.