NS fence construction safety, VDOT 507SX20-0013
Low bidders on VDOT contracts carried a median of $6.00 per LF for this item, over the 24 months to 28 OCT 2026, across 1 low bids. Half of all 4 bids fell between $8.63 and $28.75.
- Owner
- Virginia DOT
- Item
- 507SX20-0013
- Unit
- LF
- Data through
- 28 OCT 2026
VDOT prints this item as “NS FENCE CONSTRUCTION SAFETY”.
VDOT has bid this work under more than one code: 23600 on lettings from 26 MAR 2002 to 25 AUG 2021 (437 bids); 507SX20-0013 on lettings from 27 MAY 2026 to 27 MAY 2026 (4 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 11 | 17 | $4.00 | 50 | $5.10 |
| 2003 | 8 | 15 | $3.25 | 45 | $3.50 |
| 2004 | 12 | 27 | $6.50 | 49 | $7.00 |
| 2005 | 3 | 4 | $17.00 | 9 | $12.50 |
| 2006 | 7 | 8 | $4.77 | 21 | $5.20 |
| 2007 | 7 | 13 | $8.85 | 39 | $9.40 |
| 2008 | 4 | 9 | $10.50 | 25 | $8.50 |
| 2009 | 6 | 10 | $7.67 | 30 | $8.50 |
| 2010 | 2 | 2 | $20.50 | 6 | $20.50 |
| 2011 | 7 | 8 | $14.00 | 24 | $14.00 |
| 2012 | 5 | 6 | $5.75 | 17 | $5.50 |
| 2013 | 6 | 6 | $12.00 | 18 | $15.00 |
| 2014 | 8 | 10 | $9.75 | 30 | $12.62 |
| 2015 | 10 | 13 | $9.90 | 31 | $10.00 |
| 2016 | 3 | 2 | $21.65 | 5 | $22.62 |
| 2017 | 3 | 4 | $16.60 | 12 | $17.60 |
| 2018 | 2 | 4 | $181.50 | 12 | $197.50 |
| 2019 | 1 | 1 | $4.00 | 1 | $4.00 |
| 2020 | 2 | 2 | $20.50 | 5 | $24.15 |
| 2021 | 2 | 2 | $23.07 | 6 | $23.07 |
| 2026 | 1 | 1 | $6.00 | 4 | $17.25 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Staunton | 50 | $7.70 | 126 | $7.80 |
| Northern Virginia | 35 | $8.00 | 98 | $8.00 |
| Culpeper | 33 | $6.00 | 88 | $6.67 |
| Hampton Roads | 16 | $14.50 | 43 | $15.00 |
| Salem | 13 | $5.00 | 34 | $10.50 |
| Fredericksburg | 6 | $17.56 | 18 | $21.11 |
| Richmond | 5 | $20.00 | 14 | $23.62 |
| Bristol | 4 | $20.18 | 12 | $23.07 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 16 to 205 | 41 | $20.00 |
| 215 to 500 | 41 | $8.50 |
| 500 to 1,510 | 41 | $7.70 |
| 1,600 to 12,368 | 41 | $4.80 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| General Excavation, Inc. | 37 | 22 (59%) |
| Chemung Contracting Corporation | 12 | 8 (67%) |
| Pearson Construction, Inc. | 9 | 7 (78%) |
| Rock & Raines Construction Co., Inc | 13 | 5 (38%) |
| Rappawan, Inc. | 9 | 5 (56%) |
| E. V. Williams, Inc. | 8 | 5 (63%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 27 MAY 2026 | C0000121826C01 | Northern Virginia | 98 | $6.00 | $17.25 | 4 | Fort Myer Construction Corporation | VDOT |
| 25 AUG 2021 | C0000116173N01 | Bristol | 11,810 | $31.15 | $35.94 | 3 | W-L Construction & Paving, Inc. | VDOT |
| 26 MAY 2021 | C0000104005C01 | Northern Virginia | 1,200 | $15.00 | $14.40 | 3 | Shirley Contracting Company, LLC | VDOT |
| 24 JUN 2020 | C0000107797C01 | Richmond | 325 | $20.00 | $24.15 | 3 | Allan Myers Va, Inc. | VDOT |
| 25 MAR 2020 | C0000018003C01 | Staunton | 568 | $21.00 | $23.00 | 2 | General Excavation, Inc. | VDOT |
| 30 AUG 2019 | C0000116220N01 | Salem | 200 | $4.00 | $4.00 | 1 | E. C. Pace Company, Inc. | VDOT |
| 23 MAY 2018 | C0000112769N01 | Fredericksburg | 25 | $565.00 | $565.00 | 3 | Hurricane Fence Co. | VDOT |
| 24 JAN 2018 | C000109813C01B | Northern Virginia | 117 | $175.00 | $195.00 | 3 | Ardent Company, LLC | VDOT |
| 24 JAN 2018 | C000109813C01B | Northern Virginia | 145 | $188.00 | $200.00 | 3 | Ardent Company, LLC | VDOT |
| 24 JAN 2018 | C000109813C01B | Northern Virginia | 285 | $5.00 | $12.00 | 3 | Ardent Company, LLC | VDOT |
| 20 DEC 2017 | C0000087905M01 | Salem | 4,728 | $12.00 | $13.80 | 3 | Sowers Construction Co., Inc. | VDOT |
| 20 DEC 2017 | C0000087905M01 | Salem | 3,109 | $10.00 | $11.50 | 3 | Sowers Construction Co., Inc. | VDOT |
| 15 NOV 2017 | C0000090183M01 | Staunton | 305 | $21.20 | $22.00 | 3 | Fairfield-Echols, LLC | VDOT |
| 22 FEB 2017 | C0000109129B25 | Culpeper | 50 | $125.00 | $125.00 | 3 | DW Miller Construction, Inc. | VDOT |
| 25 MAY 2016 | C0000108336C01 | Northern Virginia | 84 | $22.62 | $25.31 | 2 | Fort Myer Construction Corporation | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.