NS safety uniformed flagger, VDOT 512SX20-0045

Low bidders on VDOT contracts carried a median of $109.12 per HR for this item, over the 24 months to 28 OCT 2026, across 2 low bids. Half of all 4 bids fell between $105.94 and $142.12.

Owner
Virginia DOT
Item
512SX20-0045
Unit
HR
Data through
28 OCT 2026

VDOT prints this item as “NS SAFETY UNIFORMED FLAGGER”.

VDOT has bid this work under more than one code: 24360 on lettings from 06 JUL 2005 to 15 DEC 2021 (162 bids); 512SX20-0045 on lettings from 19 NOV 2025 to 25 FEB 2026 (4 bids). They are combined here into one trend.

$109.12Low bidder's median, per HR
$127.25Median of all bids, per HR
2Contracts in the window

By year of letting

NS safety uniformed flagger, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200511$65.003$65.00
200611$225.001$225.00
200711$37.503$39.13
200811$20.002$20.00
200911$22.423$25.00
201011$55.001$55.00
201111$4.003$28.00
201211$120.003$120.00
201333$72.005$72.00
201421$20.005$55.00
201544$175.0010$112.50
2016910$68.5029$75.00
201733$80.009$75.00
201856$98.5015$72.00
201988$39.5019$40.00
20201111$65.0026$48.68
20211010$53.5023$50.00
202511$78.752$114.38
202611$139.492$127.25

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Richmond22$53.5057$40.00
Bristol11$51.5925$50.00
Culpeper7$72.0016$75.00
Northern Virginia4$107.5012$50.00
Lynchburg4$115.0012$100.00
Hampton Roads4$37.7511$39.13
Salem5$50.1411$55.00
Fredericksburg4$102.5011$100.00
Staunton5$78.759$150.00
NS safety uniformed flagger, VDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Quantity (HR)Low bidsLow-bid median
8 to 5016$95.00
50 to 17017$72.00
175 to 50016$54.00
544 to 13,14117$50.00
NS safety uniformed flagger, VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Allan Myers Va, Inc.137 (54%)
Lanford Brothers Company, Incorporated116 (55%)
Branscome Inc.115 (45%)
Crossroads Bridge Inc84 (50%)
Curtis Contracting, Inc.53 (60%)
Elk Knob, Inc.53 (60%)
NS safety uniformed flagger, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
25 FEB 2026C0000119431C01BBristol160$139.49$127.252King General Contractors, Inc.VDOT
19 NOV 2025C0000127310N01Staunton460$78.75$114.382Richardson-Wayland-Ferreira, LLCVDOT
15 DEC 2021CM422LMA119576Richmond730$57.00$57.001Slurry Pavers, Inc.VDOT
27 OCT 2021C0000118978N01Northern Virginia800$150.00$100.003M. D. Miller Co., Inc.VDOT
27 OCT 2021C0000119130C01Staunton100$57.00$90.503B & B Signal Co., L.L.C.VDOT
22 SEP 2021C0000118463B20Bristol24$250.00$200.003M. D. Miller Co., Inc.VDOT
23 JUN 2021C0000110793C01Bristol480$20.00$20.001Ramirez Contracting, L.L.C.VDOT
28 APR 2021CM421LMB118387Richmond465$58.00$58.001Slurry Pavers, Inc.VDOT
24 FEB 2021CM421PMA117920Richmond663$36.25$36.253Allan Myers Va, Inc.VDOT
24 FEB 2021CM421PMC117924Richmond410$50.00$40.002Colony Construction, Inc.VDOT
24 FEB 2021CM421PMF117925Richmond555$50.00$40.003Colony Construction, Inc.VDOT
24 FEB 2021CM421PMG117926Richmond33$35.00$40.003Branscome Inc.VDOT
16 DEC 2020CM421LMA117636Richmond550$58.00$58.001Slurry Pavers, Inc.VDOT
18 NOV 2020C0000109419C01Bristol160$99.12$99.123Phillips Construction, LLC of Ky(Use In Va By:Phillips ConstVDOT
23 SEP 2020C0000117245N01Richmond100$74.75$74.751Richardson-Wayland Electrical Co. LLCVDOT
Latest VDOT contracts carrying NS safety uniformed flagger

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy