C Line (Green) Extension to Torrance
- Location
- Torrance, CA, United States. Location shown at city level. See it on the map
- Stage
- Planning, as of September 2025 (LA Metro).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | LA Metro | |
| Category | Urban transit | |
| Route length | 4.5 mi | LA Metro |
| New stations | 2 | LA Metro |
| Amount | US$2.23 billion (US dollars), as of September 2025 | LA Metro |
| What the amount covers | Capital estimate. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$2.23 bn | Capital estimate | Whole project | Sep 2025 | LA Metro |
Contracts and teams
Contracts and teams: No construction contract awarded yet LA Metro.
About the project
An approximately 4.5-mile light rail extension from the Redondo Beach (Marine) Station to a new Torrance Transit Center station along Metro's Harbor Subdivision right-of-way, with elevated, at-grade and trench sections and two new stations. Metro released the Final EIR on September 11, 2025; the locally preferred alternative's projected cost is $2.23 billion as estimated in 2022. Construction could start as early as 2027 with an estimated opening in 2036.
Sources
- C Line (Green) Extension to Torrance Final Environmental Impact Report, Chapter 5.2 Major Topic Responses, LA Metro, Sep 2025. MR-1 Selection of Alternatives: 'the LPA's projected cost of $2.23 billion, as estimated in 2022' versus $2.96 billion for the Hawthorne Option. Consulted 12 Nov 2026.
- LA Metro Releases Final Environmental Impact Report for C Line Extension to Torrance, LA Metro, 11 Sep 2025. Body: approximately 4.5 miles, two new stations, construction as early as 2027, opening estimated 2036. Consulted 12 Nov 2026.