ALDOT contract 20250131036 bid tabulation
INTERSECTION IMPROVEMENTS AND TRAFFIC SIGNAL INSTALLATION ON SR-14 AT THE 17 SPRINGS ENTRANCE IN MILLBROOK. Let by Alabama DOT on January 31, 2025, Elmore, 0601. 4 bids received; low bid $596,807 by Wiregrass Construction Company, Inc..
- Owner
- Alabama DOT
- Letting
- 31 JAN 2025
- Pay items
- 60
- Data through
- 28 AUG 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Wiregrass Construction Company, Inc. | $596,807 | Low |
| 2 | Dubose Construction Company, LLC | $612,631 | +3.0% |
| 3 | McElhenney Construction Co., LLC | $684,446 | +15% |
| 4 | Apac-Alabama, Inc. | $753,691 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Wiregrass Construction Company, Inc. | 2. Dubose Construction Company, LLC | 3. McElhenney Construction Co., LLC | 4. Apac-Alabama, Inc. |
|---|---|---|---|---|---|---|---|
| 0010 | Clearing and grubbing (maximum allowable bid $ 8,000.00 per acre) (approximately 1 acre) (201A002) | LS | 1 | $8,000.00 | $500.00 | $7,800.00 | $8,000.00 |
| 0020 | Removing pipe (206D000) | LF | 54 | $66.62 | $40.00 | $29.78 | $62.00 |
| 0030 | Removing headwalls (206E000) | EACH | 2 | $1,758.87 | $1,500.00 | $1,489.03 | $1,125.00 |
| 0040 | Unclassified excavation (210A000) | CY | 487 | $30.74 | $65.00 | $55.58 | $96.10 |
| 0050 | Borrow excavation (loose truckbed measurement)(A4 or better) (210D021) | CY | 126 | $56.48 | $85.00 | $60.07 | $135.60 |
| 0060 | Crushed aggregate, section 825, for miscellaneous use (305B077) | TON | 215 | $112.32 | $95.00 | $109.22 | $140.55 |
| 0070 | Bituminous treatment A (401A000) | SY | 634 | $1.05 | $2.00 | $2.55 | $3.00 |
| 0080 | Tack coat (405A000) | GAL | 155 | $28.51 | $7.50 | $8.92 | $5.85 |
| 0090 | Planing existing pavement (approximately 1.10" thru 2.0" thick) (408A052) | SY | 538 | $11.80 | $35.00 | $24.55 | $27.15 |
| 0100 | Superpave bituminous concrete wearing surface layer, 1/2" maximum aggregate size mix, esal range C/D (424A360) | TON | 97 | $186.18 | $285.00 | $258.16 | $250.95 |
| 0110 | Superpave bituminous concrete upper binder layer, widening, 3/4" maximum aggregate size mix, esal range C/D (424B661) | TON | 65 | $229.28 | $275.00 | $272.83 | $187.00 |
| 0120 | Superpave bituminous concrete lower binder layer, widening, 1" maximum aggregate size mix, esal range C/D (424B692) | TON | 93 | $252.42 | $265.00 | $234.42 | $155.00 |
| 0130 | Mobilization (600A000) | LS | 1 | $71,000 | $70,000 | $103,254 | $89,850 |
| 0140 | Filter blanket, geotextile (610D003) | SY | 200 | $11.77 | $3.50 | $2.73 | $18.00 |
| 0150 | Topsoil (650A000) | CY | 141 | $75.94 | $75.00 | $43.69 | $14.00 |
| 0160 | Seeding (652A100) | ACRE | 1 | $1,877.46 | $1,000.00 | $1,796.51 | $1,950.00 |
| 0170 | Solid sodding (bermuda) (654A001) | SY | 1,158 | $9.66 | $10.00 | $8.54 | $21.50 |
| 0180 | Mulching (656A010) | ACRE | 1 | $1,770.18 | $1,000.00 | $982.31 | $2,025.00 |
| 0190 | Temporary seeding (665A000) | ACRE | 1 | $1,743.36 | $350.00 | $1,133.71 | $430.00 |
| 0200 | Temporary mulching (665B001) | TON | 3 | $1,555.61 | $250.00 | $822.98 | $550.00 |
| 0210 | Silt fence (665J002) | LF | 979 | $2.78 | $8.00 | $5.20 | $5.35 |
| 0220 | Temporary coarse aggregate,aldot number 1 (665N000) | TON | 200 | $80.10 | $40.00 | $71.38 | $105.00 |
| 0230 | Silt fence removal (665O001) | LF | 979 | $1.34 | $3.50 | $2.03 | $1.10 |
| 0240 | Pest control treatment (666A001) | ACRE | 1 | $10.73 | $100.00 | $608.98 | $80.00 |
| 0250 | Geometric controls (680A001) | LS | 1 | $15,000 | $20,000 | $38,727 | $15,000 |
| 0260 | Construction fuel (maximum bid limited to $ 35,000.00) (698A000) | LS | 1 | $0.00 | $25,000 | $0.00 | $0.00 |
| 0270 | Dotted, class 2, type A traffic stripe (5" wide) (701B207) | LF | 360 | $2.15 | $2.00 | $2.45 | $2.50 |
| 0280 | Solid temporary traffic stripe (701C001) | MI | 1 | $1,341.04 | $2,905.00 | $1,530.79 | $1,400.00 |
| 0290 | Solid white, class 2, type A traffic stripe (5" wide) (701G253) | LF | 1,276 | $2.15 | $1.75 | $2.45 | $2.15 |
| 0300 | Traffic control markings, class 2, type A (703A002) | SF | 754 | $6.44 | $8.00 | $7.35 | $6.40 |
| 0310 | Traffic control legends, class 2, type A (703B002) | SF | 142 | $6.44 | $18.00 | $7.35 | $6.40 |
| 0320 | Temporary traffic control markings (703D001) | SF | 721 | $3.22 | $2.50 | $3.67 | $3.20 |
| 0330 | Pavement markers, class A-H, type 2-C (705A030) | EACH | 36 | $10.73 | $15.00 | $12.25 | $10.65 |
| 0340 | Pavement markers, class A-H, type 2-D (705A037) | EACH | 9 | $10.73 | $15.00 | $12.25 | $10.65 |
| 0350 | Milepost, type A (709A000) | EACH | 1 | $1,200.00 | $250.00 | $306.16 | $275.00 |
| 0360 | Class 10 aluminum flat sign panels (type XI background) (710A163) | SF | 22 | $26.82 | $25.00 | $30.62 | $28.00 |
| 0370 | Roadway sign post (#3 U channel, galvanized steel or 2 ", 14 GA square tubular steel) (710B021) | LF | 51 | $18.24 | $17.00 | $20.82 | $19.00 |
| 0380 | Removal of existing roadway signs (710C000) | LS | 1 | $1,200.00 | $250.00 | $306.16 | $275.00 |
| 0390 | Fiber optic trunk cable, 36F (729A001) | LF | 4,963 | $2.84 | $2.65 | $3.25 | $3.50 |
| 0400 | Conduit, underground, non-metallic, 2 inch (729I101) | LF | 2,650 | $5.55 | $5.17 | $6.33 | $23.65 |
| 0410 | Locate tone wire (729I800) | LF | 3,228 | $0.73 | $0.68 | $0.83 | $1.20 |
| 0420 | Miscellaneous infrastructure, fusion splicing (729N000) | EACH | 40 | $65.61 | $61.16 | $74.90 | $80.30 |
| 0430 | Miscellaneous infrastructure, splice closure, underground, 36 fiber (729N113) | EACH | 2 | $1,800.00 | $1,003.01 | $1,228.32 | $1,250.00 |
| 0440 | Miscellaneous infrastructure, commbox, type F1 (729N301) | EACH | 10 | $2,385.39 | $2,223.44 | $2,722.89 | $2,125.00 |
| 0450 | Miscellaneous infrastructure, commbox, type F2 (729N302) | EACH | 3 | $3,436.66 | $3,203.34 | $3,922.90 | $3,000.00 |
| 0460 | Miscellaneous infrastructure, fiber marker post (729N500) | EACH | 13 | $244.23 | $227.65 | $278.79 | $415.00 |
| 0470 | Furnishing and installing traffic control unit ( SR-14 at 17 springs boulevard) (730C000) | LS | 1 | $28,000 | $20,944 | $38,710 | $16,520 |
| 0480 | Metal traffic signal pole foundation (730E000) | EACH | 4 | $5,673.18 | $5,288.02 | $6,475.86 | $14,985 |
| 0490 | Metal traffic signal strain pole (730G001) | EACH | 4 | $18,804 | $17,527 | $21,464 | $21,210 |
| 0500 | Traffic signal junction box type S1 (730K001) | EACH | 2 | $700.81 | $653.23 | $799.97 | $770.00 |
| 0510 | Traffic signal junction box type S2 (730K002) | EACH | 1 | $10,000 | $1,374.18 | $1,682.86 | $1,655.00 |
| 0520 | 1", non-metallic, conduit (730L003) | LF | 30 | $20.74 | $19.33 | $23.67 | $12.00 |
| 0530 | 2", non-metallic, conduit (730L005) | LF | 25 | $24.02 | $22.39 | $27.42 | $15.00 |
| 0540 | Luminaire extension assembly, 12' (730N000) | EACH | 6 | $2,444.54 | $2,278.58 | $2,790.41 | $3,565.00 |
| 0550 | Electrical power service assembly with wood pole (730T010) | EACH | 1 | $15,000 | $4,141.81 | $5,072.18 | $3,565.00 |
| 0560 | Construction signs (740B000) | SF | 254 | $6.97 | $6.50 | $7.96 | $8.10 |
| 0570 | Channelizing drums (740D000) | EACH | 100 | $55.00 | $75.00 | $12.25 | $100.35 |
| 0580 | Cones (36 inches high) (740E000) | EACH | 100 | $7.34 | $25.00 | $30.62 | $5.00 |
| 0590 | Portable sequential arrow and chevron sign unit (741C010) | EACH | 1 | $5,500.00 | $10,000 | $642.93 | $6,500.00 |
| 0600 | 6" electrical conduit, 1 line, type 5 installation (756A028) | LF | 733 | $72.90 | $67.95 | $83.21 | $80.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
Every contract let that day: ALDOT letting of January 31, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.