ALDOT letting results, April 25, 2025
18 contracts let by Alabama DOT on April 25, 2025, $45,773,101 in low bids, a median of 3 bidders per contract.
- Owner
- Alabama DOT
- Contracts
- 18
- Low bids, total
- $45,773,101
- Data through
- 28 AUG 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| 20250425035 | ROADWAY IMPROVEMENTS/ADDITIONAL LANES ON CR-39 (MCDONALD ROAD) FROM A POINT NORTH OF THE I-10 INTERCHANGE TO THE INTERSECTION OF OLD PASCAGOULA ROAD WEST | 0901 | 4 | Frank Turner Construction Co., Inc. | $8,621,974 | $9,684,122 | +12% | ALDOT |
| 20250425022 | ADVANCED CORRIDOR MANAGEMENT (TSM&O) ON VARIOUS ROUTES AT VARIOUS LOCATIONS AS INDICATED IN THE PLANS | 0104 | 3 | Williams Power & Signal, LLC | $7,590,357 | $9,596,957 | +26% | ALDOT |
| 20250425019 | RESURFACE, SIGNAL UPGRADES, INTERSECTION MODS, & STRIPE ON SR-7 (US-11) FROM THE JUNCTION OF SR-69 TO THE JUNCTION OF PLEASANT HILL DRIVE | 0502 | 2 | Apac-Alabama, Inc. | $6,897,558 | $7,259,899 | +5.0% | ALDOT |
| 20250425018 | SAFETY WIDEN, RESURFACE, ACCESS MANAGE, GUARDRAIL, & STRIPE ON SR-6 (US-82) FROM WEST OF THE JUNCTION OF ECHOLA ROAD TO WEST OF THE JUNCTION OF BUHL CUTOFF ROAD | 0502 | 2 | S. T. Bunn Construction Company, Inc. | $5,300,599 | $6,223,239 | +17% | ALDOT |
| 20250425026 | PLANING, RESURFACING, AND TRAFFIC STRIPE ON SR-10 FROM THE INTERSECTION OF SR-69 TO THE JUNCTION OF RECREATION DRIVE IN SWEET WATER | 0802 | 3 | Wiregrass Construction Company, Inc. | $2,875,002 | $2,895,127 | +1.0% | ALDOT |
| 20250425012 | MICRO-MILLING, RESURFACING, GUARDRAIL INSTALL, AND STRIPE ON SR-35 FROM THE INTERSECTION OF STAR ROAD TO THE JUNCTION OF DEERMAN AVENUE IN RAINSVILLE | 0103 | 3 | Rogers Group, Inc. | $2,586,280 | $2,895,675 | +12% | ALDOT |
| 20250425032 | SAFETY WIDEN, RESURFACE, GUARDRAIL INSTALL, AND STRIPE ON THE SR-28 FROM THE JUNCTION OF CR-21 TO THE JUNCTION OF SR-8 (US-80) | 0506 | 1 | S. T. Bunn Construction Company, Inc. | $2,450,320 | ALDOT | ||
| 20250425016 | SAFETY WIDENING, PLANING, RESURFACING, AND TRAFFIC STRIPE ON THE SR-193 SERVICE ROADS FROM HAMILTON BVLD TO SR- 193 TO INCLUDE HAMILTON BVLD FROM DOCKSIDE DR TO | 0901 | 2 | Apac-Alabama, Inc. | $1,594,503 | $1,657,780 | +4.0% | ALDOT |
| 20250425045 | ROADWAY IMPROVEMENTS AND WIDENING ON SR-225 FROM THE JUNCTION OF OAKRIDGE DRIVE IN SPANISH FORT TO THE JUNCTION OF GENERAL CANBY BOULEVARD | 0902 | 5 | Southern Land Development, L.L.C. | $1,299,463 | $1,339,511 | +3.0% | ALDOT |
| 20250425005 | TRAFFIC SIGN REPLACEMENTS ON I-22 FROM THE MISSISSIPPI STATE LINE TO THE JEFFERSON COUNTY LINE | 1008, 1009 | 2 | Ozark Safety Services, LLC | $1,282,061 | $1,344,993 | +5.0% | ALDOT |
| 20250425029 | PLANING, RESURFACING, GUARDRAIL INSTALL, AND TRAFFIC STRIPE ON SR-157 FROM THE JUNCTION OF CRUNK ROAD TO A POINT 0.520 MILE SOUTH OF THE JUNCTION OF CR-272 (MP | 0201 | 3 | Apac-Alabama, Inc. | $959,301 | $963,528 | 0.0% | ALDOT |
| 20250425008 | PLANING, RESURFACING, AND TRAFFIC STRIPE ON SR-9 (US-331) FROM 0.430 MILE NORTH OF THE JUNCTION OF RICHBURG HILL ROAD TO THE INTERSECTION OF 4TH STREET | 0705 | 2 | Wiregrass Construction Company, Inc. | $949,921 | $988,296 | +4.0% | ALDOT |
| 20250425039 | PLANING, RESURFACING, AND TRAFFIC STRIPE ON CR-83 (WALLAHATCHIE ROAD) FROM THE JUNCTION OF CR-85 (PIKE ROAD) TO THE JUNCTION OF SR-110 IN PIKE ROAD | 0603 | 4 | Apac-Alabama, Inc. | $872,007 | $892,494 | +2.0% | ALDOT |
| 20250425038 | PLANING, RESURFACING, AND TRAFFIC STRIPE ON ROSE HILL RD FROM GRANDVIEW RD TO CR-23 AND ON AIRPORT RD FROM CR-23 TO SR-14 | 0601 | 3 | Asphalt Contractors, Inc. | $712,479 | $751,927 | +6.0% | ALDOT |
| 20250425027 | RESRFACE (MICRO-SURFACING & SCRUB SEAL), AND STRIPE ON SR-106 FROM THE INTERSECTION OF SR-3 (US-31) IN GEORGIANA TO THE INTERSECTION OF CR-27 | 0604 | 3 | Wiregrass Construction Company, Inc. | $668,829 | $694,660 | +4.0% | ALDOT |
| 20250425042 | RESURFACING AND TRAFFIC STRIPE ON CR-68 FROM THE INTERSECTION OF CR-49 TO THE HOUSTON COUNTY LINE | 0704 | 3 | Apac-Alabama, Inc. | $554,382 | $559,497 | +1.0% | ALDOT |
| 20250425004 | TRAFFIC SIGN REPLACEMENT & TRAFFIC MONITORING UNITS ON I-22 FROM THE WALKER COUNTY LINE TO THE I-65 INTERCHANGE IN BIRMINGHAM | 0301 | 2 | Ozark Safety Services, LLC | $436,945 | $479,397 | +10% | ALDOT |
| 20250425001 | HIGH FRICTION SURFACE TREATMENT AND TRAFFIC STRIPE ON PELZER AVENUE FROM THE JUNCTION OF WAREINGWOOD DRIVE TO THE JUNCTION OF HONEYSUCKLE ROAD IN MONTGOMERY | 0603 | 1 | The Truesdell Corporation | $121,121 | ALDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ALDOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.