ARDOT contract 050439 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO REPLACE ONE BRIDGE ON HIGHWAY 25 IN INDEPENDENCE COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL AND DISPOSAL ITEMS, EARTHWORK, AGGREGATE BASE COURSE, ACHM BINDER, AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, APPROACH SLAB AND GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, EROSION CONTROL, RUMBLE STRIPES, CONSTRUCT ONE BRIDGE NO. 07721 (196.00'), AND MISC. ITEMS. Let by Arkansas DOT on November 4, 2026, Independence. 5 bids received; low bid $4,165,923 by White River Materials, Inc..
- Owner
- Arkansas DOT
- Letting
- 04 NOV 2026
- Pay items
- 81
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | White River Materials, Inc. | $4,165,923 | Low |
| 2 | Thomco, Inc. | $5,142,038 | +23% |
| 3 | Capital Paving & Construction, LLC | $5,154,911 | +24% |
| 4 | Robertson Contractors, Inc. | $5,414,111 | +30% |
| 5 | Graylee Construction, LLC | $6,174,843 | +48% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. White River Materials, Inc. | 2. Thomco, Inc. | 3. Capital Paving & Construction, LLC | 4. Robertson Contractors, Inc. | 5. Graylee Construction, LLC |
|---|---|---|---|---|---|---|---|---|
| 0001 | Clearing (201011) | STA | 24 | $564.75 | $1,099.66 | $715.61 | $2,050.00 | $1,310.40 |
| 0002 | Grubbing (201111) | STA | 24 | $813.31 | $792.77 | $319.89 | $1,600.00 | $954.00 |
| 0003 | Removal and disposal of fence (202011) | LF | 3,276 | $4.20 | $5.12 | $2.19 | $8.50 | $7.20 |
| 0004 | Removal and disposal of gates (202017) | EACH | 8 | $293.76 | $319.88 | $141.67 | $500.00 | $384.00 |
| 0005 | Removal and disposal of concrete driveways (202062) | SY | 47 | $31.23 | $24.95 | $100.31 | $45.00 | $30.00 |
| 0006 | Removal and disposal of pipe culverts (202096) | EACH | 5 | $423.96 | $2,507.82 | $947.96 | $850.00 | $3,012.00 |
| 0007 | Removal and disposal of guardrail (202132) | LF | 450 | $4.61 | $9.00 | $7.61 | $8.00 | $7.20 |
| 0008 | Removal of existing bridge structure (site no. 1) (205011) | LS | 1 | $145,000 | $70,000 | $53,379 | $80,000 | $47,940 |
| 0009 | Unclassified excavation (210213) | CY | 6,839 | $12.20 | $18.46 | $7.24 | $20.50 | $22.20 |
| 0010 | Compacted embankment (210611) | CY | 30,684 | $20.28 | $25.42 | $28.85 | $26.85 | $30.60 |
| 0011 | Soil stabilization (210702) | TON | 100 | $220.00 | $400.00 | $356.99 | $307.50 | $480.00 |
| 0012 | Aggregate base course (class 7) (303117) | TON | 7,284 | $22.24 | $30.28 | $38.93 | $31.50 | $36.34 |
| 0013 | Tack coat (401011) | GAL | 1,412 | $6.00 | $6.00 | $7.88 | $6.00 | $7.20 |
| 0014 | Mineral aggregate in achm binder course (1") (406161) | TON | 2,312 | $117.60 | $117.60 | $154.53 | $117.60 | $141.12 |
| 0015 | Asphalt binder (PG 70-22) in achm binder course (1") (minimum bid $120.00) (406412) | TON | 114 | $120.00 | $120.00 | $157.68 | $120.00 | $144.00 |
| 0016 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 1,985 | $138.01 | $138.01 | $181.36 | $138.01 | $165.61 |
| 0017 | Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442) | TON | 124 | $120.00 | $120.00 | $157.68 | $120.00 | $144.00 |
| 0018 | Cold milling asphalt pavement (412002) | SY | 489 | $19.88 | $19.88 | $26.12 | $19.88 | $23.86 |
| 0019 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 10 | $300.00 | $350.00 | $190.54 | $220.00 | $216.00 |
| 0020 | Achm patching of existing roadway (415011) | TON | 10 | $400.00 | $400.00 | $525.63 | $400.00 | $966.00 |
| 0021 | Approach slabs (504031) | CY | 150.40 | $586.93 | $950.00 | $690.55 | $960.00 | $991.80 |
| 0022 | Approach gutters (504264) | CY | 16.80 | $1,124.97 | $2,550.00 | $1,701.98 | $1,650.00 | $1,803.60 |
| 0023 | Portland cement concrete driveway (505011) | SY | 88.73 | $117.77 | $300.00 | $125.59 | $170.00 | $225.00 |
| 0024 | Furnishing field office (602011) | EACH | 1 | $38,730 | $50,000 | $77,607 | $40,000 | $50,400 |
| 0025 | Maintenance of traffic (603009) | LS | 1 | $70,017 | $136,000 | $100,576 | $115,000 | $66,000 |
| 0026 | Signs (604003) | SF | 472 | $7.00 | $14.40 | $23.65 | $14.40 | $21.60 |
| 0027 | Barricades (604013) | LF | 32 | $25.00 | $20.00 | $32.85 | $20.00 | $30.00 |
| 0028 | Traffic drums (604023) | EACH | 60 | $24.00 | $52.00 | $85.41 | $52.00 | $78.00 |
| 0029 | Furnishing and installing precast concrete barrier (604031) | LF | 1,092 | $40.00 | $46.00 | $60.44 | $46.00 | $56.40 |
| 0030 | Relocating precast concrete barrier (max. bid 25% of item number ) (604036) | LF | 426 | $10.00 | $11.50 | $15.11 | $11.50 | $14.09 |
| 0031 | Construction pavement markings (604041) | LF | 10,040 | $0.32 | $1.00 | $1.64 | $1.00 | $1.50 |
| 0032 | Removable construction pavement markings (604051) | LF | 784 | $5.00 | $3.60 | $5.91 | $3.60 | $5.40 |
| 0033 | Vertical panels (604083) | EACH | 22 | $25.00 | $68.00 | $111.69 | $68.00 | $102.00 |
| 0034 | Concrete ditch paving (type B) (605012) | SY | 160 | $134.13 | $140.00 | $95.56 | $215.00 | $216.00 |
| 0035 | 18" side drain (606703) | LF | 250 | $67.38 | $75.26 | $77.53 | $85.00 | $92.40 |
| 0036 | Selected pipe bedding (606994) | CY | 20 | $2.56 | $50.00 | $168.19 | $54.09 | $60.00 |
| 0037 | 4" pipe underdrains (611008) | LF | 500 | $3.92 | $38.71 | $34.81 | $2.60 | $46.80 |
| 0038 | Underdrain outlet protectors (611013) | EACH | 2 | $350.00 | $959.28 | $4,463.15 | $567.50 | $1,152.00 |
| 0039 | Guardrail (type A) (617005) | LF | 450 | $34.00 | $32.00 | $44.68 | $32.00 | $40.80 |
| 0040 | Guardrail terminal (type 2) (617312) | EACH | 4 | $3,300.00 | $3,515.00 | $4,336.39 | $3,515.00 | $3,960.00 |
| 0041 | Thrie beam guardrail terminal (617332) | EACH | 4 | $2,500.00 | $2,315.00 | $3,285.14 | $2,315.00 | $3,000.00 |
| 0042 | Wire fence (type C) (619027) | LF | 3,280 | $6.86 | $8.50 | $11.17 | $6.86 | $10.20 |
| 0043 | 16' steel gates (619332) | EACH | 8 | $785.00 | $800.00 | $1,051.24 | $785.00 | $960.00 |
| 0044 | Lime (620001) | TON | 9 | $45.00 | $90.00 | $118.26 | $45.00 | $108.00 |
| 0045 | Seeding (620011) | ACRE | 4.73 | $1,286.29 | $1,500.00 | $1,971.09 | $1,286.29 | $1,800.00 |
| 0046 | Mulch cover (620022) | ACRE | 22.02 | $1,118.47 | $900.00 | $1,314.06 | $1,118.47 | $1,200.00 |
| 0047 | Water (620030) | MGAL | 836.10 | $10.00 | $10.00 | $13.14 | $10.00 | $12.00 |
| 0048 | Temporary seeding (621001) | ACRE | 17.29 | $786.29 | $700.00 | $985.54 | $786.29 | $900.00 |
| 0049 | Silt fence (621021) | LF | 5,876 | $3.38 | $3.50 | $4.63 | $3.38 | $4.20 |
| 0050 | Sediment removal and disposal (621111) | CY | 260 | $1.46 | $30.73 | $4.17 | $4.23 | $39.60 |
| 0051 | Rock ditch checks (621151) | CY | 66 | $103.04 | $71.75 | $60.57 | $105.00 | $88.80 |
| 0052 | Filter sock (18") (621169) | LF | 351 | $13.86 | $14.60 | $19.18 | $13.86 | $18.00 |
| 0053 | Wattle (20") (621173) | LF | 180 | $13.86 | $10.00 | $13.14 | $13.86 | $15.00 |
| 0054 | Second seeding application (623001) | ACRE | 4.73 | $475.00 | $350.00 | $459.92 | $475.00 | $420.00 |
| 0055 | Solid sodding (624001) | SY | 71 | $13.82 | $10.60 | $13.93 | $9.68 | $13.20 |
| 0056 | Erosion control matting (class 3) (626003) | SY | 471 | $6.35 | $8.00 | $10.51 | $6.35 | $10.20 |
| 0057 | Roadway construction control (635001) | LS | 1 | $124,405 | $14,500 | $50,218 | $55,000 | $42,000 |
| 0058 | Bridge construction control (636001) | LS | 1 | $9,142.89 | $70,000 | $88,929 | $50,000 | $66,000 |
| 0059 | Mailboxes (637001) | EACH | 2 | $69.16 | $60.00 | $98.55 | $60.00 | $90.00 |
| 0060 | Mailbox supports (single) (637017) | EACH | 2 | $184.43 | $160.00 | $262.81 | $160.00 | $240.00 |
| 0061 | Centerline rumble stripes in asphalt roadways (642102) | LF | 2,046 | $0.30 | $3.00 | $1.69 | $0.16 | $4.76 |
| 0062 | Thermoplastic pavement marking white (6") (719002) | LF | 4,884 | $0.92 | $1.08 | $1.77 | $1.08 | $1.62 |
| 0063 | Thermoplastic pavement marking yellow (6") (719102) | LF | 4,880 | $0.92 | $1.08 | $1.77 | $1.08 | $1.62 |
| 0064 | Raised pavement markers (type II) (721002) | EACH | 31 | $15.00 | $40.00 | $65.70 | $40.00 | $60.00 |
| 0065 | Temporary impact attenuation barrier (731071) | EACH | 3 | $2,718.76 | $11,800 | $11,169 | $6,800.00 | $12,520 |
| 0066 | Temporary impact attenuation barrier (repair) (731072) | EACH | 3 | $551.18 | $800.00 | $1,314.06 | $800.00 | $1,200.00 |
| 0067 | Unclassified excavation for structures-bridge (801001) | CY | 475 | $299.00 | $250.00 | $69.67 | $240.00 | $97.01 |
| 0068 | Class S concrete-bridge (802112) | CY | 276.90 | $881.11 | $1,525.00 | $1,306.61 | $1,585.00 | $2,164.70 |
| 0069 | Class S(AE) concrete-bridge (802122) | CY | 359.70 | $1,140.09 | $1,350.00 | $1,624.96 | $1,830.00 | $2,209.60 |
| 0070 | Prestressed concrete beams (type III) (802599) | LF | 967.50 | $353.92 | $525.00 | $434.70 | $535.00 | $658.04 |
| 0071 | Class 2 protective surface treatment (803004) | SY | 1,052.60 | $3.19 | $8.00 | $5.23 | $10.70 | $9.30 |
| 0072 | Reinforcing steel-roadway (grade 60) (804003) | LB | 19,160 | $1.50 | $2.00 | $1.35 | $2.25 | $2.07 |
| 0073 | Reinforcing steel-bridge (grade 60) (804013) | LB | 45,030 | $2.00 | $2.00 | $1.72 | $2.05 | $1.86 |
| 0074 | Epoxy coated reinforcing steel (grade 60) (804023) | LB | 82,920 | $1.89 | $1.85 | $1.79 | $2.15 | $2.32 |
| 0075 | Steel piling (HP 12X53) (805022) | LF | 470 | $178.62 | $183.00 | $136.84 | $185.00 | $224.90 |
| 0076 | Preboring (805504) | LF | 318 | $196.93 | $450.00 | $311.34 | $255.00 | $402.00 |
| 0077 | Elastomeric bearings (808002) | CUIN | 9,653 | $5.45 | $4.00 | $6.12 | $6.80 | $5.69 |
| 0078 | Bridge name plate (type D) (812004) | EACH | 1 | $4,405.01 | $2,000.00 | $1,210.21 | $2,760.00 | $6,600.00 |
| 0079 | Filter blanket (816003) | SY | 919 | $6.01 | $5.00 | $6.70 | $3.84 | $7.20 |
| 0080 | Dumped riprap (816111) | CY | 580 | $57.81 | $88.70 | $84.76 | $87.00 | $108.00 |
| 0081 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $173,294 | $223,000 | $167,415 | $255,000 | $243,948 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of November 4, 2026. Compiled by Mirage Metrics.