ARDOT contract 101091 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO REPLACE ONE STRUCTURE ON HIGHWAY 18 IN CRAIGHEAD COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL AND DISPOSAL ITEMS, STONE BACKFILL, EARTHWORK, AGGREGATE BASE COURSE, ACHM BINDER AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, MAINTENANCE OF TRAFFIC, MINOR DRAINAGE, EROSION CONTROL, PAVEMENT MARKING, CONSTRUCT ONE R.C. BOX CULVERT (43.0'), AND MISC. ITEMS. Let by Arkansas DOT on November 5, 2025, Craighead. 3 bids received; low bid $1,068,789 by Kesser International, Inc..

Owner
Arkansas DOT
Letting
05 NOV 2025
Pay items
46
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Kesser International, Inc.$1,068,789Low
2Robertson Contractors, Inc.$1,198,827+12%
3Richard Baughn Construction, Inc.$1,850,135+73%
ARDOT contract 101091: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Kesser International, Inc.2. Robertson Contractors, Inc.3. Richard Baughn Construction, Inc.
0001Clearing (201011)STA2$2,240.00$3,500.00$5,000.00
0002Grubbing (201111)STA2$2,240.00$3,000.00$5,000.00
0003Removal and disposal of pipe culverts (202096)EACH1$2,800.00$850.00$1,250.00
0004Removal and disposal of guardrail (202132)LF324$16.80$12.00$8.00
0005Removal and disposal of impact attenuation barrier (202143)EACH1$2,240.00$500.00$1,200.00
0006Removal of existing bridge structure (site no. 1) (205011)LS1$56,000$32,500$18,000
0007Stone backfill (207011)TON509$78.40$95.00$84.00
0008Unclassified excavation (210213)CY4,087$22.40$28.50$32.00
0009Compacted embankment (210611)CY3,284$28.00$36.10$54.00
0010Soil stabilization (210702)TON50$336.00$50.00$425.00
0011Aggregate base course (class 7) (303117)TON377$84.00$68.00$85.00
0012Tack coat (401011)GAL249$7.15$6.00$4.00
0013Mineral aggregate in achm binder course (1") (406161)TON36$454.72$220.00$730.73
0014Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402)TON2$454.72$120.00$1,200.00
0015Mineral aggregate in achm surface course (1/2") (407162)TON174$454.72$230.00$221.73
0016Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432)TON10$454.72$120.00$1,000.00
0017Cold milling asphalt pavement (412002)SY444$53.48$15.00$17.00
0018Furnishing field office (602011)EACH1$16,800$15,000$50,000
0019Maintenance of traffic (603010)LS1$28,000$55,000$125,000
0020Signs (604003)SF427$19.49$7.50$18.00
0021Barricades (604013)LF32$32.48$16.00$48.00
002218" side drain (606703)LF26$224.00$115.00$180.00
0023Selected pipe bedding (606994)CY10$44.80$95.00$40.00
00244" pipe underdrains (611008)LF250$5.60$1.00$10.00
0025Underdrain outlet protectors (611013)EACH1$784.00$1.00$875.00
0026Lime (620001)TON1$196.00$125.00$160.00
0027Seeding (620011)ACRE0.63$4,127.20$2,235.64$3,300.00
0028Mulch cover (620022)ACRE1.26$2,352.00$1,987.29$2,000.00
0029Water (620030)MGAL77.40$13.44$10.00$10.00
0030Temporary seeding (621001)ACRE0.63$2,475.20$1,387.47$1,905.00
0031Silt fence (621021)LF821$4.22$4.38$4.00
0032Sand bag ditch checks (621031)BAG198$15.59$12.29$15.00
0033Sediment basin (621071)CY100$13.44$1.00$48.00
0034Obliteration of sediment basin (621101)CY100$13.44$1.00$48.00
0035Sediment removal and disposal (621111)CY144$13.44$1.00$48.00
0036Rock ditch checks (621151)CY12$140.00$125.00$125.00
0037Second seeding application (623001)ACRE0.63$2,078.72$785.29$1,600.00
0038Solid sodding (624001)SY33$20.16$16.47$20.00
0039Roadway construction control (635001)LS1$33,600$35,000$125,000
0040Reflectorized paint pavement marking white (6") (718002)LF740$4.55$3.50$3.75
0041Reflectorized paint pavement marking yellow (6") (718102)LF740$4.55$3.50$3.75
0042Raised pavement markers (type II) (721002)EACH5$32.48$25.00$28.00
0043Unclassified excavation for structures-roadway (801101)CY137$112.00$245.00$120.00
0044Class S concrete-roadway (802012)CY257.96$1,232.00$1,785.00$2,900.00
0045Reinforcing steel-roadway (grade 60) (804003)LB40,511$2.24$2.35$3.00
0046Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$44,800$57,000$75,000
ARDOT contract 101091: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of November 5, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy