ARDOT contract A40053 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY AND SCRUB SEAL APPROXIMATELY 6.142 MILES OF HIGHWAY 186 IN FRANKLIN COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, TRENCHING AND SHOULDER PREPARATION, AGGREGATE BASE COURSE, ASPHALT SURFACE TREATMENT, REJUVENATING EMULSIFIED ASPHALT, ACHM BINDER AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, EROSION CONTROL ITEMS, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on November 5, 2025, Franklin. 5 bids received; low bid $2,865,278 by Emery Sapp & Sons, Inc..
- Owner
- Arkansas DOT
- Letting
- 05 NOV 2025
- Pay items
- 33
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Emery Sapp & Sons, Inc. | $2,865,278 | Low |
| 2 | Blackstone Construction, LLC | $3,003,340 | +5.0% |
| 3 | Forsgren, Inc. | $3,120,811 | +9.0% |
| 4 | Apac-Central, Inc. | $3,494,999 | +22% |
| 5 | Robinson Construction, LLC | $3,732,684 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Emery Sapp & Sons, Inc. | 2. Blackstone Construction, LLC | 3. Forsgren, Inc. | 4. Apac-Central, Inc. | 5. Robinson Construction, LLC |
|---|---|---|---|---|---|---|---|---|
| 0001 | Removal and disposal of curb and gutter (202003) | LF | 100 | $58.50 | $30.00 | $7.25 | $20.00 | $25.00 |
| 0002 | Removal and disposal of approach gutters (202052) | EACH | 4 | $3,398.74 | $3,300.00 | $1,800.00 | $4,000.00 | $250.00 |
| 0003 | Removal and disposal of guardrail (202132) | LF | 1,600 | $14.29 | $12.61 | $6.50 | $14.00 | $6.00 |
| 0004 | Trenching and shoulder preparation (215011) | STA | 233 | $196.55 | $500.00 | $300.00 | $430.00 | $355.00 |
| 0005 | Aggregate base course (class 7) (303117) | TON | 2,722 | $37.58 | $39.12 | $36.00 | $53.00 | $55.00 |
| 0006 | Tack coat (401011) | GAL | 31,846 | $3.23 | $0.01 | $3.25 | $3.25 | $4.55 |
| 0007 | Mineral aggregate in asphalt surface treatment (class 4) (402114) | TON | 1,238 | $64.12 | $109.00 | $114.50 | $110.00 | $185.00 |
| 0008 | Rejuvenating emulsified asphalt (CMS-1PC) (402501) | GAL | 33,016 | $4.89 | $5.89 | $6.20 | $6.50 | $6.25 |
| 0009 | Mineral aggregate in achm binder course (1") (406161) | TON | 2,179 | $103.60 | $18.81 | $115.90 | $121.00 | $145.00 |
| 0010 | Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402) | TON | 96 | $120.00 | $2,000.00 | $120.00 | $120.00 | $128.00 |
| 0011 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 14,246 | $109.91 | $104.26 | $110.20 | $120.00 | $122.00 |
| 0012 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 909 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 0013 | Cold milling asphalt pavement (412002) | SY | 1,511 | $3.21 | $5.00 | $8.65 | $7.75 | $6.55 |
| 0014 | Achm patching of existing roadway (415011) | TON | 750 | $128.44 | $200.00 | $155.00 | $165.00 | $245.00 |
| 0015 | Approach gutters (504264) | CY | 34.32 | $566.46 | $1,700.00 | $1,600.00 | $2,100.00 | $1,120.00 |
| 0016 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $36,674 | $143,016 | $67,000 | $165,000 | $177,000 |
| 0017 | Maintenance of traffic (603009) | LS | 1 | $33,653 | $30,000 | $85,000 | $72,270 | $40,000 |
| 0018 | Signs (604003) | SF | 1,169 | $12.46 | $11.00 | $11.55 | $11.92 | $14.20 |
| 0019 | Traffic drums (604023) | EACH | 73 | $67.97 | $60.00 | $63.00 | $65.00 | $81.35 |
| 0020 | Construction pavement markings (604041) | LF | 243,270 | $0.23 | $0.20 | $0.21 | $0.22 | $0.28 |
| 0021 | Guardrail (type A) (617005) | LF | 1,100 | $43.99 | $38.83 | $40.80 | $42.07 | $55.00 |
| 0022 | Guardrail terminal (type 2) (617312) | EACH | 8 | $4,269.75 | $3,768.82 | $3,960.00 | $4,083.04 | $4,855.00 |
| 0023 | Thrie beam guardrail terminal (617332) | EACH | 4 | $3,121.40 | $2,755.20 | $2,900.00 | $2,984.91 | $3,582.00 |
| 0024 | Sand bag ditch checks (621031) | BAG | 25 | $86.37 | $20.12 | $19.20 | $30.23 | $155.00 |
| 0025 | Wattle (20") (621173) | LF | 200 | $12.98 | $7.12 | $6.80 | $14.51 | $30.00 |
| 0026 | Mailboxes (637001) | EACH | 16 | $56.65 | $50.00 | $52.50 | $54.17 | $110.00 |
| 0027 | Mailbox supports (single) (637017) | EACH | 16 | $226.58 | $200.00 | $210.00 | $216.67 | $265.00 |
| 0028 | Portable traffic signal system - actuated (701603) | WEEK | 4 | $1,529.43 | $1,350.00 | $1,425.00 | $1,462.55 | $1,800.00 |
| 0029 | Reflectorized paint pavement marking white (6") (718002) | LF | 65,683 | $0.23 | $0.20 | $0.21 | $0.22 | $0.31 |
| 0030 | Reflectorized paint pavement marking white (12") (718005) | LF | 50 | $11.33 | $10.00 | $10.50 | $10.83 | $13.45 |
| 0031 | Reflectorized paint pavement marking yellow (6") (718102) | LF | 55,952 | $0.23 | $0.20 | $0.21 | $0.22 | $0.26 |
| 0032 | Raised pavement markers (type II) (721002) | EACH | 407 | $7.93 | $7.00 | $7.35 | $7.58 | $9.42 |
| 0033 | Reinforcing steel-roadway (grade 60) (804003) | LB | 3,068 | $3.40 | $3.00 | $2.35 | $3.25 | $5.10 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of November 5, 2025. Compiled by Mirage Metrics.