CDOT contract C25624 bid tabulation
The R1 Expansion Joint Repairs at Railroads project includes the removal and replacement of expansion devices, joint repairs, deck repairs, concrete sealing, and slope paving and drainage repairs. The project locations include the I-25 exit to I-70; I-225 over Smith Road; and Buckley Road over I-76. Let by Colorado DOT on February 6, 2025, Adams and Denver, Region 1. 4 bids received; low bid $2,684,444 by Native Sun Materials Inc, -23% against the engineer's estimate of $3,500,000.
- Owner
- Colorado DOT
- Letting
- 06 FEB 2025
- Pay items
- 57
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Native Sun Materials Inc | $2,684,444 | Low | -23% |
| 2 | Abco Contracting, Inc. | $2,894,147 | +8.0% | -17% |
| 3 | Myers & Sons Construction, LLC | $2,903,428 | +8.0% | -17% |
| 4 | Structures, Inc. | $3,171,471 | +18% | -9.0% |
Engineer's estimate: $3,500,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Native Sun Materials Inc | 2. Abco Contracting, Inc. | 3. Myers & Sons Construction, LLC | 4. Structures, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Removal of slope and ditch paving (202-00026) | SY | 359 | $13.88 | $15.79 | $80.00 | $35.00 | $50.90 |
| 2 | Removal of pipe (202-00035) | LF | 129 | $53.70 | $29.99 | $65.00 | $35.00 | $25.47 |
| 3 | Removal of portions of present structure (class 2) (202-00453) | SY | 324 | $400.00 | $393.62 | $440.00 | $250.00 | $469.56 |
| 4 | Removal of portions of present structure (class 3) (202-00460) | SY | 33 | $1,500.00 | $515.31 | $770.00 | $500.00 | $503.26 |
| 5 | Removal of expansion device (202-00504) | LF | 609 | $500.00 | $366.26 | $310.00 | $500.00 | $415.28 |
| 6 | Clean inlet (202-04010) | EACH | 5 | $1,351.08 | $1,380.00 | $1,650.00 | $1,500.00 | $1,895.30 |
| 7 | Potholing (203-01597) | HR | 10 | $300.00 | $575.00 | $440.00 | $200.00 | $317.98 |
| 8 | Structure excavation (206-00000) | CY | 87 | $106.66 | $85.61 | $270.00 | $70.00 | $112.58 |
| 9 | Structure backfill (class 2) (206-00200) | CY | 274 | $33.21 | $78.84 | $170.00 | $110.00 | $669.05 |
| 10 | Aggregate bag (208-00035) | LF | 50 | $15.26 | $25.30 | $30.00 | $10.00 | $15.87 |
| 11 | Pre-fabricated concrete washout structure (type 1) (208-00046) | EACH | 3 | $2,500.00 | $2,875.00 | $3,900.00 | $5,000.00 | $2,579.93 |
| 12 | Storm drain inlet protection (type II) (208-00054) | EACH | 5 | $273.84 | $316.25 | $340.00 | $350.00 | $380.36 |
| 13 | Removal and disposal of sediment (labor) (208-00103) | HR | 50 | $72.61 | $189.75 | $55.00 | $45.00 | $51.78 |
| 14 | Removal and disposal of sediment (equipment) (208-00105) | HR | 50 | $146.10 | $189.75 | $100.00 | $150.00 | $110.06 |
| 15 | Sweeping (sediment removal) (208-00106) | HR | 40 | $148.41 | $189.75 | $320.00 | $225.00 | $113.13 |
| 16 | Removal of trash (208-00107) | HR | 20 | $123.27 | $189.75 | $70.00 | $45.00 | $89.15 |
| 17 | 4 inch drilled hole (211-00136) | LF | 69 | $200.00 | $109.25 | $195.00 | $70.00 | $81.15 |
| 18 | Patch existing drill hole (211-00150) | EACH | 69 | $200.00 | $109.25 | $195.00 | $70.00 | $37.19 |
| 19 | Wildlife biologist (240-00000) | HR | 40 | $140.83 | $189.75 | $330.00 | $200.00 | $176.55 |
| 20 | Removal of nests (240-00010) | HR | 40 | $174.29 | $189.75 | $315.00 | $180.00 | $187.55 |
| 21 | Polyurethane slab jacking (412-05100) | LB | 1,000 | $20.00 | $18.09 | $16.00 | $20.00 | $25.47 |
| 22 | Riprap (12 inch) (506-00212) | CY | 22 | $200.00 | $214.00 | $540.00 | $400.00 | $263.94 |
| 23 | Concrete slope and ditch paving (reinforced) (507-00100) | CY | 45 | $1,415.95 | $1,288.00 | $1,800.00 | $1,400.00 | $1,670.30 |
| 24 | Concrete sealer (515-00400) | SY | 11,208 | $12.00 | $10.63 | $14.00 | $9.00 | $14.33 |
| 25 | Bridge expansion device (0-4 inch) (518-01004) | LF | 609 | $1,000.00 | $630.32 | $645.00 | $900.00 | $568.34 |
| 26 | Sawing and sealing bridge joint (518-03000) | LF | 609 | $500.00 | $26.45 | $35.00 | $25.00 | $46.11 |
| 27 | Concrete class DR (601-03057) | CY | 125 | $3,000.00 | $1,822.75 | $2,800.00 | $3,000.00 | $2,832.69 |
| 28 | Galvanic anodes (601-51005) | EACH | 1,782 | $27.00 | $65.78 | $27.00 | $35.00 | $34.62 |
| 29 | Reinforcing steel (epoxy coated) (602-00020) | LB | 8,254 | $5.00 | $3.12 | $4.00 | $3.00 | $2.72 |
| 30 | 10 inch galvanized pipe (619-30800) | LF | 4 | $120.00 | $592.25 | $880.00 | $750.00 | $688.34 |
| 31 | Sanitary facility (620-00020) | EACH | 2 | $2,648.74 | $1,897.50 | $2,290.00 | $8,000.00 | $2,310.85 |
| 32 | Mobilization (626-00000) | LS | 1 | $327,147 | $142,352 | $345,000 | $290,000 | $560,033 |
| 33 | Public information management (tier III) (626-01113) | DAY | 142 | $80.23 | $151.80 | $67.00 | $85.00 | $62.15 |
| 34 | Modified epoxy pavement marking (627-00008) | GAL | 28 | $475.00 | $879.18 | $875.00 | $695.00 | $339.00 |
| 35 | Pavement marking paint (high build)(temporary) (627-00016) | GAL | 91 | $175.00 | $309.93 | $308.00 | $245.00 | $80.25 |
| 36 | Preformed plastic pavement marking (type I)(inlaid) (627-01010) | SF | 1,017 | $24.00 | $40.48 | $40.00 | $32.00 | $39.55 |
| 37 | Preformed plastic pavement marking (contrast)(inlaid) (627-01011) | SF | 350 | $24.00 | $40.48 | $40.00 | $32.00 | $50.85 |
| 38 | Flagging (630-00000) | HR | 40 | $80.00 | $94.88 | $48.00 | $49.00 | $50.85 |
| 39 | Uniformed traffic control (630-00003) | HR | 1,322 | $150.00 | $151.80 | $167.00 | $125.00 | $133.75 |
| 40 | Uniformed traffic control (vehicle) (630-00006) | HR | 1,322 | $30.00 | $151.80 | $44.00 | $25.00 | $28.25 |
| 41 | Traffic control inspection (630-00007) | DAY | 64 | $500.00 | $316.25 | $415.00 | $175.00 | $339.00 |
| 42 | Traffic control management (630-00012) | DAY | 128 | $2,000.00 | $1,644.50 | $1,910.00 | $1,600.00 | $1,569.64 |
| 43 | Uniformed traffic control coordination (630-00015) | HR | 10 | $30.98 | $151.80 | $20.00 | $5.00 | $56.50 |
| 44 | Flashing beacon (portable) (630-80001) | EACH | 15 | $1,000.00 | $695.75 | $1,260.00 | $850.00 | $1,695.00 |
| 45 | Barricade (type 3 M-A) (temporary) (630-80335) | EACH | 25 | $114.02 | $398.48 | $95.00 | $275.00 | $452.00 |
| 46 | Construction traffic sign (panel size A) (630-80341) | EACH | 10 | $47.64 | $94.88 | $32.00 | $55.00 | $113.00 |
| 47 | Construction traffic sign (panel size B) (630-80342) | EACH | 56 | $63.59 | $94.88 | $38.00 | $85.00 | $339.00 |
| 48 | Construction traffic sign (panel size C) (630-80343) | EACH | 6 | $73.52 | $107.53 | $44.00 | $100.00 | $452.00 |
| 49 | Construction traffic sign (special) (630-80344) | SF | 300 | $80.00 | $28.46 | $27.00 | $18.50 | $28.25 |
| 50 | Vertical panel (630-80350) | EACH | 6 | $35.12 | $44.28 | $13.00 | $27.50 | $50.85 |
| 51 | Portable message sign panel (630-80355) | EACH | 4 | $5,200.09 | $13,915 | $5,115.00 | $4,250.00 | $11,300 |
| 52 | Advance warning flashing or sequencing arrow panel (C type) (630-80358) | EACH | 4 | $1,189.59 | $2,530.00 | $2,065.00 | $1,975.00 | $1,605.00 |
| 53 | Drum channelizing device (630-80360) | EACH | 250 | $36.93 | $44.28 | $15.00 | $35.00 | $84.75 |
| 54 | Drum channelizing device (with light) (flashing) (630-80363) | EACH | 50 | $40.21 | $56.93 | $22.00 | $55.00 | $85.60 |
| 55 | Traffic cone (630-80380) | EACH | 300 | $9.10 | $18.98 | $15.00 | $18.00 | $26.75 |
| 56 | Mobile attenuator (630-85041) | DAY | 168 | $1,100.00 | $917.13 | $600.01 | $600.00 | $588.50 |
| 57 | Night work lighting (632-00000) | LS | 1 | $100,000 | $31,625 | $24,000 | $162,000 | $52,714 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of February 6, 2025. Compiled by Mirage Metrics.