CDOT contract C25624 bid tabulation

The R1 Expansion Joint Repairs at Railroads project includes the removal and replacement of expansion devices, joint repairs, deck repairs, concrete sealing, and slope paving and drainage repairs. The project locations include the I-25 exit to I-70; I-225 over Smith Road; and Buckley Road over I-76. Let by Colorado DOT on February 6, 2025, Adams and Denver, Region 1. 4 bids received; low bid $2,684,444 by Native Sun Materials Inc, -23% against the engineer's estimate of $3,500,000.

Owner
Colorado DOT
Letting
06 FEB 2025
Pay items
57
Data through
10 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Native Sun Materials Inc$2,684,444Low-23%
2Abco Contracting, Inc.$2,894,147+8.0%-17%
3Myers & Sons Construction, LLC$2,903,428+8.0%-17%
4Structures, Inc.$3,171,471+18%-9.0%
CDOT contract C25624: bids by rank

Engineer's estimate: $3,500,000.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Native Sun Materials Inc2. Abco Contracting, Inc.3. Myers & Sons Construction, LLC4. Structures, Inc.
1Removal of slope and ditch paving (202-00026)SY359$13.88$15.79$80.00$35.00$50.90
2Removal of pipe (202-00035)LF129$53.70$29.99$65.00$35.00$25.47
3Removal of portions of present structure (class 2) (202-00453)SY324$400.00$393.62$440.00$250.00$469.56
4Removal of portions of present structure (class 3) (202-00460)SY33$1,500.00$515.31$770.00$500.00$503.26
5Removal of expansion device (202-00504)LF609$500.00$366.26$310.00$500.00$415.28
6Clean inlet (202-04010)EACH5$1,351.08$1,380.00$1,650.00$1,500.00$1,895.30
7Potholing (203-01597)HR10$300.00$575.00$440.00$200.00$317.98
8Structure excavation (206-00000)CY87$106.66$85.61$270.00$70.00$112.58
9Structure backfill (class 2) (206-00200)CY274$33.21$78.84$170.00$110.00$669.05
10Aggregate bag (208-00035)LF50$15.26$25.30$30.00$10.00$15.87
11Pre-fabricated concrete washout structure (type 1) (208-00046)EACH3$2,500.00$2,875.00$3,900.00$5,000.00$2,579.93
12Storm drain inlet protection (type II) (208-00054)EACH5$273.84$316.25$340.00$350.00$380.36
13Removal and disposal of sediment (labor) (208-00103)HR50$72.61$189.75$55.00$45.00$51.78
14Removal and disposal of sediment (equipment) (208-00105)HR50$146.10$189.75$100.00$150.00$110.06
15Sweeping (sediment removal) (208-00106)HR40$148.41$189.75$320.00$225.00$113.13
16Removal of trash (208-00107)HR20$123.27$189.75$70.00$45.00$89.15
174 inch drilled hole (211-00136)LF69$200.00$109.25$195.00$70.00$81.15
18Patch existing drill hole (211-00150)EACH69$200.00$109.25$195.00$70.00$37.19
19Wildlife biologist (240-00000)HR40$140.83$189.75$330.00$200.00$176.55
20Removal of nests (240-00010)HR40$174.29$189.75$315.00$180.00$187.55
21Polyurethane slab jacking (412-05100)LB1,000$20.00$18.09$16.00$20.00$25.47
22Riprap (12 inch) (506-00212)CY22$200.00$214.00$540.00$400.00$263.94
23Concrete slope and ditch paving (reinforced) (507-00100)CY45$1,415.95$1,288.00$1,800.00$1,400.00$1,670.30
24Concrete sealer (515-00400)SY11,208$12.00$10.63$14.00$9.00$14.33
25Bridge expansion device (0-4 inch) (518-01004)LF609$1,000.00$630.32$645.00$900.00$568.34
26Sawing and sealing bridge joint (518-03000)LF609$500.00$26.45$35.00$25.00$46.11
27Concrete class DR (601-03057)CY125$3,000.00$1,822.75$2,800.00$3,000.00$2,832.69
28Galvanic anodes (601-51005)EACH1,782$27.00$65.78$27.00$35.00$34.62
29Reinforcing steel (epoxy coated) (602-00020)LB8,254$5.00$3.12$4.00$3.00$2.72
3010 inch galvanized pipe (619-30800)LF4$120.00$592.25$880.00$750.00$688.34
31Sanitary facility (620-00020)EACH2$2,648.74$1,897.50$2,290.00$8,000.00$2,310.85
32Mobilization (626-00000)LS1$327,147$142,352$345,000$290,000$560,033
33Public information management (tier III) (626-01113)DAY142$80.23$151.80$67.00$85.00$62.15
34Modified epoxy pavement marking (627-00008)GAL28$475.00$879.18$875.00$695.00$339.00
35Pavement marking paint (high build)(temporary) (627-00016)GAL91$175.00$309.93$308.00$245.00$80.25
36Preformed plastic pavement marking (type I)(inlaid) (627-01010)SF1,017$24.00$40.48$40.00$32.00$39.55
37Preformed plastic pavement marking (contrast)(inlaid) (627-01011)SF350$24.00$40.48$40.00$32.00$50.85
38Flagging (630-00000)HR40$80.00$94.88$48.00$49.00$50.85
39Uniformed traffic control (630-00003)HR1,322$150.00$151.80$167.00$125.00$133.75
40Uniformed traffic control (vehicle) (630-00006)HR1,322$30.00$151.80$44.00$25.00$28.25
41Traffic control inspection (630-00007)DAY64$500.00$316.25$415.00$175.00$339.00
42Traffic control management (630-00012)DAY128$2,000.00$1,644.50$1,910.00$1,600.00$1,569.64
43Uniformed traffic control coordination (630-00015)HR10$30.98$151.80$20.00$5.00$56.50
44Flashing beacon (portable) (630-80001)EACH15$1,000.00$695.75$1,260.00$850.00$1,695.00
45Barricade (type 3 M-A) (temporary) (630-80335)EACH25$114.02$398.48$95.00$275.00$452.00
46Construction traffic sign (panel size A) (630-80341)EACH10$47.64$94.88$32.00$55.00$113.00
47Construction traffic sign (panel size B) (630-80342)EACH56$63.59$94.88$38.00$85.00$339.00
48Construction traffic sign (panel size C) (630-80343)EACH6$73.52$107.53$44.00$100.00$452.00
49Construction traffic sign (special) (630-80344)SF300$80.00$28.46$27.00$18.50$28.25
50Vertical panel (630-80350)EACH6$35.12$44.28$13.00$27.50$50.85
51Portable message sign panel (630-80355)EACH4$5,200.09$13,915$5,115.00$4,250.00$11,300
52Advance warning flashing or sequencing arrow panel (C type) (630-80358)EACH4$1,189.59$2,530.00$2,065.00$1,975.00$1,605.00
53Drum channelizing device (630-80360)EACH250$36.93$44.28$15.00$35.00$84.75
54Drum channelizing device (with light) (flashing) (630-80363)EACH50$40.21$56.93$22.00$55.00$85.60
55Traffic cone (630-80380)EACH300$9.10$18.98$15.00$18.00$26.75
56Mobile attenuator (630-85041)DAY168$1,100.00$917.13$600.01$600.00$588.50
57Night work lighting (632-00000)LS1$100,000$31,625$24,000$162,000$52,714
CDOT contract C25624: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

Every contract let that day: CDOT letting of February 6, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy