CDOT contract C25972 bid tabulation
Timber bridge retrofit project on 21 structures located in CDOT Region 2 on CO 9B, US 24A, US 24G, CO 67C, AND US 285D. Let by Colorado DOT on January 16, 2025, El Paso, Park and Teller, Region 2. 7 bids received; low bid $1,798,366 by Lobato Construction, LLC, -38% against the engineer's estimate of $2,900,000.
- Owner
- Colorado DOT
- Letting
- 16 JAN 2025
- Pay items
- 30
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Lobato Construction, LLC | $1,798,366 | Low | -38% |
| 2 | Structures, Inc. | $2,242,122 | +25% | -23% |
| 3 | Myers & Sons Construction, LLC | $2,269,053 | +26% | -22% |
| 4 | Tricon 2, LLC | $2,995,000 | +67% | +3.0% |
| 5 | Abco Contracting, Inc. | $3,272,287 | +82% | +13% |
| 6 | Native Sun Materials Inc | $3,518,961 | +96% | +21% |
| 7 | W.W. Clyde & Co. | $4,227,621 | +135% | +46% |
Engineer's estimate: $2,900,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Lobato Construction, LLC | 2. Structures, Inc. | 3. Myers & Sons Construction, LLC | 4. Tricon 2, LLC | 5. Abco Contracting, Inc. | 6. Native Sun Materials Inc |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removal of asphalt mat (202-00220) | SY | 281 | $130.00 | $35.00 | $50.07 | $100.00 | $72.50 | $67.00 | $23.48 |
| 2 | Removal of fence (202-01000) | LF | 300 | $50.00 | $10.00 | $7.43 | $5.00 | $2.75 | $30.00 | $11.03 |
| 3 | Sawing asphalt material (10 inch) (202-05030) | LF | 352 | $20.00 | $15.00 | $12.70 | $15.00 | $10.00 | $25.00 | $11.03 |
| 4 | Unclassified excavation (complete in place) (203-00010) | CY | 640 | $80.00 | $75.00 | $89.61 | $80.00 | $35.00 | $140.00 | $51.39 |
| 5 | Erosion log type 2 (18 inch) (208-00009) | LF | 3,000 | $13.43 | $13.00 | $14.50 | $15.00 | $16.25 | $15.00 | $12.12 |
| 6 | Pre-fabricated vehicle tracking pad (208-00075) | EACH | 42 | $1,000.00 | $1,500.00 | $494.99 | $500.00 | $1,000.00 | $1,000.00 | $2,657.03 |
| 7 | Construction mat (208-00082) | SF | 4,000 | $25.00 | $30.00 | $13.41 | $10.00 | $19.00 | $33.00 | $7.55 |
| 8 | Removal and disposal of sediment (labor) (208-00103) | HR | 60 | $60.58 | $100.00 | $49.55 | $40.00 | $35.00 | $60.00 | $160.28 |
| 9 | Removal and disposal of sediment (equipment) (208-00105) | HR | 60 | $151.37 | $175.00 | $115.88 | $65.00 | $100.00 | $115.00 | $160.28 |
| 10 | Erosion control management (208-00207) | DAY | 60 | $350.04 | $150.00 | $279.27 | $100.00 | $250.00 | $490.00 | $441.00 |
| 11 | Water control (208-00400) | LS | 1 | $50,000 | $45,000 | $39,031 | $15,000 | $18,750 | $50,000 | $145,530 |
| 12 | Reset fence (210-01000) | LF | 300 | $50.00 | $30.00 | $17.10 | $5.00 | $37.50 | $35.00 | $29.77 |
| 13 | Seeding (native) broadcast (212-00708) | ACRE | 10.50 | $3,000.00 | $2,200.00 | $983.13 | $1,800.00 | $3,300.00 | $2,750.00 | $6,214.13 |
| 14 | Removal of nests (240-00010) | HR | 200 | $172.66 | $185.00 | $52.91 | $45.00 | $40.00 | $165.00 | $203.96 |
| 15 | Aggregate base course (class 6) (304-06007) | CY | 233 | $170.00 | $135.00 | $108.07 | $275.00 | $100.00 | $285.00 | $159.94 |
| 16 | Hot mix asphalt (patching) (asphalt) (403-00720) | TON | 153.64 | $400.00 | $300.00 | $544.87 | $600.00 | $340.00 | $1,255.00 | $850.91 |
| 17 | Structural steel (install only) (509-00003) | LB | 594,813 | $2.71 | $1.10 | $2.04 | $1.98 | $3.00 | $2.55 | $3.53 |
| 18 | Fence (plastic) (607-11525) | LF | 1,142 | $2.95 | $5.00 | $4.05 | $2.00 | $4.44 | $12.00 | $6.84 |
| 19 | Sanitary facility (620-00020) | EACH | 1 | $3,407.62 | $15,000 | $5,852.00 | $5,000.00 | $6,250.00 | $3,125.00 | $6,945.75 |
| 20 | Mobilization (626-00000) | LS | 1 | $204,072 | $175,000 | $198,437 | $225,000 | $271,455 | $450,000 | $218,556 |
| 21 | Public information services (tier IV) (626-01104) | LS | 1 | $15,000 | $12,500 | $9,844.00 | $18,000 | $10,000 | $10,300 | $9,591.75 |
| 22 | Flagging (630-00000) | HR | 4,000 | $40.00 | $41.00 | $40.13 | $35.00 | $48.00 | $52.00 | $48.51 |
| 23 | Uniformed traffic control (630-00003) | HR | 200 | $200.00 | $160.00 | $160.50 | $160.00 | $287.00 | $195.00 | $181.91 |
| 24 | Traffic control inspection (630-00007) | DAY | 58 | $500.00 | $250.00 | $195.55 | $225.00 | $375.00 | $260.00 | $242.55 |
| 25 | Traffic control management (630-00012) | DAY | 116 | $1,750.00 | $1,300.00 | $1,311.67 | $1,600.00 | $1,705.00 | $1,560.00 | $1,455.30 |
| 26 | Construction traffic sign (panel size A) (630-80341) | EACH | 28 | $130.00 | $75.00 | $53.50 | $120.00 | $79.00 | $65.00 | $60.64 |
| 27 | Construction information sign (630-80348) | EACH | 4 | $118.28 | $75.00 | $53.50 | $175.00 | $122.00 | $65.00 | $60.64 |
| 28 | Vertical panel (630-80350) | EACH | 20 | $31.33 | $75.00 | $80.25 | $25.00 | $58.00 | $65.00 | $60.64 |
| 29 | Traffic cone (630-80380) | EACH | 40 | $9.47 | $10.00 | $8.03 | $19.75 | $21.00 | $6.00 | $6.06 |
| 30 | Mobile attenuator (630-85020) | EACH | 1 | $65,000 | $65,000 | $53,500 | $60,000 | $59,000 | $65,000 | $60,638 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of January 16, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.