FDOT contract T1927 bid tabulation

WEST MAIN ST FROM HANCHEY RD TO W OF FLORIDA AVE. Let by Florida DOT on July 30, 2025, Hardee, District 1. 6 bids received; low bid $414,963 by Garcia Civil Contractors.

Owner
Florida DOT
Letting
30 JUL 2025
Pay items
32
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Garcia Civil Contractors$414,963Low
2Alexander Design + Build, LLC$437,258+5.0%
3Blacktip Services Incorporated$458,741+11%
4National Traffic Solution, Inc$496,932+20%
5American Design Engineering Construction Inc.$507,140+22%
6Janus Construction Corp.$568,227+37%
FDOT contract T1927: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Garcia Civil Contractors2. Alexander Design + Build, LLC3. Blacktip Services Incorporated4. National Traffic Solution, Inc5. American Design Engineering Construction Inc.6. Janus Construction Corp.
0005Mobilization (0101-1)LS1$56,139$96,764$53,000$39,999$150,000$56,797
0010Maintenance of traffic (0102-1)DA1$30,310$25,700$20,000$69,999$35,000$96,294
0015Commercial material for temporary driveway maintenance (0102-3)CY188.90$43.94$64.25$15.00$149.99$35.00$115.15
0020Work zone sign (0102-60)ED2,400$0.29$0.01$0.30$0.35$2.00$0.30
0025Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED7,500$0.12$0.01$0.15$0.24$2.00$0.15
0030Portable changeable message sign, temporary (0102-99)ED228$17.25$0.01$17.00$24.50$35.00$17.63
0035Sediment barrier (0104-10-3)LF2,020$1.29$3.86$4.00$10.00$7.00$4.70
0040Inlet protection system (0104-18)EACH1$343.31$321.25$50.00$950.00$150.00$176.25
0045Clearing & grubbing (0110-1-1)ACRE1$25,427$25,700$110,000$19,500$15,000$56,450
0050Removal of existing concrete (0110-4-10)SY87$65.95$70.68$90.00$50.00$15.00$50.53
0055Regular excavation (0120-1)CY149.20$152.48$19.28$90.00$40.00$40.00$106.34
0060Embankment (0120-6)CY327.80$78.03$19.28$40.00$65.00$40.00$57.58
0065Optional base, base group 02 (0285-702)SY395$27.23$83.53$52.00$59.95$45.00$64.63
0070Superpave asphaltic conc, traffic B (0334-1-12)TN32.60$593.56$385.50$654.00$355.00$650.00$440.63
0075Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81)TN32.60$633.13$642.50$723.00$415.00$650.00$470.00
0080Pipe culvert, optional material, other shape - ellip/arch, 18"SD (0430-174218)LF33$365.21$224.88$225.00$315.00$150.00$246.75
0085Mitered end sect, optional - elliptical / arch, 18" SD (0430-984625)EACH2$4,340.20$5,782.50$1,500.00$3,950.00$4,500.00$3,525.00
0090Pipe handrail - guiderail, steel (0515-1-1)LF29$209.15$192.75$100.00$150.00$200.00$164.50
0095Concrete curb & gutter, type F (0520-1-10)LF497$46.69$32.13$30.00$65.00$45.00$70.50
0100Concrete sidewalk and driveways, 4" thick (0522-1)SY1,048$69.29$66.82$61.00$95.00$65.00$88.13
0105Concrete sidewalk and driveways, 6" thick (0522-2)SY280$103.77$93.81$79.00$105.00$75.00$114.27
0110Detectable warnings (0527-2)SF161$28.56$33.41$30.00$45.00$35.00$35.25
0115Performance turf, sod (0570-1-2)SY2,216$6.65$5.14$8.00$9.00$8.00$7.34
0120Plastic erosion mat, turf reinforced mat, type 1 (0571-1-11)SY482$5.42$25.70$5.00$9.50$6.00$14.10
0125Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH2$575.00$1,002.30$672.00$395.00$950.00$705.00
0130Single column ground sign assembly, relocate (0700-1500)EACH1$172.50$1,002.30$560.00$295.00$650.00$235.00
0135Single column ground sign assembly, remove (0700-1600)EACH2$57.50$321.24$56.00$95.00$350.00$105.75
0140Multi-column ground sign assembly, relocate (0700-2500)EACH1$575.00$3,212.50$8,960.00$4,500.00$950.00$7,050.00
0145Painted pavement markings, surface (0710-90)LS1$1,725.00$6,425.00$2,800.00$2,500.00$10,000$4,406.25
0150Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF245$6.10$6.43$7.00$2.50$5.00$8.81
0155Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF16$21.56$32.13$14.00$4.50$8.00$16.50
0160Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF195$11.79$28.27$22.00$24.00$25.00$16.50
FDOT contract T1927: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of July 30, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy