FDOT contract T1933 bid tabulation
SR 25 (US 27) FROM MP 4.478 TO MP 4.856. Let by Florida DOT on May 20, 2026, Highlands, District 1. 6 bids received; low bid $5,395,000 by Ohla USA Inc.
- Owner
- Florida DOT
- Letting
- 20 MAY 2026
- Pay items
- 75
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ohla USA Inc | $5,395,000 | Low |
| 2 | I N C USA Corporation | $6,320,278 | +17% |
| 3 | Russell Engineering, Inc. | $6,369,512 | +18% |
| 4 | Ajax Paving Industries of Florida LLC | $6,576,642 | +22% |
| 5 | Gibbs & Register, Inc. | $7,122,839 | +32% |
| 6 | The Stout Group LLC | $9,388,018 | +74% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ohla USA Inc | 2. I N C USA Corporation | 3. Russell Engineering, Inc. | 4. Ajax Paving Industries of Florida LLC | 5. Gibbs & Register, Inc. | 6. The Stout Group LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $530,000 | $630,922 | $655,013 | $434,500 | $700,000 | $930,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $360,000 | $564,611 | $555,013 | $316,978 | $35,000 | $275,000 |
| 0015 | Special detour- temporary pavement (0102-2200) | SY | 1 | $115,000 | $427,615 | $236,013 | $197,944 | $417,000 | $235,000 |
| 0020 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $75,000 | $384,797 | $536,055 | $204,519 | $207,000 | $295,000 |
| 0025 | Traffic control officer (0102-14) | HR | 3,000 | $1.15 | $40.00 | $0.01 | $109.57 | $80.00 | $115.50 |
| 0030 | Work zone sign (0102-60) | ED | 12,660 | $0.25 | $0.23 | $0.21 | $0.25 | $0.25 | $0.22 |
| 0035 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 2,600 | $1.00 | $31.58 | $33.00 | $41.06 | $37.00 | $36.75 |
| 0040 | Temporary barrier, relocate, anchored (0102-71-25) | LF | 2,538 | $1.00 | $14.66 | $14.00 | $17.01 | $16.00 | $15.75 |
| 0045 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 56,737 | $0.15 | $0.11 | $0.10 | $0.10 | $0.12 | $0.11 |
| 0050 | Temporary separator, F&I remove (0102-75-1) | LF | 3,831 | $24.50 | $23.10 | $21.00 | $25.37 | $24.00 | $21.00 |
| 0055 | Arrow board / advance warning arrow panel (0102-76) | ED | 500 | $6.00 | $5.50 | $5.00 | $6.34 | $5.50 | $5.25 |
| 0060 | Temporary crash cushion, redirective option (0102-89-1) | LO | 2 | $3,825.00 | $880.00 | $800.00 | $1,211.05 | $1,000.00 | $3,675.00 |
| 0065 | Portable changeable message sign, temporary (0102-99) | ED | 1,028 | $11.60 | $11.00 | $10.00 | $12.69 | $11.00 | $10.50 |
| 0070 | Type III barricade (0102-115) | ED | 240 | $0.45 | $0.39 | $0.35 | $0.35 | $0.40 | $0.37 |
| 0075 | Removable tape, white, solid 6" (0102-913-21) | GM | 0.39 | $14,020 | $13,200 | $10,013 | $11,534 | $11,500 | $12,600 |
| 0080 | Removable tape, yellow, solid, (0102-913-31) | GM | 0.28 | $19,285 | $18,233 | $10,013 | $11,534 | $11,500 | $12,600 |
| 0085 | Sediment barrier (0104-10-3) | LF | 3,617 | $3.15 | $3.82 | $2.36 | $1.19 | $2.00 | $4.20 |
| 0090 | Floating turbidity barrier (0104-11) | LF | 114 | $14.50 | $16.60 | $22.55 | $6.66 | $15.00 | $15.75 |
| 0095 | Staked turbidity barrier- nylon reinforced PVC (0104-12) | LF | 54 | $7.55 | $10.65 | $18.55 | $15.14 | $8.00 | $21.00 |
| 0100 | Soil tracking prevention device (0104-15) | EACH | 2 | $4,750.00 | $5,066.78 | $1,285.00 | $1,500.00 | $12,500 | $9,975.00 |
| 0105 | Inlet protection system (0104-18) | EACH | 3 | $205.00 | $191.59 | $485.00 | $272.49 | $250.00 | $157.50 |
| 0110 | Litter removal (0107-1) | ACRE | 204.50 | $1.00 | $32.01 | $25.00 | $50.00 | $150.00 | $54.60 |
| 0115 | Mowing (0107-2) | ACRE | 181.85 | $1.00 | $39.52 | $25.00 | $170.00 | $150.00 | $48.30 |
| 0120 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $158,761 | $334,000 | $158,776 | $71,115 | $185,000 | $230,000 |
| 0125 | Regular excavation (0120-1) | CY | 2,604.40 | $7.50 | $7.66 | $17.69 | $16.55 | $12.00 | $24.15 |
| 0130 | Embankment (0120-6) | CY | 26,984 | $26.50 | $10.74 | $21.00 | $34.72 | $38.00 | $68.25 |
| 0135 | Type B stabilization (0160-4) | SY | 18,627 | $9.35 | $7.23 | $4.90 | $12.23 | $6.50 | $26.25 |
| 0140 | Optional base, base group 01 (0285-701) | SY | 4,933 | $29.15 | $17.25 | $18.13 | $32.35 | $12.00 | $36.75 |
| 0145 | Optional base, base group 10 (0285-710) | SY | 10,053 | $31.50 | $26.64 | $28.55 | $41.84 | $28.00 | $52.50 |
| 0150 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 1,264 | $6.50 | $2.98 | $6.26 | $6.00 | $7.00 | $11.55 |
| 0155 | Milling existing asphalt pavement, 2 1/4" avg depth (0327-70-11) | SY | 9,712 | $2.20 | $3.01 | $3.55 | $3.38 | $4.00 | $4.20 |
| 0160 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 3,558 | $140.60 | $166.17 | $169.55 | $162.41 | $195.00 | $189.00 |
| 0165 | Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25) | TN | 968.80 | $235.80 | $258.24 | $313.00 | $296.62 | $350.00 | $262.50 |
| 0170 | Concrete class NS, gravity index 400-011 (0400-0-11) | CY | 16.60 | $2,050.00 | $1,034.57 | $720.00 | $2,306.77 | $1,650.00 | $2,817.74 |
| 0175 | Concrete class IV, culverts (0400-4-1) | CY | 403 | $1,525.00 | $1,888.30 | $1,358.00 | $1,567.62 | $2,250.00 | $3,525.00 |
| 0180 | Reinforcing steel- roadway (0415-1-1) | LB | 71,069 | $1.75 | $1.52 | $1.50 | $1.73 | $1.00 | $1.53 |
| 0185 | Inlets, DT bot, type D, <10' (0425-1541) | EACH | 1 | $7,725.00 | $8,227.48 | $6,354.00 | $7,384.02 | $6,000.00 | $10,500 |
| 0190 | Inlets, DT bot, type H, partial (0425-1585) | EACH | 2 | $7,000.00 | $16,286 | $11,097 | $6,949.14 | $19,500 | $10,500 |
| 0195 | Pipe culvert, optional material, other shape - ellip/arch, 18"SD (0430-174218) | LF | 133 | $300.00 | $232.19 | $116.00 | $154.87 | $200.00 | $189.00 |
| 0200 | Pipe culvert, opt material, round, 36"S/CD (0430-175136) | LF | 419 | $325.00 | $220.62 | $190.00 | $239.59 | $275.00 | $315.00 |
| 0205 | Pipe culvert,optional material,other shape-elip/arch, 24"S/CD (0430-175224) | LF | 78 | $350.00 | $216.30 | $156.55 | $183.19 | $250.00 | $221.60 |
| 0210 | Straight concrete endwalls, double, 0 degrees, round (0430-536200) | EACH | 2 | $8,500.00 | $11,202 | $12,769 | $19,376 | $9,000.00 | $14,499 |
| 0215 | Mitered end section, optional - elliptical / arch, 24" CD (0430-982629) | EACH | 1 | $7,000.00 | $4,918.01 | $5,685.00 | $3,258.29 | $10,000 | $4,200.00 |
| 0220 | Mitered end sect, optional - elliptical / arch, 18" SD (0430-984625) | EACH | 6 | $5,000.00 | $3,522.41 | $2,270.00 | $2,764.64 | $3,500.00 | $5,250.00 |
| 0225 | Concrete curb & gutter, type E (0520-1-7) | LF | 478 | $47.50 | $43.02 | $56.55 | $62.58 | $74.00 | $33.60 |
| 0230 | Concrete ditch pavement, 4", reinforced (0524-1-29) | SY | 28 | $126.00 | $169.38 | $133.00 | $527.55 | $150.00 | $94.50 |
| 0235 | Fencing, type B, 8.1-10.0', with barbed wire attmt (0550-10251) | LF | 10,655 | $38.00 | $35.20 | $49.55 | $36.91 | $42.00 | $33.60 |
| 0240 | Fence gate, type B, single, 0- 6.0' opening (0550-60211) | EACH | 4 | $2,625.00 | $1,540.00 | $2,455.00 | $1,614.74 | $1,350.00 | $3,675.00 |
| 0245 | Fence gate, type B, double, 18.1- 20.0' opening (0550-60224) | EACH | 6 | $4,700.00 | $3,850.00 | $6,013.00 | $4,036.84 | $3,700.00 | $1,470.00 |
| 0250 | Performance turf, sod (0570-1-2) | SY | 14,797 | $4.25 | $4.91 | $6.00 | $6.52 | $6.50 | $6.30 |
| 0255 | Performance turf, sod and shoulder treatment index (0570-1-3) | SY | 22,916 | $4.80 | $5.78 | $10.55 | $10.86 | $14.00 | $6.30 |
| 0260 | Plastic erosion mat, turf reinforced mat, type 1 (0571-1-11) | SY | 1,594 | $15.50 | $8.73 | $10.36 | $8.01 | $12.50 | $20.75 |
| 0265 | Raised pavement marker, type B (0706-1-3) | EACH | 2,271 | $6.00 | $5.50 | $4.00 | $4.56 | $4.00 | $5.25 |
| 0270 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 3.77 | $1,105.00 | $1,045.00 | $1,755.00 | $2,018.42 | $2,000.00 | $1,677.32 |
| 0275 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 60 | $2.35 | $2.20 | $1.83 | $2.08 | $2.00 | $4.20 |
| 0280 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 1.22 | $1,000.00 | $935.00 | $509.00 | $576.69 | $550.00 | $1,044.82 |
| 0285 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 2 | $116.00 | $110.00 | $42.00 | $46.14 | $45.00 | $89.25 |
| 0290 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 11 | $87.00 | $82.50 | $42.00 | $46.14 | $45.00 | $47.25 |
| 0295 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 3.66 | $1,100.00 | $1,045.00 | $1,755.00 | $2,018.42 | $2,000.00 | $1,678.62 |
| 0300 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 19 | $1.75 | $1.65 | $1.75 | $1.96 | $2.00 | $3.15 |
| 0305 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $65,917 | $65,917 | $65,917 | $65,917 | $65,917 | $65,917 |
| 0310 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 2.21 | $2,000.00 | $2,296.04 | $3,013.00 | $5,906.82 | $10,500 | $10,000 |
| 0315 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 9 | $752.85 | $753.50 | $655.00 | $749.70 | $750.00 | $682.50 |
| 0320 | Single column ground sign assembly, remove (0700-1600) | EACH | 1 | $116.25 | $110.00 | $103.00 | $149.94 | $150.00 | $105.00 |
| 0325 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 8 | $145.25 | $233.20 | $126.00 | $173.01 | $175.00 | $131.25 |
| 0330 | Tubular marker, 36" yellow (0704-1-4) | EACH | 2 | $150.57 | $143.00 | $255.00 | $288.35 | $275.00 | $210.00 |
| 0335 | Raised pavement marker, type B (0706-1-3) | EACH | 373 | $6.00 | $5.50 | $4.00 | $4.56 | $4.00 | $5.25 |
| 0340 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 471 | $3.59 | $3.41 | $4.03 | $4.61 | $5.00 | $10.50 |
| 0345 | Painted pavement markings, surface (0710-90) | LS | 1 | $9,850.00 | $9,328.66 | $18,000 | $20,524 | $22,500 | $7,875.00 |
| 0350 | Thermoplastic, standard, arrow (0711-11170) | EACH | 11 | $235.00 | $220.00 | $75.00 | $86.50 | $85.00 | $105.00 |
| 0355 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 19 | $3.50 | $3.30 | $4.90 | $5.65 | $5.50 | $7.35 |
| 0360 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.09 | $2,755.00 | $3,604.79 | $2,255.00 | $2,599.73 | $2,500.00 | $4,572.58 |
| 0365 | Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101) | GM | 1.34 | $5,815.00 | $6,727.97 | $6,813.00 | $7,851.09 | $8,000.00 | $6,809.75 |
| 0370 | Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131) | GM | 1.22 | $2,875.00 | $3,100.88 | $1,709.00 | $1,963.06 | $2,000.00 | $4,701.69 |
| 0375 | Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201) | GM | 1.13 | $5,800.00 | $6,714.43 | $6,013.00 | $6,931.84 | $7,000.00 | $6,800.92 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of May 20, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.