FDOT contract T1944 bid tabulation
HOMESTEAD AVE OVER MARSH CREEK, BRIDGE NO 074026. Let by Florida DOT on September 30, 2026, Hendry, District 1. 8 bids received; low bid $1,043,588 by Zep Construction, Inc..
- Owner
- Florida DOT
- Letting
- 30 SEP 2026
- Pay items
- 52
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Zep Construction, Inc. | $1,043,588 | Low |
| 2 | Timmons Contracting DBA Lovin Construction | $1,572,671 | +51% |
| 3 | Thomas Marine Construction, Inc. | $1,590,462 | +52% |
| 4 | Manhattan Road & Bridge Company | $1,673,096 | +60% |
| 5 | General Asphalt Company, LLC | $1,792,844 | +72% |
| 6 | Ferreira Construction Co., Inc. | $1,798,675 | +72% |
| 7 | Posillico Civil, Inc. | $1,886,953 | +81% |
| 8 | RJ Gorman Contracting LLC | $1,895,597 | +82% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Zep Construction, Inc. | 2. Timmons Contracting DBA Lovin Construction | 3. Thomas Marine Construction, Inc. | 4. Manhattan Road & Bridge Company | 5. General Asphalt Company, LLC | 6. Ferreira Construction Co., Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Conc class II, bridge superstructure (0400-2-4) | CY | 84.50 | $1,284.98 | $1,863.00 | $1,220.00 | $2,200.00 | $2,280.43 | $1,725.00 |
| 0010 | Concrete class II, approach slabs (0400-2-10) | CY | 45 | $642.40 | $1,354.00 | $1,274.00 | $1,200.00 | $1,080.91 | $750.00 |
| 0015 | Concrete class IV, bridge substructure (0400-4-5) | CY | 33.50 | $1,560.28 | $2,013.00 | $2,920.00 | $3,500.00 | $3,214.03 | $2,725.00 |
| 0020 | Bridge deck grooving (0400-7-1) | SY | 186 | $40.61 | $43.00 | $54.00 | $40.00 | $26.00 | $83.20 |
| 0025 | Plain neoprene bearing pads (0400-148) | CF | 2.70 | $2,695.07 | $2,400.00 | $2,500.00 | $5,000.00 | $3,130.40 | $4,482.00 |
| 0030 | Reinforcing steel - bridge superstructure (0415-1-4) | LB | 25,042 | $1.04 | $1.50 | $2.00 | $1.75 | $2.60 | $2.00 |
| 0035 | Reinforcing steel- bridge substructure (0415-1-5) | LB | 7,037 | $1.13 | $1.50 | $2.00 | $2.25 | $2.60 | $2.80 |
| 0040 | Reinforcing steel- approach slabs (0415-1-9) | LB | 10,568 | $1.13 | $1.50 | $2.00 | $1.75 | $2.60 | $1.90 |
| 0045 | Pile inspection, driven pile (0455-20-1) | EACH | 10 | $401.99 | $1,200.00 | $750.00 | $3,500.00 | $845.00 | $1,150.00 |
| 0050 | Prestressed concrete piling, SQ (0455-34-3) | LF | 484 | $125.94 | $257.00 | $281.00 | $140.00 | $309.40 | $490.00 |
| 0055 | Pile redrive (0455-115) | EACH | 3 | $1,349.86 | $2,000.00 | $300.00 | $1,500.00 | $2,340.00 | $1,425.00 |
| 0060 | Load test (dynamic), data collection and analysis (0455-137) | EACH | 11 | $1,121.34 | $2,150.00 | $150.00 | $575.00 | $2,080.00 | $2,532.50 |
| 0065 | Load test (dynamic), test (0455-137-2) | EACH | 3 | $540.03 | $2,150.00 | $200.00 | $605.00 | $2,184.00 | $994.90 |
| 0070 | Test piles-prestressed concrete,18" SQ (0455-143-3) | LF | 154 | $162.81 | $608.00 | $300.00 | $650.00 | $492.31 | $725.00 |
| 0075 | Bridge deck expansion joint, construction, F&I poured joint with backer rod (0458-1-11) | LF | 56 | $43.68 | $79.00 | $25.00 | $225.00 | $97.50 | $73.60 |
| 0080 | Concrete traffic railing- 36" single-slope (0521-5-13) | LF | 203 | $125.22 | $229.00 | $450.00 | $350.00 | $257.89 | $525.00 |
| 0085 | Riprap, sand-cement bags (0530-1100) | CY | 19.30 | $914.19 | $1,803.00 | $700.00 | $2,250.00 | $1,560.00 | $1,607.20 |
| 0090 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 354.90 | $94.30 | $193.00 | $145.00 | $155.00 | $198.00 | $265.00 |
| 0095 | Bedding stone (0530-74) | TN | 255 | $76.29 | $199.00 | $141.00 | $225.00 | $165.60 | $240.00 |
| 0100 | Mobilization (0101-1) | LS | 1 | $177,323 | $149,907 | $238,170 | $163,710 | $100,000 | $177,450 |
| 0105 | Maintenance of traffic (0102-1) | DA | 1 | $2,089.28 | $30,761 | $37,000 | $15,000 | $260,000 | $8,166.20 |
| 0110 | Work zone sign (0102-60) | ED | 5,700 | $0.31 | $0.28 | $0.40 | $0.35 | $0.35 | $0.40 |
| 0115 | Portable changeable message sign, temporary (0102-99) | ED | 2,428 | $10.58 | $11.00 | $12.00 | $11.15 | $12.00 | $14.20 |
| 0120 | Type III barricade (0102-115) | ED | 1,500 | $0.53 | $0.60 | $0.60 | $0.60 | $0.60 | $0.70 |
| 0125 | Sediment barrier (0104-10-3) | LF | 122 | $3.42 | $12.00 | $3.00 | $15.00 | $3.36 | $4.50 |
| 0130 | Floating turbidity barrier (0104-11) | LF | 481 | $9.95 | $13.25 | $16.00 | $10.00 | $24.00 | $15.20 |
| 0135 | Staked turbidity barrier- nylon reinforced PVC (0104-12) | LF | 44 | $11.88 | $44.00 | $6.25 | $35.00 | $27.60 | $15.50 |
| 0140 | Inlet protection system (0104-18) | EACH | 6 | $156.61 | $330.00 | $190.00 | $500.00 | $204.00 | $191.40 |
| 0145 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $6,629.27 | $54,530 | $41,500 | $15,000 | $22,200 | $38,000 |
| 0150 | Regular excavation (0120-1) | CY | 1,059.80 | $31.39 | $36.00 | $20.00 | $60.00 | $32.40 | $20.50 |
| 0155 | Embankment (0120-6) | CY | 703.90 | $26.55 | $56.00 | $49.00 | $55.00 | $31.20 | $12.50 |
| 0160 | Type B stabilization (0160-4) | SY | 1,059 | $28.74 | $46.00 | $37.00 | $45.00 | $13.20 | $28.10 |
| 0165 | Optional base, base group 03 (0285-703) | SY | 951 | $49.58 | $50.00 | $52.00 | $41.50 | $59.71 | $27.10 |
| 0170 | Superpave asphaltic conc, traffic B (0334-1-12) | TN | 79.60 | $314.32 | $361.00 | $374.00 | $254.00 | $330.86 | $456.10 |
| 0175 | Inlets, DT bot, type C,jbot, <10' (0425-1523) | EACH | 2 | $10,987 | $25,840 | $10,844 | $28,000 | $15,000 | $15,476 |
| 0180 | Pipe culvert, opt material, round, 36"S/CD (0430-175136) | LF | 426 | $254.99 | $251.00 | $374.00 | $305.00 | $316.80 | $308.90 |
| 0185 | Pipe filling and plugging- place out of service (0430-830) | CY | 0.70 | $2,115.73 | $5,704.00 | $2,000.00 | $2,000.00 | $1,800.00 | $8,059.90 |
| 0190 | Mitered end section, optional round, 36" CD (0430-982138) | EACH | 2 | $7,009.50 | $2,729.00 | $3,750.00 | $4,500.00 | $9,840.00 | $2,878.40 |
| 0195 | Concrete curb & gutter, type F (0520-1-10) | LF | 8 | $110.33 | $118.00 | $52.00 | $225.00 | $150.00 | $98.60 |
| 0200 | Shoulder gutter- concrete (0520-6) | LF | 17 | $52.03 | $114.00 | $75.00 | $225.00 | $180.00 | $104.50 |
| 0205 | Shoulder concrete barrier, 38" or 44" height (0521-72-40) | LF | 91 | $465.13 | $682.00 | $1,100.00 | $950.00 | $564.00 | $1,267.10 |
| 0210 | Concrete ditch pavement, non reinforced, 6" (0524-1-4) | SY | 20 | $234.91 | $238.00 | $15.00 | $175.00 | $177.60 | $210.20 |
| 0215 | Concrete ditch pavement, 6", reinforced (0524-1-49) | SY | 29 | $106.80 | $239.00 | $190.00 | $200.00 | $240.00 | $231.60 |
| 0220 | Guardrail removal (0536-73) | LF | 220 | $3.73 | $21.00 | $3.00 | $50.00 | $13.72 | $23.00 |
| 0225 | Performance turf, sod (0570-1-2) | SY | 553 | $8.36 | $4.00 | $7.00 | $3.10 | $9.84 | $10.80 |
| 0230 | Single column ground sign assembly, relocate (0700-1500) | EACH | 1 | $1,586.80 | $554.00 | $180.00 | $155.50 | $405.60 | $597.00 |
| 0235 | Raised pavement marker, type B (0706-1-3) | EACH | 14 | $10.58 | $12.00 | $6.00 | $5.25 | $6.90 | $10.00 |
| 0240 | Painted pavement markings, surface (0710-90) | LS | 1 | $3,171.48 | $3,500.00 | $3,000.00 | $2,590.00 | $2,220.00 | $6,632.90 |
| 0245 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 56 | $7.41 | $8.00 | $6.00 | $5.25 | $4.00 | $6.00 |
| 0250 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.05 | $7,933.99 | $8,500.00 | $7,300.00 | $5,825.00 | $6,594.00 | $8,106.90 |
| 0255 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.07 | $7,933.99 | $8,500.00 | $7,300.00 | $6,291.00 | $6,594.00 | $12,508 |
| 0260 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.03 | $52,893 | $55,600 | $180,000 | $124,350 | $101,700 | $71,186 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of September 30, 2026. Compiled by Mirage Metrics.