FDOT contract T1944 bid tabulation

HOMESTEAD AVE OVER MARSH CREEK, BRIDGE NO 074026. Let by Florida DOT on September 30, 2026, Hendry, District 1. 8 bids received; low bid $1,043,588 by Zep Construction, Inc..

Owner
Florida DOT
Letting
30 SEP 2026
Pay items
52
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Zep Construction, Inc.$1,043,588Low
2Timmons Contracting DBA Lovin Construction$1,572,671+51%
3Thomas Marine Construction, Inc.$1,590,462+52%
4Manhattan Road & Bridge Company$1,673,096+60%
5General Asphalt Company, LLC$1,792,844+72%
6Ferreira Construction Co., Inc.$1,798,675+72%
7Posillico Civil, Inc.$1,886,953+81%
8RJ Gorman Contracting LLC$1,895,597+82%
FDOT contract T1944: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Zep Construction, Inc.2. Timmons Contracting DBA Lovin Construction3. Thomas Marine Construction, Inc.4. Manhattan Road & Bridge Company5. General Asphalt Company, LLC6. Ferreira Construction Co., Inc.
0005Conc class II, bridge superstructure (0400-2-4)CY84.50$1,284.98$1,863.00$1,220.00$2,200.00$2,280.43$1,725.00
0010Concrete class II, approach slabs (0400-2-10)CY45$642.40$1,354.00$1,274.00$1,200.00$1,080.91$750.00
0015Concrete class IV, bridge substructure (0400-4-5)CY33.50$1,560.28$2,013.00$2,920.00$3,500.00$3,214.03$2,725.00
0020Bridge deck grooving (0400-7-1)SY186$40.61$43.00$54.00$40.00$26.00$83.20
0025Plain neoprene bearing pads (0400-148)CF2.70$2,695.07$2,400.00$2,500.00$5,000.00$3,130.40$4,482.00
0030Reinforcing steel - bridge superstructure (0415-1-4)LB25,042$1.04$1.50$2.00$1.75$2.60$2.00
0035Reinforcing steel- bridge substructure (0415-1-5)LB7,037$1.13$1.50$2.00$2.25$2.60$2.80
0040Reinforcing steel- approach slabs (0415-1-9)LB10,568$1.13$1.50$2.00$1.75$2.60$1.90
0045Pile inspection, driven pile (0455-20-1)EACH10$401.99$1,200.00$750.00$3,500.00$845.00$1,150.00
0050Prestressed concrete piling, SQ (0455-34-3)LF484$125.94$257.00$281.00$140.00$309.40$490.00
0055Pile redrive (0455-115)EACH3$1,349.86$2,000.00$300.00$1,500.00$2,340.00$1,425.00
0060Load test (dynamic), data collection and analysis (0455-137)EACH11$1,121.34$2,150.00$150.00$575.00$2,080.00$2,532.50
0065Load test (dynamic), test (0455-137-2)EACH3$540.03$2,150.00$200.00$605.00$2,184.00$994.90
0070Test piles-prestressed concrete,18" SQ (0455-143-3)LF154$162.81$608.00$300.00$650.00$492.31$725.00
0075Bridge deck expansion joint, construction, F&I poured joint with backer rod (0458-1-11)LF56$43.68$79.00$25.00$225.00$97.50$73.60
0080Concrete traffic railing- 36" single-slope (0521-5-13)LF203$125.22$229.00$450.00$350.00$257.89$525.00
0085Riprap, sand-cement bags (0530-1100)CY19.30$914.19$1,803.00$700.00$2,250.00$1,560.00$1,607.20
0090Riprap, rubble, F&I, ditch lining (0530-3-4)TN354.90$94.30$193.00$145.00$155.00$198.00$265.00
0095Bedding stone (0530-74)TN255$76.29$199.00$141.00$225.00$165.60$240.00
0100Mobilization (0101-1)LS1$177,323$149,907$238,170$163,710$100,000$177,450
0105Maintenance of traffic (0102-1)DA1$2,089.28$30,761$37,000$15,000$260,000$8,166.20
0110Work zone sign (0102-60)ED5,700$0.31$0.28$0.40$0.35$0.35$0.40
0115Portable changeable message sign, temporary (0102-99)ED2,428$10.58$11.00$12.00$11.15$12.00$14.20
0120Type III barricade (0102-115)ED1,500$0.53$0.60$0.60$0.60$0.60$0.70
0125Sediment barrier (0104-10-3)LF122$3.42$12.00$3.00$15.00$3.36$4.50
0130Floating turbidity barrier (0104-11)LF481$9.95$13.25$16.00$10.00$24.00$15.20
0135Staked turbidity barrier- nylon reinforced PVC (0104-12)LF44$11.88$44.00$6.25$35.00$27.60$15.50
0140Inlet protection system (0104-18)EACH6$156.61$330.00$190.00$500.00$204.00$191.40
0145Clearing & grubbing (0110-1-1)ACRE1$6,629.27$54,530$41,500$15,000$22,200$38,000
0150Regular excavation (0120-1)CY1,059.80$31.39$36.00$20.00$60.00$32.40$20.50
0155Embankment (0120-6)CY703.90$26.55$56.00$49.00$55.00$31.20$12.50
0160Type B stabilization (0160-4)SY1,059$28.74$46.00$37.00$45.00$13.20$28.10
0165Optional base, base group 03 (0285-703)SY951$49.58$50.00$52.00$41.50$59.71$27.10
0170Superpave asphaltic conc, traffic B (0334-1-12)TN79.60$314.32$361.00$374.00$254.00$330.86$456.10
0175Inlets, DT bot, type C,jbot, <10' (0425-1523)EACH2$10,987$25,840$10,844$28,000$15,000$15,476
0180Pipe culvert, opt material, round, 36"S/CD (0430-175136)LF426$254.99$251.00$374.00$305.00$316.80$308.90
0185Pipe filling and plugging- place out of service (0430-830)CY0.70$2,115.73$5,704.00$2,000.00$2,000.00$1,800.00$8,059.90
0190Mitered end section, optional round, 36" CD (0430-982138)EACH2$7,009.50$2,729.00$3,750.00$4,500.00$9,840.00$2,878.40
0195Concrete curb & gutter, type F (0520-1-10)LF8$110.33$118.00$52.00$225.00$150.00$98.60
0200Shoulder gutter- concrete (0520-6)LF17$52.03$114.00$75.00$225.00$180.00$104.50
0205Shoulder concrete barrier, 38" or 44" height (0521-72-40)LF91$465.13$682.00$1,100.00$950.00$564.00$1,267.10
0210Concrete ditch pavement, non reinforced, 6" (0524-1-4)SY20$234.91$238.00$15.00$175.00$177.60$210.20
0215Concrete ditch pavement, 6", reinforced (0524-1-49)SY29$106.80$239.00$190.00$200.00$240.00$231.60
0220Guardrail removal (0536-73)LF220$3.73$21.00$3.00$50.00$13.72$23.00
0225Performance turf, sod (0570-1-2)SY553$8.36$4.00$7.00$3.10$9.84$10.80
0230Single column ground sign assembly, relocate (0700-1500)EACH1$1,586.80$554.00$180.00$155.50$405.60$597.00
0235Raised pavement marker, type B (0706-1-3)EACH14$10.58$12.00$6.00$5.25$6.90$10.00
0240Painted pavement markings, surface (0710-90)LS1$3,171.48$3,500.00$3,000.00$2,590.00$2,220.00$6,632.90
0245Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF56$7.41$8.00$6.00$5.25$4.00$6.00
0250Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM0.05$7,933.99$8,500.00$7,300.00$5,825.00$6,594.00$8,106.90
0255Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM0.07$7,933.99$8,500.00$7,300.00$6,291.00$6,594.00$12,508
0260Permanent tape, yellow, solid, for concrete bridges (0713-103201)GM0.03$52,893$55,600$180,000$124,350$101,700$71,186
FDOT contract T1944: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of September 30, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way