FDOT contract T2A70 bid tabulation

SR 121 FROM SR 55 (US 19) TO SR 45 (US 41 / SW 7TH ST). Let by Florida DOT on March 25, 2026, Levy, District 2. 5 bids received; low bid $10,660,305 by Anderson Columbia Co., Inc..

Owner
Florida DOT
Letting
25 MAR 2026
Pay items
65
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Anderson Columbia Co., Inc.$10,660,305Low
2C.W. Roberts Contracting, Inc.$11,298,091+6.0%
3Preferred Materials Inc.$11,904,651+12%
4Whitehurst, V. E. & Sons, Inc.$12,217,757+15%
5Superior Asphalt, Inc.$12,341,001+16%
FDOT contract T2A70: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Anderson Columbia Co., Inc.2. C.W. Roberts Contracting, Inc.3. Preferred Materials Inc.4. Whitehurst, V. E. & Sons, Inc.5. Superior Asphalt, Inc.
0005Mobilization (0101-1)LS1$691,737$710,000$299,802$636,685$348,026
0010Maintenance of traffic (0102-1)DA1$415,145$545,000$559,051$346,834$372,500
0015Traffic control officer (0102-14)HR80$115.13$100.00$100.00$125.00$100.00
0020Work zone sign (0102-60)ED25,960$0.29$0.25$0.25$0.22$0.20
0025Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED45,216$0.06$0.05$0.05$0.11$0.10
0030Temporary raised/retroreflective pavement marker, type D (0102-78-1)EACH4,493$4.89$4.50$5.15$4.57$4.45
0035Portable changeable message sign, temporary (0102-99)ED1,524$11.51$10.50$10.00$10.75$9.45
0040Temporary signalization and maintenance, intersection (0102-104)ED240$38.41$33.00$18.55$1.00$26.25
0045Temporary traffic detection and maintenance, intersection (0102-107-1)ED240$22.75$33.00$17.38$1.00$26.25
0050Type III barricade (0102-115)ED40$0.26$0.25$0.23$0.27$0.25
0055Temporary raised rumble per day, includes all sets and relocations (0102-909)DA45$28.78$26.50$200.00$53.75$12.35
0060Artificial coverings /rolled erosion control products (0104-1)SY829$1.15$13.00$7.03$25.00$2.10
0065Sediment barrier (0104-10-3)LF22,604$2.58$0.01$1.10$1.75$1.20
0070Litter removal (0107-1)ACRE1,438.70$50.00$42.00$47.50$107.50$47.25
0075Mowing (0107-2)ACRE1,244.30$50.00$68.00$62.28$161.25$68.25
0080Clearing & grubbing (0110-1-1)ACRE1$81,194$167,179$50,488$21,500$203,000
0085Removal of existing concrete (0110-4-10)SY330$40.70$28.00$60.55$65.00$34.65
0090Regular excavation (0120-1)CY1,269.30$63.97$49.25$24.23$15.00$41.15
0095Embankment (0120-6)CY361.30$168.55$37.25$58.84$20.00$75.00
0100Optional base, base group 01 (0285-701)SY8,024$8.51$11.50$9.72$20.00$19.95
0105Optional base, base group 02 (0285-702)SY89$105.54$73.50$95.99$35.00$19.95
0110Milling existing asphalt pavement, 1" avg depth (0327-70-1)SY47,088$1.92$2.50$3.79$1.77$3.55
0115Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2)SY4,123$4.93$3.50$6.34$3.67$4.25
0120Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY227,212$1.71$2.25$1.73$2.16$2.85
0125Milling existing asphalt pavement, 2 1/2" avg depth (0327-70-8)SY136,988$1.74$2.20$2.39$2.94$3.00
0130Milling existing asphalt pavement, 1 1/4" avg depth (0327-70-12)SY1,749$5.57$9.50$11.06$1.97$5.95
0135Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53)TN11,775.20$134.66$122.00$164.00$157.00$157.25
0140Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN40,689.20$132.09$139.00$158.15$157.00$162.30
0145Valve boxes, adjust (0425-6)EACH1$1,151.35$850.00$2,187.25$2,352.00$1,915.00
0150Mitered end section, optional round, 18" SD (0430-984125)EACH5$1,863.33$2,865.00$3,113.25$2,580.00$2,485.00
0155Pipe liner, cured in place, 24" (0431-1124)LF63$320.53$310.00$300.00$300.00$365.00
0160Riprap, rubble, F&I, ditch lining (0530-3-4)TN23.60$250.16$255.00$440.00$473.50$310.00
0165Bedding stone (0530-74)TN16.90$250.16$275.00$432.62$465.00$175.00
0170Performance turf, sod (0570-1-2)SY82,905$3.45$4.80$3.44$2.60$2.50
0175Raised pavement marker, type B (0706-1-3)EACH4,472$4.89$4.50$5.15$4.60$4.50
0180Painted pavement markings, standard, white, solid, 6" (0710-11101)GM40.65$2,127.67$1,950.00$2,149.52$1,987.00$1,940.00
0185Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF1,461$2.30$2.10$3.00$2.15$2.10
0190Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM1.46$921.07$820.00$795.07$8.60$840.00
0195Painted pavement markings, standard, white, message or symbol (0710-11160)EACH54$86.34$78.00$95.00$80.65$78.75
0200Painted pavement markings, standard, white, arrows (0710-11170)EACH19$57.57$50.00$55.00$53.75$52.50
0205Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM21.67$2,127.67$1,950.00$2,150.00$1,987.00$1,940.00
0210Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224)LF506$1.73$1.55$3.00$1.61$1.60
0215Painted pavement markings, standard, yellow, skip, 6" (0710-11231)GM12.37$921.07$830.00$474.73$860.00$840.00
0220Initial contingency amount, DO not bid (0999-25)LS1$133,894$133,894$133,894$133,894$133,894
0225Raised rumble strip set- permanent (0546-71-1)EACH4$1,381.60$525.00$1,200.00$537.50$525.00
0230Ground-in rumble strips, 8" sinusoidal (0546-72-3)GM57.60$1,788.09$1,450.00$2,297.76$2,003.00$1,020.00
0235Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH38$518.11$475.00$450.00$537.50$525.00
0240Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH1$2,187.55$2,000.00$1,900.00$1,827.50$1,785.00
0245Single column ground sign assembly, relocate (0700-1500)EACH2$57.57$52.00$50.00$53.75$52.50
0250Single column ground sign assembly, remove (0700-1600)EACH23$28.78$26.00$25.00$53.75$52.50
0255Multi-column ground sign assembly, F&I ground mount, 30.0 SF (0700-2113)EACH1$7,483.69$6,800.00$6,500.00$5,805.00$5,670.00
0260Multi-column ground sign assembly, remove (0700-2600)EACH1$310.86$285.00$270.00$752.50$735.00
0265Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH4$172.70$158.00$150.00$161.25$160.00
0270Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH32$74.84$68.00$65.00$96.75$95.00
0275Object marker, type 1 (0705-10-1)EACH3$287.84$264.00$250.00$135.00$130.00
0280Raised pavement marker, type B (0706-1-3)EACH4,472$4.89$4.50$5.15$4.60$4.50
0285Painted pavement markings, surface (0710-90)LS1$161,666$145,000$178,000$150,947$150,000
0290Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF1,461$7.77$8.40$6.75$8.60$8.40
0295Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM1.46$2,993.48$1,470.00$2,583.96$1,505.00$1,470.00
0300Thermoplastic, standard, message or symbol (0711-11160)EACH54$172.70$200.00$150.00$204.25$200.00
0305Thermoplastic, standard, arrow (0711-11170)EACH19$115.13$103.00$100.00$107.50$105.00
0310Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF506$6.33$4.75$5.50$4.84$4.75
0315Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM40.65$4,029.68$5,500.00$3,499.23$5,676.00$5,550.00
0320Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM21.67$4,029.68$5,500.00$3,500.00$5,676.00$5,550.00
0325Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231)GM12.37$1,381.60$1,475.00$1,199.32$1,505.00$1,470.00
FDOT contract T2A70: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of March 25, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way